Content | Date | Cost | Contractor Rank | Address | Contractor |
---|---|---|---|---|---|
SCORE 100 Traffic control: close down north, westbound lane on arapahoe from 5: am to 2: pm on 8 16 06 for concrete truck access to existing right exit. Date: August 10, 2006 Contractor: Wyatt Construction Co Inc Client: Community Boulder | Applicant: Wyatt Construction Co, Inc | Permit type: Right-of-way | Permit status: Iss | |||||
SCORE 100 Tenant finish of 29525 sf medical center (cancer center). Sub valuations tbd. Client: Community Boulder | Applicant: Golden Triangle Const., Inc. | Permit type: Building, electrical | Permit status: Co | Current use: Hospital/instit | |||||
SCORE 100 Temporary access road and drive cut. Date: May 18, 2006 Contractor: Wyatt Construction Co Inc Client: Community Boulder | Applicant: Wyatt Construction Co, Inc | Permit type: Right-of-way | Permit status: Iss | |||||
SCORE 95 Boulder community hospital cancer center. Two stories with basement. 42,7 sf. Core and shell. No restrooms shown at this time. See lur2005-00049 and tec2005-00058 Client: Community Boulder | Applicant: Wyatt Construction Company | Permit type: Building, electrical | Permit status: Co | Current use: Medical and den | |||||
SCORE 100 Fire alarm system - cancer center Date: September 19, 2006 Contractor: Core Electric Inc Client: Community Boulder | Applicant: Core Electric, Inc. | Permit type: Fire | Permit status: Cmp | Completion date: August 30, 2007 | Current use: Medical and den | |||||
SCORE 100 Installing new sewer service, water main extension, water service & fireline Date: September 19, 2006 Contractor: Wyatt Construction Co Inc Client: Community Boulder | Applicant: Wyatt Construction Co, Inc | Permit type: Right-of-way | Permit status: Iss | |||||
SCORE 100 Close northernmost west bound lane of arapahoe for concrete truck access to existing right turn only exit on 10 5 06.. Date: September 29, 2006 Contractor: Wyatt Construction Co Inc Client: Community Boulder | Applicant: Wyatt Construction Co, Inc | Permit type: Right-of-way | Permit status: Act | |||||
SCORE 100 Fire sprinkler system Date: November 21, 2006 Contractor: Fire Defense Inc Client: Community Boulder | Applicant: Fire Defense, Inc. | Permit type: Fire | Permit status: N&v | Current use: Medical and den | |||||
SCORE 100 Mechanical permit for gas piping and temporary construction heat. Date: February 27, 2007 Contractor: Golden Triangle Const. Inc Client: Community Boulder | Applicant: Golden Triangle Const., Inc. | Permit type: Mechanical | Permit status: Cmp | Current use: Hospital/instit | |||||
SCORE 99 Ti fire alarm for tebo medical center Date: May 1, 2007 Contractor: Montgomery Electric Inc Client: Community Boulder | Applicant: Montgomery Electric Inc | Permit type: Fire | Permit status: Cmp | Completion date: August 30, 2007 | Current use: Medical and den | |||||
SCORE 95 Add new solar panels for hospital. Tilt mount pv. 1 panels Client: Community Boulder | Applicant: Namaste Solar Electric Inc | Permit type: Building, flood nons | Permit status: Cmp | Completion date: October 17, 2007 | Current use: Hospital/instit | |||||
SCORE 95 Sign permit for new permanent electric wall sign for boulder community foothills hospital Date: June 22, 2007 Contractor: Schlosser Signs Inc Client: Community Boulder | Applicant: Schlosser Signs, Inc. | Permit type: Sign | Permit status: Cmp | Completion date: March 10, 2008 | Current use: Hospital/instit | |||||
SCORE 95 Sign permit application for boulder community foothills hospital for signs #5, 9 & #14 (refer to sign legend). Date: July 16, 2007 Contractor: Schlosser Signs Inc Client: Community Boulder | Applicant: Schlosser Signs, Inc. | Permit type: Sign | Permit status: Cmp | Completion date: March 10, 2008 | Current use: Hospital/instit | |||||
SCORE 95 Sign permit application for boulder community foothills hospital for signs #24 & #25 (refer to sign legend). Date: July 16, 2007 Contractor: Schlosser Signs Inc Client: Community Boulder | Applicant: Schlosser Signs, Inc. | Permit type: Sign | Permit status: Cmp | Completion date: March 10, 2008 | Current use: Hospital/instit | |||||
SCORE 95 Sign permit for 3 non-electric wall signs "rocky mountain cancer center" and "tebo family medical pavilion" Date: July 6, 2007 Contractor: Urban Fabrication Client: Community Boulder | Applicant: Urban Fabrication | Permit type: Sign | Permit status: Cmp | Completion date: March 10, 2008 | Current use: Medical and den | |||||
SCORE 87 Construction of 12 x 16 trash enclosure on west side of parking lot. See adr2008-00110. Client: Llc Oncocenter | Applicant: Property Outfitters, Llc | Permit type: Building, flood fenc | Permit status: N&v | Current use: Shed, remodel | |||||
SCORE 95 Tenant finish of 12,568 sf on the basement level for administrative offices (payroll, hr, etc.) for boulder community hospital in the baement of the tebo family medical pavilion building. Client: Llc Oncocenter | Applicant: Wyatt Construction Company | Permit type: Building, electrical | Permit status: Cmp | Completion date: February 28, 2012 | Current use: Office - admini | |||||
SCORE 100 Tennant finish sprinkler for tebo cancer center Date: October 13, 2011 Contractor: Fire Defense Inc Client: Llc Oncocenter | Applicant: Fire Defense, Inc. | Permit type: Fire | Permit status: Cmp | Completion date: March 26, 2012 | Current use: Hospital/instit | |||||
SCORE 99 Tennant finish fire alarm for basement of tebo cancer center offices and exam rooms Date: November 16, 2011 Contractor: Montgomery Electric Inc Client: Llc Oncocenter | Applicant: Montgomery Electric Inc | Permit type: Fire | Permit status: Cmp | Completion date: March 26, 2012 | Current use: Medical and den | |||||
SCORE 95 Tenant finish of education & it skills lab (room 023) in tebo family medical pavilion. See pmt2011-038 for tenant finishes throughout the building. Client: Llc Oncocenter | Applicant: Wyatt Construction Company | Permit type: Building, electrical | Permit status: Cmp | Completion date: February 24, 2012 | Current use: Hospital/instit | |||||
SCORE 99 New power conditioner for linear accelerator at tebo family medical pavilion Date: February 13, 2012 Contractor: Montgomery Electric Inc Client: Llc Oncocenter | Applicant: Montgomery Electric Inc | Permit type: Electrical | Permit status: Cmp | Completion date: April 16, 2012 | Current use: Hospital/instit | |||||
SCORE 100 Installation of exterior windsceen coposed of 6-foot linear length of storefront glazing system with laminated glass and associated foundation system adjacent to main entrance at tebo family medical pavilion. Client: Llc Oncocenter | Applicant: Golden Triangle Const., Inc. | Permit type: Building | Permit status: Cmp | Completion date: October 29, 2012 | Current use: Medical and den | |||||
SCORE 95 Tenant finish of education & it skills lab (room 023) in tebo family medical pavilion. See pmt2011-038 for tenant finishes throughout the building. Client: Llc Oncocenter | Permit type: Building, electrical, mechanical, plumbing | Permit status: Cmp | Completion date: February 24, 2012 | Current use: Hospital/institutional, tenant finish | Permit id: Pmt2012-00319 | |||||
SCORE 99 New power conditioner for linear accelerator at tebo family medical pavilion Client: Llc Oncocenter | Permit type: Electrical | Permit status: Cmp | Completion date: April 16, 2012 | Current use: Hospital/institutional, existing | Permit id: Pmt2012-00561 | |||||
SCORE 95 Installation of exterior windsceen coposed of 6-foot linear length of storefront glazing system with laminated glass and associated foundation system adjacent to main entrance at tebo family medical pavilion. Client: Llc Oncocenter | Permit type: Building | Permit status: Cmp | Completion date: October 29, 2012 | Current use: Medical and dental clinics, alteration | Permit id: Pmt2012-04250 | |||||
SCORE 95 Tenant finish of 12,568 sf on the basement level for administrative offices (payroll, hr, etc.) for boulder community hospital in the baement of the tebo family medical pavilion building. Client: Llc Oncocenter | Permit type: Building, electrical, mechanical, plumbing | Permit status: Cmp | Completion date: February 28, 2012 | Current use: Office - administrative, tenant finish | Permit id: Pmt2011-03860 | |||||
SCORE 95 Tennant finish sprinkler for tebo cancer center Client: Llc Oncocenter | Permit type: Fire | Permit status: Cmp | Completion date: March 26, 2012 | Current use: Hospital/institutional, existing | Permit id: Pmt2011-04389 | |||||
SCORE 99 Tennant finish fire alarm for basement of tebo cancer center offices and exam rooms Client: Llc Oncocenter | Permit type: Fire | Permit status: Cmp | Completion date: March 26, 2012 | Current use: Medical and dental clinics, existing | Permit id: Pmt2011-05003 | |||||
SCORE 95 Temporary access road and drive cut. Date: May 18, 2006 Contractor: Wyatt Construction Co, Inc Client: Community Boulder | Permit type: Right-of-way | Permit status: Iss | Permit id: Pmt2006-01650 | |||||
SCORE 95 Traffic control: close down north, westbound lane on arapahoe from 5: am to 2: pm on 8 16 06 for concrete truck access to existing right exit. Date: August 10, 2006 Contractor: Wyatt Construction Co, Inc Client: Community Boulder | Permit type: Right-of-way | Permit status: Iss | Permit id: Pmt2006-03216 | |||||
SCORE 95 Installing new sewer service, water main extension, water service & fireline Date: September 19, 2006 Contractor: Wyatt Construction Co, Inc Client: Community Boulder | Permit type: Right-of-way | Permit status: Iss | Permit id: Pmt2006-04004 | |||||
SCORE 95 Boulder community hospital cancer center. Two stories with basement. 42,7 sf. Core and shell. No restrooms shown at this time. See lur2005-00049 and tec2005-00058 Client: Community Boulder | Permit type: Building, electrical, mechanical, plumbing, water, wastewater, sitework | Permit status: Co | Current use: Medical and dental clinics, core and she | Permit id: Pmt2006-00302 | |||||
SCORE 95 Tenant finish of 29525 sf medical center (cancer center). Sub valuations tbd. Client: Community Boulder | Permit type: Building, electrical, mechanical, plumbing, flood accessory/remodel | Permit status: Co | Current use: Hospital/institutional, tenant finish | Permit id: Pmt2006-02457 | |||||
SCORE 95 Fire alarm system - cancer center Client: Community Boulder | Permit type: Fire | Permit status: Cmp | Completion date: August 30, 2007 | Current use: Medical and dental clinics, existing | Permit id: Pmt2006-03978 | |||||
SCORE 95 Close northernmost west bound lane of arapahoe for concrete truck access to existing right turn only exit on 10 5 06.. Contractor: Wyatt Construction Co, Inc Client: Community Boulder | Permit type: Right-of-way | Permit status: Act | Permit id: Pmt2006-04228 | |||||
SCORE 95 Fire sprinkler system Client: Community Boulder | Permit type: Fire | Permit status: N&v | Current use: Medical and dental clinics, existing | Permit id: Pmt2006-04916 | |||||
SCORE 95 Mechanical permit for gas piping and temporary construction heat. Client: Community Boulder | Permit type: Mechanical | Permit status: Cmp | Current use: Hospital/institutional, existing | Permit id: Pmt2007-00634 | |||||
SCORE 99 Ti fire alarm for tebo medical center Client: Community Boulder | Permit type: Fire | Permit status: Cmp | Completion date: August 30, 2007 | Current use: Medical and dental clinics, existing | Permit id: Pmt2007-01618 | |||||
SCORE 95 Add new solar panels for hospital. Tilt mount pv. 1 panels Client: Community Boulder | Permit type: Building, flood nonsubstantial mod/add, photovoltaic | Permit status: Cmp | Completion date: October 17, 2007 | Current use: Hospital/institutional, existing | Permit id: Pmt2007-01749 | |||||
SCORE 95 Sign permit for new permanent electric wall sign for boulder community foothills hospital Client: Community Boulder | Permit type: Sign | Permit status: Cmp | Completion date: March 10, 2008 | Current use: Hospital/institutional, existing | Permit id: Pmt2007-02122 | |||||
SCORE 95 Sign permit application for boulder community foothills hospital for signs #5, 9 & #14 (refer to sign legend). Client: Community Boulder | Permit type: Sign | Permit status: Cmp | Completion date: March 10, 2008 | Current use: Hospital/institutional, existing | Permit id: Pmt2007-02364 | |||||
SCORE 95 Sign permit application for boulder community foothills hospital for signs #24 & #25 (refer to sign legend). Client: Community Boulder | Permit type: Sign | Permit status: Cmp | Completion date: March 10, 2008 | Current use: Hospital/institutional, existing | Permit id: Pmt2007-02365 | |||||
SCORE 95 Sign permit for 3 non-electric wall signs inchrocky mountain cancer centerinch and inchtebo family medical pavilioninch Client: Community Boulder | Permit type: Sign | Permit status: Cmp | Completion date: March 10, 2008 | Current use: Medical and dental clinics, existing | Permit id: Pmt2007-02733 | |||||
SCORE 91 Construction of 12foot x 16foot trash enclosure on west side of parking lot. See adr2008-00110. Client: Llc Oncocenter | Permit type: Building, flood fence flood permit | Permit status: N&v | Current use: Shed, remodel | Permit id: Pmt2008-05095 |