Content | Date | Cost | Contractor Rank | Address | Contractor |
---|---|---|---|---|---|
SCORE 59 Temp power for construction Date: November 16, 2010 Permit type: Electrical | Permit status: Pass | Completion date: October 13, 2011 | Current use: Commercial | Permit id: Bld2010-07943 | |||||
SCORE 64 New stub into bldg test & flush, p-1 level on west side. Date: July 23, 2009 Permit type: Fire | Permit status: Completed | Completion date: March 14, 2012 | Current use: Commercial | Permit id: Bld2009-04322 | |||||
SCORE 64 Structural steel only for nordstrom on block 76. Issued 6 24: larry lincoln-the contractor has submitted structural plans to erect (2) bays of structural steel prior to the removal of the track crane located on the parking deck. The use of this crane to set this steel in this specific location is needed due to the limted reach of subsequent cranes when this track crane is removed. The contractor proceeds at his own risk due to the incompleteness of the architectual plans submitted. Ken brown-proposal involves erection of two (2) bays of structural steel prior to the removal of the track crane. Contractor proceeding at his own risk regarding the 40% glass requirement public way encroachments, etc. Impact fees will be collected at the core and shell stage. Chris kimball-approved. Date: May 27, 2009 Permit status: Pass | Completion date: February 17, 2012 | Current use: Commercial | Permit id: Bld2009-03080 | |||||
SCORE 64 New stub into bldg test & flush, p-1 level on south side. Date: July 23, 2009 Permit type: Fire | Permit status: Completed | Completion date: March 14, 2012 | Current use: Commercial | Permit id: Bld2009-04323 | |||||
Temp power for construction Date: November 16, 2010 Permit type: Electrical | Permit status: Pass | Completion date: October 13, 2011 | Current use: Commercial | Permit id: Bld2010-07943 | |||||
SCORE 64 Restaurant d. D. A. H. D. W. Date: June 13, 2011 Permit status: Cert occ no warranty | Completion date: March 14, 2012 | Current use: Commercial | Permit id: Bld2011-03392 | |||||
SCORE 59 Interior tenant improvement, mech, elec & plmbg permits reqd k. A. A. H. D. W. Date: June 13, 2011 Contractor: Plant Construction Company Lpnordstrom Ebar Permit status: Pass | Completion date: February 17, 2012 | Current use: Commercial | Permit id: Bld2011-03391 | |||||
SCORE 64 Nordstrom tenant improvement. Date: April 8, 2011 Permit status: Pass | Completion date: February 28, 2012 | Current use: Commercial | Permit id: Bld2011-02029 | |||||
SCORE 59 Electrical permit required. A. H. One wall sign one entrance sign Date: February 17, 2012 Contractor: Yesco Llcebar Space #180 Permit type: Sign | Permit status: In progress | Completion date: February 17, 2012 | Permit id: Bld2012-01388 | |||||
SCORE 77 1 marque sign k. B. Date: January 23, 2012 Contractor: Yesco Llcnordstrom Permit type: Sign | Permit status: Accepted - standard | Completion date: January 23, 2012 | Permit id: Bld2012-00570 | |||||
SCORE 64 Low voltage fire alarm. Date: July 7, 2011 Permit type: Low voltage | Permit status: Completed | Completion date: March 14, 2012 | Current use: Commercial | Permit id: Bld2011-04161 | |||||
SCORE 64 6 furnaces, ductwork over 1,000, 15 exhaust fans, 4 hoods, 16 appliances, 12 ac units. Date: July 27, 2011 Contractor: Psf Mechanical Incnordstrom Permit type: Mechanical | Permit status: No certificate req | Completion date: March 14, 2012 | Current use: Commercial | Permit id: Bld2011-04636 | |||||
SCORE 76 Electrical for tenant improvement for restaurant. Date: February 9, 2010 Permit type: Electrical | Permit status: Pass | Completion date: May 18, 2010 | Current use: Commercial | Permit id: Bld2010-00659 | |||||
SCORE 59 Install 36 fixtures, 1 water heater, 1 water softener, 1 dist piping, 1 waterline, 18 drains, 4 hose bibbs, 2 backflow preventers, 1 sump pump Date: July 29, 2011 Permit type: Plumbing | Permit status: Completed | Completion date: March 14, 2012 | Current use: Commercial | Permit id: Bld2011-04699 | |||||
SCORE 64 Connecting to existing pump. Date: July 14, 2011 Contractor: Western Automatic Sprinkler Innordstrom Permit type: Fire | Permit status: Completed | Completion date: March 14, 2012 | Current use: Commercial | Permit id: Bld2011-04324 | |||||
SCORE 64 1 rtu, 3 fit boxs, 3 hoods, 4 exhuast fans and duct. 1 transfer fan Date: September 22, 2011 Contractor: Psf Mechanical Inc.Nordstrom 6th And Pine Cafe Permit type: Mechanical | Permit status: No certificate req | Completion date: March 14, 2012 | Current use: Commercial | Permit id: Bld2011-06098 | |||||
SCORE 59 1 exhaust fan, 4 appliances, 2 heatpumps and assoc duct Date: September 22, 2011 Contractor: Psf Mechanical Inc.Nordstrom Ebar Permit type: Mechanical | Permit status: No certificate req | Completion date: March 14, 2012 | Current use: Commercial | Permit id: Bld2011-06101 | |||||
SCORE 64 Power to panel permit pending power to panel agreement and payment of balance due. Date: October 13, 2011 Contractor: Dynalectric Companynordstrom 6th And Pine Cafe Permit type: Electrical | Permit status: Completed | Completion date: March 14, 2012 | Current use: Commercial | Permit id: Bld2011-06626 | |||||
SCORE 64 This is a tenant finish inside the nordstrom space. It is a cafe. Piping is sized exactly how the nordstrom space had been previously calculated at. Date: September 29, 2011 Contractor: Western Automatic Sprinkler In6th And Pine Permit type: Fire | Permit status: No certificate req | Completion date: March 14, 2012 | Current use: Commercial | Permit id: Bld2011-06245 | |||||
SCORE 77 6 flat signs a. S. Date: August 26, 2011 Contractor: Yesco Llcnordstrom Permit type: Sign | Permit status: Accepted - standard | Completion date: August 26, 2011 | Permit id: Bld2011-05417 | |||||
SCORE 59 Elec work for tenant improvement. Permit issued to accomidate inspection associated with a concrete pour, actual elec work for the tenant finish may not proceed until building bld2011-03392 is issued. Date: June 14, 2011 Permit type: Electrical | Permit status: No certificate req | Completion date: March 14, 2012 | Current use: Commercial | Permit id: Bld2011-03460 | |||||
SCORE 66 Addition of two kitchen hood systems in nordstrom Date: September 28, 2011 Contractor: Simplexgrinnellnordstrom Kitchen Hoods Permit type: Fire | Permit status: Completed | Completion date: March 14, 2012 | Current use: Commercial | Permit id: Bld2011-06217 | |||||
SCORE 66 Ebar- this is just by the nordstrom space. It is called ebar. We have sent a hydraulic calc in and it feeds off the same nordstrom pump. Date: September 29, 2011 Contractor: Ebar Permit type: Fire | Permit status: Completed | Completion date: March 14, 2012 | Current use: Commercial | Permit id: Bld2011-06246 |