Content | Date | Cost | Contractor Rank | Address | Contractor |
---|---|---|---|---|---|
Interior tenant layout and additions to existing structure. Site improvements: existing domestic water, storm, sanitary line replacement in addition to area drains; existing fence/retaining wall upgrades. Date: October 22, 2014 Client: District Of Columbia | Applicant: Nicholas Kavana Coakley Williams | Permit type: Addition alteration | Permit status: Completed | Permit id: B1403418 | |||||
Interior demolition at existing floors for renovations for the new metropolitan police departments 6th district police station Date: February 3, 2014 Client: D.C. Government | Applicant: Andrew Willingham, Bohler Engineering | Permit type: Demolition | Permit status: Permit issued | Permit id: D1400249 | |||||
Request approval of a bciv for site and swm work only. Per approved ddoe plan tracking #3774 Date: August 25, 2014 Client: District Of Columbia | Applicant: Andrew Willingham, Bohler Engineering; Jason Phillips; Andrew Willingham | Permit type: Civil plans | Permit status: Permit issued | Permit id: Bciv1400138 | |||||
Boiler Date: November 17, 2014 Client: District Of Columbia | Applicant: Randall W Greer | Permit status: Permit issued | Permit id: Fb1500031 | |||||
SCORE 96 Boiler Date: November 17, 2014 Contractor: Randall W Greer Client: District Of Columbia | Permit status: Permit issued | Permit id: Fb1500031 | |||||
SCORE 96 Mechanical Date: November 17, 2014 Contractor: Brooke C Greer Client: District Of Columbia | Permit status: Completed | Permit id: M1500406 | |||||
SCORE 96 Plumbing and gas Date: November 17, 2014 Contractor: Randall W Greer Client: District Of Columbia | Permit status: Completed | Permit id: P1501179 | |||||
Plumbing and gas Date: December 16, 2014 Client: District Of Columbia | Permit status: Completed | Permit id: P1502038 | |||||
SCORE 86 The purpose of this permit is for a elevator review only associated with approved/issued b1403418. The elevatory review is for the new dc mpd headquarters, and proposes a two story elevator for ada accessibility to all levels. Date: January 12, 2015 Contractor: Andrew Willingham Bohler Engineering Client: District Of Columbia | Permit type: Addition alteration repair | Permit status: Permit issued | Permit id: B1503321 | |||||
SCORE 70 The purpose of this building permit is to include the review of the handicap lifts at the existing stairwells for the new metro police headquarters located at 5002 hayes street ne. This elevator review was excluded from the previously approved building permit ,b1403418, and it is the intent of this permit to approve the installation of the wheel chair lifts. Date: May 6, 2015 Contractor: Andrew Willingham Bohler Dc Client: District Of Columbia | Permit type: Alteration and repair | Permit status: Permit issued | Permit id: B1507291 | |||||
SCORE 86 Request approval of a building permit application for a proposed motorcycle canopy associated with the new metropolitian police department located at 5002 hayes street, ne. Please see attached plans for further detail. Date: June 2, 2015 Contractor: Andrew Willingham Bohler Engineering Client: District Of Columbia | Permit type: Alteration and repair | Permit status: Permit issued | Permit id: B1508343 | |||||
SCORE 96 Plumbing and gas Date: February 2, 2015 Contractor: Randall W Greer Client: District Of Columbia | Permit status: Completed | Permit id: P1503140 | |||||
SCORE 56 This supplemental permit was issued online. Use the online permit view application on dcra intranet to view the details and print a copy of the permit. Alternatively, you can copy and paste the following url into an internet browser. Https:/ospi. Dcra. Dc. Gov/ospi/printpermit. Aspx? Param=zi8iggjeilek8kzdpz1kgijomwaa28cv Date: February 19, 2015 Contractor: Ron Talton Merritt Mpd Dcra Joe Richards Client: Merritt Mpd Dcra | Permit type: Electrical | Permit status: Permit issued | Permit id: E55573481 | |||||
SCORE 56 Request approval of a bciv for site and swm work only. Per approved ddoe plan tracking #3774 Date: August 25, 2014 Client: District Of Columbia | Permit type: Civil plans | Permit status: Permit issued | Permit id: Bciv1400138 | |||||
SCORE 86 Interior demolition at existing floors for renovations for the new metropolitan police departments 6th district police station Date: February 3, 2014 Contractor: Andrew Willingham Bohler Engineering Client: D.C. Government | Permit type: Demolition | Permit status: Permit issued | Permit id: D1400249 | |||||
SCORE 96 Mechanical Date: November 17, 2014 Contractor: Brooke C Greer Client: District Of Columbia | Permit status: Completed | Permit id: M1500406 | |||||
Plumbing and gas Date: December 16, 2014 Client: District Of Columbia | Permit status: Completed | Permit id: P1502038 | |||||
SCORE 96 Plumbing and gas Date: November 17, 2014 Contractor: Randall W Greer Client: District Of Columbia | Permit status: Completed | Permit id: P1501179 | |||||
SCORE 96 Boiler Date: November 17, 2014 Contractor: Randall W Greer Client: District Of Columbia | Permit status: Permit issued | Permit id: Fb1500031 | |||||
SCORE 56 Request approval of a bciv for site and swm work only. Per approved ddoe plan tracking #3774 Date: August 25, 2014 Client: District Of Columbia | Permit type: Civil plans | Permit status: Permit issued | Permit id: Bciv1400138 | |||||
SCORE 96 Boiler Date: November 17, 2014 Contractor: Randall W Greer Client: District Of Columbia | Permit status: Permit issued | Permit id: Fb1500031 | |||||
SCORE 96 Mechanical Date: November 17, 2014 Contractor: Brooke C Greer Client: District Of Columbia | Permit status: Completed | Permit id: M1500406 | |||||
Plumbing and gas Date: December 16, 2014 Client: District Of Columbia | Permit status: Completed | Permit id: P1502038 | |||||
SCORE 86 Interior demolition at existing floors for renovations for the new metropolitan police departments 6th district police station Date: February 3, 2014 Contractor: Andrew Willingham, Bohler Engineering Client: D.C. Government | Permit type: Demolition | Permit status: Permit issued | Permit id: D1400249 | |||||
SCORE 56 Request approval of a bciv for site and swm work only. Per approved ddoe plan tracking #3774 Date: August 25, 2014 Client: District Of Columbia | Permit type: Civil plans | Permit status: Permit issued | Permit id: Bciv1400138 | |||||
Plumbing and gas Date: December 16, 2014 Client: District Of Columbia | Permit status: Completed | Permit id: P1502038 | |||||
SCORE 96 Plumbing and gas Date: November 17, 2014 Contractor: Randall W Greer Client: District Of Columbia | Permit status: Completed | Permit id: P1501179 | |||||
SCORE 96 Mechanical Date: November 17, 2014 Contractor: Brooke C Greer Client: District Of Columbia | Permit status: Completed | Permit id: M1500406 | |||||
SCORE 96 Boiler Date: November 17, 2014 Contractor: Randall W Greer Client: District Of Columbia | Permit status: Permit issued | Permit id: Fb1500031 | |||||
SCORE 56 Request approval of a building permit application for a proposed motorcycle canopy associated with the new metropolitian police department located at 5002 hayes street, ne. Please see attached plans for further detail. Date: June 2, 2015 Contractor: Andrew Willingham,Bohler Engineering Client: District Of Columbia | Permit type: Alteration and repair | Permit status: Permit issued | Permit id: B1508343 | |||||
SCORE 70 The purpose of this building permit is to include the review of the handicap lifts at the existing stairwells for the new metro police headquarters located at 5002 hayes street ne. This elevator review was excluded from the previously approved building permit ,b1403418, and it is the intent of this permit to approve the installation of the wheel chair lifts. Date: May 6, 2015 Contractor: Andrew Willingham, Bohler Dc Client: District Of Columbia | Permit type: Alteration and repair | Permit status: Permit issued | Permit id: B1507291 | |||||
SCORE 86 The purpose of this permit is for a elevator review only associated with approved issued b1403418. The elevatory review is for the new dc mpd headquarters, and proposes a two story elevator for ada accessibility to all levels. Date: January 12, 2015 Contractor: Andrew Willingham, Bohler Engineering Client: District Of Columbia | Permit type: Addition alteration repair | Permit status: Permit issued | Permit id: B1503321 | |||||
SCORE 99 An after hours permit is respectfully requested from 7:00pm thru 7:00am weekdays Date: March 11, 2015 Contractor: Christine Long Client: Crane Service | Permit type: Miscellaneous | Permit status: Permit issued | Permit id: Ah1500285 | |||||
SCORE 93 Type of elevator :one (1) vpl /interior stairs / steel /wcl Date: May 13, 2015 Contractor: Delaware Elevator Inc Client: District Of Columbia | Permit type: Elevator - new | Permit status: Permit issued | Permit id: En1501617 | |||||
SCORE 96 Plumbing and gas Date: February 2, 2015 Contractor: Randall W Greer Client: District Of Columbia | Permit status: Completed | Permit id: P1503140 | |||||
SCORE 61 5 geotech borings to ft depth for foundation design. Date: March 1, 2016 Contractor: Gregg Furson Client: District Of Columbia | Permit type: Miscellaneous | Permit status: Permit issued | Permit id: Sb1600101 | |||||
SCORE 56 Interior tenant layout and additions to existing structure. Site improvements: existing domestic water, storm, sanitary line replacement in addition to area drains; existing fence/retaining wall upgrades. Date: October 22, 2014 Contractor: Nicholas Kavana Coakley Williams Client: District Of Columbia | Permit type: Addition alteration repair | Permit status: Completed | Permit id: B1403418 | |||||
SCORE 95 Type of elevator :two (2) hydraulic/steel /core/service Date: January 21, 2015 Contractor: Schindler Elevator Corp Client: District Of Columbia | Permit type: Elevator - new | Permit status: Permit issued | Permit id: En1500960 | |||||
SCORE 93 Type of elevator :one (1) vpl /interior stairs/ steel /wcl Date: May 13, 2015 Contractor: Delaware Elevator Inc Client: District Of Columbia | Permit type: Elevator - new | Permit status: Permit issued | Permit id: En1501615 | |||||
SCORE 62 This supplemental permit was issued online. Use the online permit view application on dcra intranet to view the details and print a copy of the permit. Alternatively, you can copy and paste the following url into an internet browser. Https:/ospi. Dcra. Dc. Gov/ospi/printpermit. Aspx? Param=zi8iggjeild1osbgwzxfak2z4g1bbr03 Date: July 1, 2015 Contractor: Ron Talton; Dgs Dgs; Joesph Richards Client: Dgs Dgs | Permit type: Electrical | Permit status: Completed | Permit id: E32045967 | |||||
SCORE 56 This supplemental permit was issued online. Use the online permit view application on dcra intranet to view the details and print a copy of the permit. Alternatively, you can copy and paste the following url into an internet browser. Https:/ospi. Dcra. Dc. Gov/ospi/printpermit. Aspx? Param=zi8iggjeilek8kzdpz1kgijomwaa28cv Date: February 19, 2015 Contractor: Ron Talton; Merritt Mpd Dcra; Joe Richards Client: Merritt Mpd Dcra | Permit type: Electrical | Permit status: Permit issued | Permit id: E55573481 | |||||
SCORE 93 Type of elevator :one (1) ipl/inteiror stair / steel /wcl Date: June 10, 2015 Contractor: Delaware Elevator Inc Client: District Of Columbia | Permit type: Elevator - new | Permit status: Permit issued | Permit id: En1502061 | |||||
SCORE 93 After hours permit to work from saturday 8/8/15 to monday 8/17/15 from 7pm to 7am inconjunction with d-dot permits# 10203761-10203764-10203766-10203771-10203773 leave mobile crane on road over night Date: August 7, 2015 Contractor: Francisco Cranerental Co Client: Washington Dc | Permit type: Miscellaneous | Permit status: Permit issued | Permit id: Ah1500661 |