Content | Date | Cost | Contractor Rank | Address | Contractor |
---|---|---|---|---|---|
SCORE 98 Construction of the boulder regional fire training center -- three buildings consisting of an administrative center of 17,846, a burn building of 3. 343 sf and a training tower of 6,438 sf. Client: Of City | Applicant: Ap Mountain States Llc | Permit type: Building, electrical | Permit status: Co | Current use: Government uses | |||||
SCORE 100 Placement & installation of a construction trailer of the (brftc) (boulder regional fire training center)(adolfson & peterson mountain states)(ap mountain states) Date: June 11, 2009 Contractor: Of City Client: Of City | Applicant: Of City | Permit type: Temporary event | Permit status: Iss | |||||
SCORE 86 Installing water & sewer mains & services to the new fire training facility Date: September 9, 2009 Contractor: Diamond Excavating Inc Client: Of City | Applicant: Diamond Excavating, Inc | Permit type: Right-of-way | Permit status: Iss | |||||
SCORE 98 New sprinkler system for boulder fire training center Date: September 18, 2009 Contractor: Allstate Fire Protection Inc Client: Of City | Applicant: All-State Fire Protection, Inc | Permit type: Fire | Permit status: Cmp | Completion date: February 2, 2011 | Current use: Service industr | |||||
SCORE 95 New fire alarm system for boulder fire training grounds Date: September 23, 2009 Contractor: Accent Electrical Services Corp Client: Of City | Applicant: Accent Electrical Services Corp | Permit type: Fire | Permit status: Iss | Current use: Office - profes | |||||
SCORE 86 Install 1560foot of 8inch main Date: October 13, 2009 Contractor: Diamond Excavating Inc Client: Of City | Applicant: Diamond Excavating, Inc | Permit type: Right-of-way | Permit status: Iss | |||||
SCORE 100 Bore 280foot across road to install new electrical & trench 2753foot in easement Date: November 12, 2009 Contractor: Xcel Energy Client: Of City | Applicant: Xcel Energy | Permit type: Right-of-way | Permit status: N&v | |||||
SCORE 100 Bore from spine rd [in front of 60 spine] west under the railroad tracks & highway 119 to the fire training center Date: November 30, 2009 Contractor: Xcel Energy Client: Of City | Applicant: Xcel Energy | Permit type: Right-of-way | Permit status: Iss | |||||
SCORE 100 New radio dial for boulder county fire training facility Date: October 12, 2010 Contractor: Safe Systems Inc Client: Of City | Applicant: Safe Systems, Inc. | Permit type: Fire | Permit status: Cmp | Completion date: February 2, 2011 | Current use: Government uses | |||||
SCORE 95 Electrical work associated wtih relocation of fuel dispenser at boulder reservoir boat house. Date: January 13, 2011 Contractor: B And T Electric Inc Client: Of City | Applicant: B & T Electric Inc | Permit type: Electrical | Permit status: N&v | Current use: Government uses | |||||
SCORE 100 Mechanical permit - for relocation of existing underground gas piping ( ft) at fire training center. Date: April 5, 2011 Contractor: Gary Smith Plumbing And Heating Client: Of City | Applicant: Gary Smith Plumbing & Heating | Permit type: Mechanical | Permit status: Cmp | Completion date: May 20, 2014 | Current use: Government uses | |||||
SCORE 95 Installation of new generator at boulder fire training center, see adr2011-00064 for minor modification approval. Date: July 18, 2011 Contractor: Accent Electrical Services Corp Client: Of City | Applicant: Accent Electrical Services Corp | Permit type: Electrical | Permit status: Cmp | Completion date: March 13, 2012 | Current use: Government uses | |||||
SCORE 88 Utility installation for the boulder wildland fire to include fireline, irrigation service meter, water service meter, sanitary sewer service, fire hydrant, associated with building pmt2014-00330 Date: May 2, 2014 Contractor: Lens Excavating Inc Client: Of City | Applicant: Lens Excavating, Inc | Permit type: Right-of-way | Permit status: Iss | |||||
SCORE 100 Fs - new 13 system for boulder wildland fs Date: September 15, 2014 Contractor: Freedom Fire Protection Llc Client: Of City | Applicant: Freedom Fire Protection, Llc | Permit type: Fire | Permit status: Cmp | Completion date: July 16, 2015 | Current use: Government uses | |||||
SCORE 98 Construction of the boulder regional fire training center -- three buildings consisting of an administrative center of 17,846, a burn building of 3. 343 sf and a training tower of 6,438 sf. Client: Of City | Permit type: Building, electrical, mechanical, plumbing, water, wastewater, grading, sitework | Permit status: Co | Current use: Government uses, new, shed, new | Permit id: Pmt2009-00914 | |||||
Placement & installation of a construction trailer of the (brftc) (boulder regional fire training center)(adolfson & peterson mountain states)(ap mountain states) Client: Of City | Permit type: Temporary event | Permit status: Iss | Permit id: Pmt2009-02124 | |||||
SCORE 91 Installing water & sewer mains & services to the new fire training facility Date: September 9, 2009 Contractor: Diamond Excavating, Inc Client: Of City | Permit type: Right-of-way | Permit status: Iss | Permit id: Pmt2009-03494 | |||||
SCORE 98 New sprinkler system for boulder fire training center Client: Of City | Permit type: Fire | Permit status: Cmp | Completion date: February 2, 2011 | Current use: Service industrial, existing | Permit id: Pmt2009-03730 | |||||
SCORE 95 New fire alarm system for boulder fire training grounds Client: Of City | Permit type: Fire | Permit status: Iss | Current use: Office - professional, existing | Permit id: Pmt2009-03765 | |||||
SCORE 91 Install 1560foot of 8inch main Date: October 13, 2009 Contractor: Diamond Excavating, Inc Client: Of City | Permit type: Right-of-way | Permit status: Iss | Permit id: Pmt2009-04112 | |||||
Bore 280foot across road to install new electrical & trench 2753foot in easement Client: Of City | Permit type: Right-of-way | Permit status: N&v | Permit id: Pmt2009-04630 | |||||
Bore from spine rd [in front of 60 spine] west under the railroad tracks & highway 119 to the fire training center Date: November 30, 2009 Client: Of City | Permit type: Right-of-way | Permit status: Iss | Permit id: Pmt2009-04688 | |||||
SCORE 88 Utility installation for the boulder wildland fire to include fireline, irrigation service meter, water service meter, sanitary sewer service, fire hydrant, associated with building pmt2014-00330 Date: May 2, 2014 Contractor: Lens Excavating, Inc Client: Of City | Permit type: Right-of-way | Permit status: Iss | Permit id: Pmt2014-01892 | |||||
SCORE 95 Fs - new 13 system for boulder wildland fs Client: Of City | Permit type: Fire | Permit status: Cmp | Completion date: July 16, 2015 | Current use: Government uses, existing | Permit id: Pmt2014-04260 | |||||
SCORE 95 New radio dial for boulder county fire training facility Client: Of City | Permit type: Fire | Permit status: Cmp | Completion date: February 2, 2011 | Current use: Government uses, existing | Permit id: Pmt2010-04363 | |||||
SCORE 95 Electrical work associated wtih relocation of fuel dispenser at boulder reservoir boat house. Client: Of City | Permit type: Electrical | Permit status: N&v | Current use: Government uses, existing | Permit id: Pmt2011-00179 | |||||
SCORE 100 Mechanical permit - for relocation of existing underground gas piping ( ft) at fire training center. Client: Of City | Permit type: Mechanical | Permit status: Cmp | Completion date: May 20, 2014 | Current use: Government uses, existing | Permit id: Pmt2011-01315 | |||||
SCORE 95 Installation of new generator at boulder fire training center, see adr2011-00064 for minor modification approval. Client: Of City | Permit type: Electrical | Permit status: Cmp | Completion date: March 13, 2012 | Current use: Government uses, existing | Permit id: Pmt2011-02846 | |||||
SCORE 95 Installation of back-up generator on existing exterior pad to power fire station #8. Client: Of City | Permit type: Electrical | Permit status: Cmp | Completion date: December 16, 2015 | Current use: Government uses, existing | Permit id: Pmt2015-04594 | |||||
Placement & installation of a construction trailer of the (brftc) (boulder regional fire training center)(adolfson & peterson mountain states)(ap mountain states) Client: Of City | Permit type: Temporary event | Permit status: Iss | Permit id: Pmt2009-02124 | |||||
Fire training center - construction of a ftc confined space training facility. All steel containers are existing; new scope includes piping and concrete. Value: $404,976 Client: Of City | Permit type: Building | Permit status: Act | Current use: Government uses, new | Permit id: Pmt2017-02335 | |||||
Bore 280foot across road to install new electrical & trench 2753foot in easement Client: Of City | Permit type: Right-of-way | Permit status: N&v | Permit id: Pmt2009-04630 | |||||
Placement & installation of a construction trailer of the (brftc) (boulder regional fire training center)(adolfson & peterson mountain states)(ap mountain states) Client: Of City | Permit type: Temporary event | Permit status: Iss | Permit id: Pmt2009-02124 | |||||
Bore 280foot across road to install new electrical & trench 2753foot in easement Client: Of City | Permit type: Right-of-way | Permit status: N&v | Permit id: Pmt2009-04630 | |||||
SCORE 99 Fire training center - construction of a ftc confined space training facility. All steel containers are existing; new scope includes piping and concrete. Client: Of City | Permit type: Building | Permit status: Iss | Current use: Government uses, new | Permit id: Pmt2017-02335 |