Content | Date | Cost | Contractor Rank | Address | Contractor |
---|---|---|---|---|---|
Plumbing permit Date: September 27, 2011 Client: Newcourtland Properties | Permit status: Completed | Permit id: 365229 | |||||
Demolition permit Date: August 12, 2016 Client: Newcourtland Properties | Permit status: Active | Permit id: 709816 | |||||
Plumbing permit Date: July 21, 2016 Client: Newcourtland Properties | Permit status: Active | Permit id: 709060 | |||||
Zoning/use permit Date: March 24, 2016 Client: Newcourtland Properties | Permit status: Expired | Permit id: 668794 | |||||
Electrical permit Date: August 23, 2016 Client: Newcourtland Properties | Permit status: Active | Permit id: 716728 | |||||
New construction permit Date: September 8, 2016 Client: Newcourtland Properties | Permit status: Active | Permit id: 676253 | |||||
Zoning permit Date: April 25, 2014 Client: Newcourtland Properties | Permit status: Completed | Permit id: 532341 | |||||
Permit for the complete demolition of all structures on the lot for the erection of a detached structuresix/one story structure(maximum height nte 75 feet) with interior accessory parking for fifty seven(57) spaces including three(3) ada spaces,for use as 138 senior housing units with accessory community room, kitchen ,storage and senoir room all for use by residents only.(size and location as shown on the application) Date: December 28, 2015 Client: Newcourtland Properties | Applicant: Peter Kelsen, Esquire | Permit type: Appeal | Permit status: Granted | Permit id: 26700 | |||||
Permit for the complete demolition of all structures on the lot for the erection of a detached structure seven/six/one story structure(maximum height nte 82. 5 feet) with interior accessory below grade parking for twenty four(24) vehicles including two(2) ada spaces,for use as 144 senior housing units with accessory community room, kitchen ,storage and senoir room administrative offices all for use by residents only subject to civic design review.(size and location as shown on the application) Date: February 18, 2016 Client: Newcourtland Properties | Applicant: Peter F. Kelsen, Esquire | Permit type: Appeal | Permit status: Granted | Permit id: 27053 | |||||
Electrical permit Date: August 23, 2016 Client: Newcourtland Properties | Permit status: Active | Permit id: 716728 | |||||
Plumbing permit Date: July 21, 2016 Client: Newcourtland Properties | Permit status: Completed | Permit id: 709060 | |||||
New construction permit Date: September 8, 2016 Client: Newcourtland Properties | Permit status: Active | Permit id: 676253 | |||||
Plumbing permit Date: September 27, 2011 Client: Newcourtland Properties | Permit status: Completed | Permit id: 365229 | |||||
Zoning use permit Date: March 24, 2016 Client: Newcourtland Properties | Permit status: Completed | Permit id: 668794 | |||||
Zoning permit Date: April 25, 2014 Client: Newcourtland Properties | Permit status: Completed | Permit id: 532341 | |||||
Demolition permit Date: August 12, 2016 Client: Newcourtland Properties | Permit status: Expired | Permit id: 709816 | |||||
Permit for the complete demolition of all structures on the lot for the erection of a detached structuresix one story structure(maximum height nte 75 feet) with interior accessory parking for fifty seven(57) spaces including three(3) ada spaces,for use as 138 senior housing units with accessory community room, kitchen ,storage and senoir room all for use by residents only.(size and location as shown on the application) Date: December 28, 2015 Client: Newcourtland Properties | Applicant: Peter Kelsen, Esquire | Permit type: Appeal | Permit status: Granted | Permit id: 26700 | |||||
Permit for the complete demolition of all structures on the lot for the erection of a detached structure seven six one story structure(maximum height nte 82. 5 feet) with interior accessory below grade parking for twenty four(24) vehicles including two(2) ada spaces,for use as 144 senior housing units with accessory community room, kitchen ,storage and senoir room administrative offices all for use by residents only subject to civic design review.(size and location as shown on the application) Date: February 18, 2016 Client: Newcourtland Properties | Applicant: Peter F. Kelsen, Esquire | Permit type: Appeal | Permit status: Granted | Permit id: 27053 | |||||
SCORE 100 Installation of (1) 200amp single phase temp. Electrical service of demo of old school house as per 2008 nec (east district) Date: August 23, 2016 Contractor: Amp Tech Systems Llc Client: Newcourtland Properties | Permit type: Electrical permit | Permit status: Expired | Completion date: August 23, 2016 | Permit id: 716728 | |||||
Amend permit number 676253 deleted basement and revised ground floor plan to accomodate mechanical requirements at grade. Revised floor to floor and overall building heights. Date: March 13, 2017 Client: Newcourtland Properties | Permit type: Administrative permit | Permit status: Completed | Completion date: September 22, 2017 | Permit id: 725778 | |||||
SCORE 99 Remove one 3,0 gallon #2 fuel oil tank discovered during construction activities. Date: February 7, 2017 Contractor: Oxford Engineering Company Client: Newcourtland Properties | Permit type: Demolition permit | Permit status: Active | Completion date: July 26, 2017 | Permit id: 757438 | |||||
New construction 6 story structure. No demolition this permit - separate permit required per code bulletin and department regulations. Civil site work approved by others. Separate amended permit is required for special inspectors approval additional permits required : electrical, plumbing,hvac,sprinklers, s. Pipes & signs, demolition. Date: September 8, 2016 Client: Newcourtland Properties | Permit type: New construction permit | Permit status: Active | Completion date: November 7, 2017 | Permit id: 676253 | |||||
SCORE 100 House drain Date: September 27, 2011 Contractor: Herman Goldner Co Inc Client: Newcourtland Properties | Permit type: Plumbing permit | Permit status: Completed | Completion date: September 29, 2011 | Permit id: 365229 | |||||
Relocation of lot lines one one parcel into three new lots. Date: April 25, 2014 Client: Newcourtland Properties | Permit type: Zoning permit | Permit status: Completed | Completion date: April 25, 2014 | Permit id: 532341 | |||||
Demo of all existing buildings. Construction of a one story, two story, six story and seven story story building in three phases to include 144 one bedroom units of senior housing with community room, kitchen, storage, mail room, administrative offices and senior center, 24 accessory parking spaces below grade per plans attached Date: March 24, 2016 Client: Newcourtland Properties | Permit type: Zoning/use permit | Permit status: Completed | Completion date: November 17, 2016 | Permit id: 668794 | |||||
SCORE 100 Building to be demolished. Date: August 12, 2016 Contractor: Haines And Kibblehouse Inc Client: Newcourtland Properties | Permit type: Zoning/use permit | Permit status: Completed | Completion date: November 17, 2016 | Permit id: 709819 | |||||
SCORE 100 Complete demolition of building to 5 below grade using mechanical equipement and as shown on plans. Complete removal of footings & foundation in + -4,0 sf of building, crush & back fill voids. Asbestos removal necessary prior to demolition. Date: August 12, 2016 Contractor: Haines And Kibblehouse Inc Client: Newcourtland Properties | Permit type: Demolition permit | Permit status: Completed | Completion date: February 3, 2017 | Permit id: 709816 | |||||
SCORE 100 Install new 4000amp service 120v 208volts, 42 new 1 amp panels, 11 new receptacles, 592 new light fixtures, 2 new 1 amp roof tops units and 1 new 225 amp roof top unit as per 2008 nec (east district) Date: April 26, 2017 Contractor: Joule Electric Inc Client: New Courtland Life At St Bartholomew Inc | Permit type: Electrical permit | Permit status: Expired | Completion date: April 26, 2017 | Permit id: 755534 | |||||
SCORE 100 New construction:interior & exterior plumbing; 6 story structure;144 one bedroom units of senior housing - the installation will comply with the philadephia plubming code 2004 Date: March 16, 2017 Contractor: Dwd Mechanical Contractor Inc Client: New Courtland Life At St Bartholomew Inc | Permit type: Plumbing permit | Permit status: Active | Completion date: November 7, 2017 | Permit id: 745316 | |||||
SCORE 100 New construction:site work; 6 story structure; relocate 12" sanitary main with new piping pa20170442347 - the installation will comply with the philadephia plubming code 2004 Date: March 16, 2017 Contractor: Dominic Garofolo Client: Newcourtland Properties | Permit type: Plumbing permit | Permit status: Completed | Completion date: May 5, 2017 | Permit id: 764374 | |||||
SCORE 100 Seal 5" sewer lateral Date: March 21, 2017 Contractor: Mr Ds Plumbing And Heating Client: Newcourtland Properties | Permit type: Plumbing permit | Permit status: Completed | Completion date: March 27, 2017 | Permit id: 768307 | |||||
SCORE 100 New construction: site work; (1)8" sanitary lateral (1)15" storm lateral (1)4" domestic water line; backflow;senior apts - the installation will comply with the philadephia plubming code 2004 Date: June 5, 2017 Contractor: Dominic Garofolo Client: Newcourtland Properties | Permit type: Plumbing permit | Permit status: Completed | Completion date: September 27, 2017 | Permit id: 779133 | |||||
SCORE 95 Combined manual wet standpipe & automatic sprinkler system install w. Four (4) inch fire service & backflow prevention (bfp) assembly (in pit) including ul listed diesel fire pump assembly for previously approved six (6) story above grade plane mixed-use senior living facility per approved plans & manufacturers specifications. Combined automatic sprinkler & standpipe system & fire pump assembly install per nfpa 13 14 20. Date: August 8, 2017 Contractor: Preferred Fire Protection Inc Client: Newcourtland Properties | Permit type: Suppression permit | Permit status: Active | Completion date: August 30, 2017 | Permit id: 782384 | |||||
Minor revisions for permit #668794 including decrease in the approved open area from 47. 4% of the site to 47. 3% of the site, the addition of a generator and a transformer near the sanger street frontage of the property and elimination of previously approved curb cut on sanger street as per plans. Date: January 30, 2017 Client: New Courtland Life At St Bartholomew Inc | Permit type: Zoning admin review | Permit status: Completed | Completion date: January 30, 2017 | Permit id: 735585 | |||||
SCORE 100 Hvac installation for senior housing complex. Work includes rooftop units, ductwork, supply diffusers, return registers, bathroom and laundry exhausts, fan heaters and fire smoke dampers. Work at individual dwelling units include domestic kitchen and bathrooms exhausts, fan coil units and refrigerant piping, energy recovery ventilators per plans. Separate permits required for all electrical and plumbing work. Date: May 26, 2017 Contractor: Accord Mechanical And Mgmt Svs Client: Newcourtland Apartments A | Permit type: Mechanical permit | Permit status: Active | Completion date: November 7, 2017 | Permit id: 770004 | |||||
SCORE 100 Seal 5" sewer lateral pa one call #2016-2002568 Date: July 21, 2016 Contractor: Mr Ds Plumbing And Heating Client: Newcourtland Properties | Permit type: Plumbing permit | Permit status: Completed | Completion date: January 17, 2017 | Permit id: 709060 | |||||
SCORE 100 Install new fire alarm system consisting of 1-main fire command panel,6-booster panels,121-horn strobes,118-smoke detectors,15-pull stations,4-duct detectors and 8-smoke dampers as per nfpa72 Date: August 31, 2017 Contractor: Joule Electric Inc Client: Newcourtland Properties | Permit type: Electrical permit | Permit status: Active | Completion date: August 31, 2017 | Permit id: 801426 |