SCORE 100 Install photovoltaic system on roof Applicant: Bower Robert | Permit status: Finaled | Completion date: March 25, 2009 | Permit id: 0901070007 | |||||
SCORE 100 Electrical for photovoltaic system. Date: January 28, 2009 Contractor: Real Goods Applicant: Bower Robert | Permit status: Finaled | Completion date: March 25, 2009 | Permit id: 0901280002 | |||||
20kw standby generator to main electric pannel & trans for switch. Rzcr201200949 approved 11-08-12. Date: November 20, 2012 Applicant: Same As Owner | Permit status: Finaled | Completion date: November 27, 2012 | Permit id: 1211200017 | |||||
SCORE 99 Fau change out Date: February 25, 2011 Contractor: American Air Conditioning Applicant: Jacoby Eric | Permit status: Finaled | Completion date: March 1, 2011 | Permit id: 1102250014 | |||||
Gas line to 20kw stand by generator. Date: November 20, 2012 Applicant: Same As Owner | Permit status: Finaled | Completion date: November 27, 2012 | Permit id: 1211200011 |