SCORE 70 Add ada parking stalls; provide handrail at entrance ramp convert public restrooms to meet ada compliance Engineer: Aed | Applicant: Hartman John | Permit status: Permisud | Expiration date: February 2, 2006 | Permit id: 407270001 | |||||
SCORE 70 Retrofit existing entrance & rear walkway for barrier remova l also minor interior access upgrade work Engineer: Wayne C. Siu, Aia | Applicant: Wayne C. Siu | Permit status: Finaled | Completion date: October 15, 2010 | Expiration date: June 16, 2011 | Permit id: 1005120073 | |||||
SCORE 95 Grinding & re-surfacing of (e) parking lot. Re-striping Engineer: Raw International | Applicant: Salvador Najera | Permit status: Permisud | Expiration date: February 4, 2015 | Permit id: 1310310011 | |||||
SCORE 95 Tenant improvement: new drop ceiling, replace counter, & new folding doors at kitchennette Engineer: Roland A. Wiley | Applicant: Dequilla Robert | Permit status: Permisud | Expiration date: March 9, 2016 | Permit id: 1407170075 | |||||
SCORE 95 Structural changes for a replacement chiller on the roof Engineer: Roland A. Wiley | Applicant: Jareno Teofilo | Permit status: Permisud | Expiration date: April 1, 2016 | Permit id: 1412230006 | |||||
SCORE 95 New 810" monument sign. Engineer: Roland A. Wiley | Applicant: Dequilla Robert | Permit status: Permisud | Expiration date: March 9, 2016 | Permit id: 1501080024 | |||||
SCORE 66 Install new carport with pv system (electrical part of this pv is under cb1502170011 since pv system is tie into the main pv system on the existing building Applicant: Joshua D Howser Tittsworth | Permit status: Permisud | Expiration date: August 12, 2016 | Permit id: 1503170037 | |||||
SCORE 66 New roof mounted solar system on existing library & carport at 118 kw system Engineer: Andy Blackwell | Applicant: Joshua D Howser Tittsworth | Permit status: Permisud | Expiration date: August 12, 2016 | Permit id: 1502170011 | |||||
SCORE 99 Convert new boler to existing electric service. Date: August 31, 2005 Contractor: Southern California Boiler Applicant: Sanford John | Permit status: Finaled | Completion date: October 27, 2005 | Expiration date: February 27, 2006 | Permit id: 508310010 | |||||
SCORE 70 Retrofit existing entrance & rear walkway for barrier remova l also minor interior access upgrade work Date: June 16, 2010 Contractor: Los Angeles County Isd Engineer: Wayne C. Siu, Aia | Applicant: Wayne C. Siu | Permit status: Finaled | Completion date: October 15, 2010 | Expiration date: June 16, 2011 | Permit id: 1006160025 | |||||
SCORE 95 Upgrade exterior & interior lighting Date: April 2, 2015 Contractor: Mackone Development Inc Engineer: R. Wiley Raw International | Applicant: Jareno Teofilo | Permit status: Permisud | Expiration date: April 1, 2016 | Permit id: 1412230014 | |||||
SCORE 66 Electrical for sub panels and exterior lighting. Date: August 13, 2015 Contractor: Rbt Electric Inc Engineer: Andy Blackwell | Applicant: Joshua D Howser Tittsworth | Permit status: Permisud | Expiration date: August 12, 2016 | Permit id: 1507210061 | |||||
SCORE 99 Replace existing building heat boiler. Date: August 31, 2005 Contractor: Southern California Boiler Applicant: Sanford John | Permit status: Finaled | Completion date: October 27, 2005 | Expiration date: February 27, 2006 | Permit id: 508310009 | |||||
SCORE 95 Replace chiller on roof; provide controls upgrade to replace existing pnematic controls w/ ddc controls & elec actuations Date: April 2, 2015 Contractor: Mackone Development Inc Engineer: R. Wiley Raw International | Applicant: Jareno Teofilo | Permit status: Permisud | Expiration date: April 1, 2016 | Permit id: 1412230005 | |||||
SCORE 99 Convert new boler to existing gas service. Date: August 31, 2005 Contractor: Southern California Boiler Applicant: Sanford John | Permit status: Finaled | Completion date: October 27, 2005 | Expiration date: February 27, 2006 | Permit id: 508310007 | |||||
SCORE 100 Grinding & re-surfacing of (e) parking lot. Re-striping Engineer: Raw International | Applicant: Salvador Najera | Permit status: Permisud | Expiration date: February 4, 2015 | Permit id: 1310310011 | |||||
SCORE 100 Tenant improvement: new drop ceiling, replace counter, & new folding doors at kitchennette Engineer: Roland A. Wiley | Applicant: Dequilla Robert | Permit status: Permisud | Expiration date: March 9, 2016 | Permit id: 1407170075 | |||||
SCORE 100 Structural changes for a replacement chiller on the roof Engineer: Roland A. Wiley | Applicant: Jareno Teofilo | Permit status: Permisud | Expiration date: April 1, 2016 | Permit id: 1412230006 | |||||
SCORE 100 New 810" monument sign. Engineer: Roland A. Wiley | Applicant: Dequilla Robert | Permit status: Permisud | Expiration date: March 9, 2016 | Permit id: 1501080024 | |||||
SCORE 66 Install new carport with pv system (electrical part of this pv is under cb1502170011 since pv system is tie into the main pv system on the existing building Applicant: Joshua D Howser Tittsworth | Permit status: Permisud | Expiration date: August 12, 2016 | Permit id: 1503170037 | |||||
SCORE 66 New roof mounted solar system on existing library & carport at 118 kw system Engineer: Andy Blackwell | Applicant: Joshua D Howser Tittsworth | Permit status: Permisud | Expiration date: August 12, 2016 | Permit id: 1502170011 | |||||
SCORE 100 Upgrade exterior & interior lighting Date: April 2, 2015 Contractor: Mackone Development, Inc Engineer: R. Wiley Raw International | Applicant: Jareno Teofilo | Permit status: Permisud | Expiration date: April 1, 2016 | Permit id: 1412230014 | |||||
SCORE 66 Electrical for sub panels and exterior lighting. Date: August 13, 2015 Contractor: Rbt Electric, Inc Engineer: Andy Blackwell | Applicant: Joshua D Howser Tittsworth | Permit status: Permisud | Expiration date: August 12, 2016 | Permit id: 1507210061 | |||||
SCORE 100 Replace chiller on roof; provide controls upgrade to replace existing pnematic controls w ddc controls & elec actuations Date: April 2, 2015 Contractor: Mackone Development, Inc Engineer: R. Wiley Raw International | Applicant: Jareno Teofilo | Permit status: Permisud | Expiration date: April 1, 2016 | Permit id: 1412230005 |