Content | Date | Cost | Contractor Rank | Address | Contractor |
---|---|---|---|---|---|
SCORE 98 New accessible bathroom for existing unit 5047. Applicant: C.E.G. Construction | Permit status: Finaled | Completion date: March 29, 2006 | Permit id: 0602210026 | |||||
SCORE 64 Ti (partition walls) Applicant: K And D Construction | Permit status: Finaled | Completion date: March 23, 2006 | Permit id: 0603020014 | |||||
SCORE 90 Add 2 fire sprinkler heads and relocate 2 heads Applicant: Dinovo,Gaylene | Permit status: Finaled | Completion date: March 30, 2006 | Permit id: 0603130014 | |||||
SCORE 97 Relocate 4 fire sprinklers for new construction Applicant: Medina Edsardo | Permit status: Finaled | Completion date: November 28, 2011 | Permit id: 1111090007 | |||||
SCORE 98 3 outlets-lighting,1 lighting fixture and 1 exhaust fan. Date: February 21, 2006 Contractor: C E G Construction Applicant: C.E.G. Construction | Permit status: Finaled | Completion date: March 31, 2006 | Permit id: 0602210009 | |||||
SCORE 64 18 circuits,2 electric water heaters for ti Date: March 2, 2006 Contractor: K And D Construction Services Applicant: K And D Construction | Permit status: Finaled | Completion date: March 23, 2006 | Permit id: 0603020017 | |||||
SCORE 70 Relocate light fixtures and outlets Date: November 3, 2011 Contractor: Stv Electric Applicant: Stv Electric | Permit status: Finaled | Completion date: November 28, 2011 | Permit id: 1111030026 | |||||
SCORE 64 Alteration of duct system to accomodate ti Date: March 2, 2006 Contractor: K And D Construction Services Applicant: K And D Construction | Permit status: Finaled | Completion date: March 29, 2006 | Permit id: 0603020008 | |||||
SCORE 98 1 new lavatory and 1 water closet. Date: February 21, 2006 Contractor: C E G Construction Applicant: C.E.G. Construction | Permit status: Finaled | Completion date: March 31, 2006 | Permit id: 0602210003 | |||||
SCORE 64 T. I of office - 1474 sf, suite a-5 Date: November 4, 2011 Contractor: City Plumbing Engineer: Jeffrey Russell | Applicant: Dc Expediting | Permit status: Finaled | Completion date: November 28, 2011 | Expiration date: November 3, 2012 | Permit id: 1111040001 | |||||
SCORE 97 T. I of office - 1474 sf, suite a-5 Engineer: Jeffrey Russell | Applicant: Dc Expediting | Permit status: Finaled | Completion date: November 28, 2011 | Expiration date: November 1, 2012 | Permit id: 1108250043 | |||||
SCORE 98 3 outlets-lighting, 1 lighting fixture and 1 exhaust fan. Date: February 21, 2006 Contractor: C E G Construction Applicant: C.E.G. Construction | Permit status: Finaled | Completion date: March 31, 2006 | Expiration date: August 20, 2006 | Permit id: 602210009 | |||||
SCORE 64 18 circuits, 2 electric water heaters for ti Date: March 2, 2006 Contractor: K And D Construction Services Applicant: K And D Construction | Permit status: Finaled | Completion date: March 23, 2006 | Expiration date: August 29, 2006 | Permit id: 603020017 | |||||
SCORE 100 T. I of office - 1474 sf, suite a-5 Date: November 10, 2011 Contractor: Acco Engineered Systems Engineer: Jeffrey Russell | Applicant: Dc Expediting | Permit status: Finaled | Completion date: November 28, 2011 | Expiration date: November 9, 2012 | Permit id: 1111100004 | |||||
SCORE 100 Electrical for a c unit Date: March 5, 2012 Contractor: Acco Engineered Systems Applicant: Wright Russell | Permit status: Finaled | Completion date: March 7, 2012 | Expiration date: March 5, 2013 | Permit id: 1203050044 | |||||
SCORE 100 1 ton package unit and 3 inlets outlets Date: January 30, 2012 Contractor: Acco Engineered Systems Applicant: Wright Russell | Permit status: Finaled | Completion date: March 7, 2012 | Expiration date: January 29, 2013 | Permit id: 1201300009 | |||||
SCORE 76 Add 2 fire sprinkler heads and relocate 2 heads Applicant: Dinovo, Gaylene | Permit status: Finaled | Completion date: March 30, 2006 | Expiration date: March 8, 2007 | Permit id: 603130014 |