Content | Date | Cost | Contractor Rank | Address | Contractor |
---|---|---|---|---|---|
SCORE 59 Change of use electronic communnication switch station demolition of existing partition walls, ceiling grid system,install temporary walls;temporary switching station. Date: October 31, 2000 Contractor: Peter J.Weiland Iii Client: U.S.A. Inc, 3 Network | Permit id: B00005550 | |||||
SCORE 83 Alteration electronic communnication switch station demolition of existing partition walls. Modification of mechanical & electrical systems,structual reinforcements as per plans. Phase i Date: August 9, 2002 Contractor: Peter J. Weiland Iii Client: U.S.A. Inc, 3 Network | Permit id: B00005553 | |||||
SCORE 62 Alteration electronic communnication switch station demolition of existing partition walls. Modification of mechanical & electrical systems, structural reinforcements as per plans. Phase ii Date: January 18, 2001 Contractor: Peter J Weiland Iii Client: U.S.A. Inc, 3 Network | Permit id: B00005555 | |||||
SCORE 98 New construction project office building new service and branch circuits Date: January 24, 2001 Contractor: Rickey Kastner Client: U.S.A. Inc, 3 Network | Permit id: E01000521 | |||||
SCORE 89 Install mechanical equipment community center install five elec warm air furnace and five ac system (4)-20-ton and (1)-10-ton. Kim guzman - 468-3700 Date: January 19, 2001 Contractor: Bristerstephens Incorporated Client: U.S.A. Inc, 3 Network | Permit id: M01000363 | |||||
SCORE 59 Change of use electronic communnication switch station demolition of existing partition walls, ceiling grid system,install temporary walls;temporary switching station. Date: October 31, 2000 Contractor: Peter J.Weiland Iii Client: U.S.A. Inc, 3 Network | Permit id: B00005550 | |||||
SCORE 83 Alteration electronic communnication switch station demolition of existing partition walls. Modification of mechanical & electrical systems,structual reinforcements as per plans. Phase i Date: October 31, 2000 Contractor: Peter J. Weiland Iii Client: U.S.A. Inc, 3 Network | Permit id: B00005553 | |||||
SCORE 62 Alteration electronic communnication switch station demolition of existing partition walls. Modification of mechanical & electrical systems, structural reinforcements as per plans. Phase ii Date: October 31, 2000 Contractor: Peter J Weiland Iii Client: U.S.A. Inc, 3 Network | Permit id: B00005555 | |||||
SCORE 98 New construction project office building new service and branch circuits Date: January 24, 2001 Contractor: Rickey Kastner Client: U.S.A. Inc, 3 Network | Permit id: E01000521 | |||||
Install mechanical equipment community center install five elec warm air furnace and five a c system (4)-20-ton and (1)-10-ton. Kim guzman - 468-3700 Date: January 19, 2001 Client: U.S.A. Inc, 3 Network | Permit id: M01000363 | |||||
SCORE 56 Change of use electronic communnication switch station demolition of existing partition walls, ceiling grid system,install temporary walls;temporary switching station. Date: October 31, 2000 Contractor: Peter J.Weiland,Iii Client: U.S.A. Inc, 3 Network | Permit id: B00005550 | |||||
SCORE 89 Install mechanical equipment community center install five elec warm air furnace and five a c system (4)-20-ton and (1)-10-ton. Kim guzman - 468-3700 Date: January 19, 2001 Contractor: Bristerstephens Incorporated Client: U.S.A. Inc, 3 Network | Permit id: M01000363 |