Content | Date | Cost | Contractor Rank | Address | Contractor |
---|---|---|---|---|---|
Electrical permit Date: January 29, 2008 Client: Septa | Client Company: Gerard Maier Dir Of R E | Permit status: Completed | Permit id: 125000 | |||||
Alteration permit Date: September 23, 2016 Client: Septa | Client Company: Gerard Maier Dir Of R E | Permit status: Active | Permit id: 723370 | |||||
Alteration permit Date: March 11, 2008 Client: Septa | Client Company: Gerard Maier Dir Of R E | Permit status: Completed | Permit id: 135420 | |||||
Mechanical permit Date: September 23, 2016 Client: Septa | Client Company: Gerard Maier Dir Of R E | Permit status: Active | Permit id: 716458 | |||||
Alteration permit Date: March 11, 2008 Client: Septa | Client Company: Gerard Maier Dir Of R E | Permit status: Completed | Permit id: 135420 | |||||
Electrical permit Date: December 19, 2016 Client: Septa | Client Company: Gerard Maier Dir Of R E | Permit status: Active | Permit id: 731135 | |||||
Mechanical permit Date: September 23, 2016 Client: Septa | Client Company: Gerard Maier Dir Of R E | Permit status: Active | Permit id: 716458 | |||||
Electrical permit Date: January 29, 2008 Client: Septa | Client Company: Gerard Maier Dir Of R E | Permit status: Completed | Permit id: 125000 | |||||
Alteration permit Date: September 23, 2016 Client: Septa | Client Company: Gerard Maier Dir Of R E | Permit status: Active | Permit id: 723370 | |||||
SCORE 100 For the installation of five (5) roof-mounted makeup air units and exhaust fans, the removal of existing boiler, and for the installation of new infrared ceiling-mounted heaters. Permit is also for the installation of any new registers diffusers, or supplemental ductwork as shown in approved plans. Date: September 23, 2016 Contractor: Dwd Mechanical Contractor Inc Client: Septa | Client Company: Gerard Maier Dir Of R E | Permit type: Mechanical permit | Permit status: Completed | Completion date: November 6, 2017 | Permit id: 716458 | |||||
SCORE 100 Install breaker to feed transformer & new panel, disconnect 28 exhaust fans and reconnect replacing 21 starters. Wire 3 sets of new louvers and co2, control panel. Install 18 new floor top recepts as per 2005 nec (north district) Date: January 29, 2008 Contractor: Hyde Electric Corp Client: Septa | Client Company: Gerard Maier Dir Of R E | Permit type: Electrical permit | Permit status: Completed | Completion date: September 12, 2008 | Permit id: 125000 | |||||
SCORE 82 Remove roofing membrane and replace with 5 ply modified bituminous, built up system. Install new pre-fab roof curbs. Existing metal deck to remain. Rooftop units to be removed and reinstalled Date: March 11, 2008 Contractor: Plato Construction Corp Client: Septa | Client Company: Gerard Maier Dir Of R E | Permit type: Alteration permit | Permit status: Completed | Completion date: June 12, 2014 | Permit id: 135420 | |||||
SCORE 100 For structural modications to existing roof system to provide support for new mechanical appliances as approved under permit #716458. Date: September 23, 2016 Contractor: Dwd Mechanical Contractor Inc Client: Septa | Client Company: Gerard Maier Dir Of R E | Permit type: Alteration permit | Permit status: Completed | Completion date: May 4, 2017 | Permit id: 723370 | |||||
SCORE 100 Install 5 roof mount mua units, 21 new ceiling mount infrared heaters,new panels and transformers and new exhaust fans per 2008 nec (bus garage )north district Date: December 19, 2016 Contractor: Goldhorn Elect Construction Co Client: Septa | Client Company: Gerard Maier Dir Of R E | Permit type: Electrical permit | Permit status: Completed | Completion date: July 25, 2017 | Permit id: 731135 |