SCORE 56 New construction project hotel new construction of a 186 room hotel as per plans, cpc ord # , hdlc c a # , & bza dkt #136-2001. Date: September 12, 2002 Contractor: James Doucette Client: Female Orphan A, Lum | Permit id: B02003438 | |||||
SCORE 82 Swimming pool hotel construct an inground swimming pool to existing hotel as per sketch and the n o comprehensive zon ord art 15 sec 15. 5. 12 #7. Date: October 31, 2003 Contractor: Christy Sanders Client: Female Orphan A, Lum | Permit id: B03005838 | |||||
SCORE 95 Electrical construction loop hotel earl langhoff Date: December 6, 2002 Contractor: Earl Langhoff Client: Female Orphan A, Lum | Permit id: E02009315 | |||||
SCORE 59 Circuits only hotel tower crane and manlift Date: December 12, 2002 Contractor: E. Langhoff Client: Female Orphan A, Lum | Permit id: E02009457 | |||||
SCORE 95 New construction project hotel earl langhoff Date: January 6, 2003 Contractor: Earl Langhoff Client: Female Orphan A, Lum | Permit id: E03000074 | |||||
SCORE 97 Swimming pool hotel randy farrell Date: December 17, 2003 Contractor: Randy Farrell Client: Female Orphan A, Lum | Permit id: E03009643 | |||||
SCORE 84 Electrical reconnect hotel arthur leiter Date: December 23, 2003 Contractor: Arthur Leiter Client: Female Orphan A, Lum | Permit id: E03009801 | |||||
SCORE 95 Canopy sign hotel earl langhoff Date: January 5, 2004 Contractor: Earl Langhoff Client: Female Orphan A, Lum | Permit id: E04000027 | |||||
SCORE 56 Install mechanical equipment hotel workmans hoist 6000# cap.& 17 stops john 826-2443 Date: May 21, 2003 Contractor: Carl E.Woodward Client: Female Orphan A, Lum | Permit id: M03003392 | |||||
SCORE 56 Install operate passenger elevator hotel install 3 new elevs. Vernon 736-0776 Date: September 10, 2003 Contractor: Kone Elev.Co Client: Female Orphan A, Lum | Permit id: M03005570 | |||||
SCORE 74 Install mechanical equipment hotel construction elev. John 822-6443 Date: November 26, 2003 Contractor: Carl E Woodward Client: Female Orphan A, Lum | Permit id: M03007231 | |||||
SCORE 74 Install mechanical equipment hotel elev. #2 used for construction john 822-6443 Date: December 15, 2003 Contractor: Carl E Woodward Client: Female Orphan A, Lum | Permit id: M03007600 | |||||
SCORE 93 Flat sign hotel erect one (1) 4 x 8 flat sign on tchoupitoulas and one (1) 14 x 7. 42 on constance (both illuminated) as per hdlc #c2194 and sketch. Date: October 20, 2003 Contractor: Michael Bocage Client: Female Orphan A, Lum | Permit id: S03001084 | |||||
Changing existing signage Date: March 15, 2017 Permit type: Hdlc coa | Permit status: Permit issued | Expiration date: September 24, 2017 | Current use: Business use | Permit id: 17-07651-Hdlc | |||||
SCORE 100 Change 3 existing signs - all to be in location of existing Date: March 7, 2017 Contractor: Commercial Signs Permit type: Attached sign | Permit status: Permit issued | Expiration date: September 30, 2017 | Current use: Business use | Permit id: 17-07651-Satt | |||||
SCORE 89 Install mechanical equipment hotel install 13-elec warm air furnace . Thomas boudreaux 833-8297 Date: November 26, 2003 Contractor: Mech. Const. Co Client: Female Orphan A, Lum | Permit id: M03007228 | |||||
SCORE 90 Install mechanical equipment hotel install 23-elec warm air furnace rms. 1701-1708,1709d,1709e,1700, 1722,1711. Thomas boudreaux 833-8291 Date: November 26, 2003 Contractor: Mech Const Co Client: Female Orphan A, Lum | Permit id: M03007229 | |||||
SCORE 90 Install mechanical equipment hotel install gas line joseph jaeger - 833-8291 Date: November 26, 2003 Contractor: Mech Const Co Client: Female Orphan A, Lum | Permit id: M03007233 | |||||
SCORE 90 Install mechanical equipment hotel install 2-elec warm air furnace, gas water heater, 4-unit heater, 14,5,2 & 6ton ac system. Thomas boudreaux - 833-8291 Date: December 3, 2003 Contractor: Mech Const Co Client: Female Orphan A, Lum | Permit id: M03007356 | |||||
SCORE 90 Install mechanical equipment hotel install 13-elec warm air furnace rms, 1101-1108,1109d,1109e, 1110d, 1111 & 1122 . Thomas boudreaux - 833-8291 Date: November 26, 2003 Contractor: Mech Const Co Client: Female Orphan A, Lum | Permit id: M03007235 | |||||
SCORE 90 Install mechanical equipment hotel install 13-elec warm air furnace rms. 1201-1208,1209d,1208e, 1210d 1211 & 1222. Thomas boudreaux - 833-8291 Date: November 26, 2003 Contractor: Mech Const Co Client: Female Orphan A, Lum | Permit id: M03007236 | |||||
SCORE 89 Install mechanical equipment hotel install 13-elec warm air furnace. Rms. 1301-1308,1309d,1309e,1310d, 1311 & 1322. Thomas boudreaux - 833-8291 Date: November 26, 2003 Contractor: Mech. Const. Co Client: Female Orphan A, Lum | Permit id: M03007237 | |||||
SCORE 90 Install mechanical equipment hotel install 13-elec warm air furnace rms. 1401-1408,1409d,1409e,1410d, 1411 & 1422. Thomas boudreaux - 833-8291 Date: November 26, 2003 Contractor: Mech Const Co Client: Female Orphan A, Lum | Permit id: M03007238 | |||||
SCORE 90 Install mechanical equipment hotel install 13-elec warm air furnace thomas boudreaux - 833-8291 rms. 1501-1508,1509d,1509e,15105 1511 & 1522 Date: November 26, 2003 Contractor: Mech Const Co Client: Female Orphan A, Lum | Permit id: M03007239 | |||||
SCORE 90 Install mechanical equipment hotel install 13-elec warm air furnace . Thomas boudreaux 833-8291 Date: December 1, 2003 Contractor: Mech Const Co Client: Female Orphan A, Lum | Permit id: M03007292 | |||||
SCORE 90 Install mechanical equipment hotel install 13-elec warm air furnace thomas boudreaux 833-8291 rms,701-708, 709d,709e, 711 & 722 Date: December 1, 2003 Contractor: Mech Const Co Client: Female Orphan A, Lum | Permit id: M03007293 | |||||
SCORE 89 Install mechanical equipment hotel install 13=elec warm air furnace thomas boureaux - 833-8291 rms. 801-808,809d,809e and 811 & 822 Date: December 1, 2003 Contractor: Mech. Const. Co Client: Female Orphan A, Lum | Permit id: M03007294 | |||||
SCORE 90 Install mechanical equipment hotel install 13-elec warm air furnace thomas boudreaux - 833-8291 rms. 901-908,909d,909e,910d 911& 922 Date: December 1, 2003 Contractor: Mech Const Co Client: Female Orphan A, Lum | Permit id: M03007295 | |||||
SCORE 90 Install mechanical equipment hotel install 13-elec warm air furnace thomas boudreaux - 833-8291 rms. - 1001-1008 , 1009d, 1009e 1010d, 1011 & 1022 Date: December 1, 2003 Contractor: Mech Const Co Client: Female Orphan A, Lum | Permit id: M03007296 | |||||
SCORE 90 Install mechanical equipment hotel install 16-elec warm air furnace thomas boudreaux - 833-8291 rms. 201-205,210d,211-214 & 222, 206 & 209 Date: December 3, 2003 Contractor: Mech Const Co Client: Female Orphan A, Lum | Permit id: M03007357 | |||||
SCORE 89 Install mechanical equipment hotel install 15-elec warm air furnace thomas boudreaux - 833-8291 rms. 301-309,310d,311-314 & 322 Date: December 3, 2003 Contractor: Mech. Const. Co Client: Female Orphan A, Lum | Permit id: M03007358 | |||||
SCORE 90 Install mechanical equipment hotel install 15-elec warm air furnace thomas boudreaux - 833-8291 rms. 401-409,410d,411-414 &422 Date: December 3, 2003 Contractor: Mech Const Co Client: Female Orphan A, Lum | Permit id: M03007359 | |||||
SCORE 90 Install mechanical equipment hotel install 16-elec warm air furnace thomas boudreaux - 833-8291 rm. 501-509,510d,511d,511e,512,513,522 & 526 Date: December 3, 2003 Contractor: Mech Const Co Client: Female Orphan A, Lum | Permit id: M03007360 |