Hvac Date: April 13, 2010 Permit status: Permit expired | Current use: Commercial | Permit id: 10044-10000-034 | |||||
SCORE 88 New equipment pads and platforms for four filter units, piping suppor Permit type: Nonbldg-new | Permit status: Issued | Current use: Commercial | Permit id: 12020-30000-019 | |||||
SCORE 59 Alteration to rooftop of mfg bldg: remove & replace 12 a switchboar Permit type: Bldg-alter/repair | Permit status: Issued | Current use: Commercial | Permit id: 15016-10000-278 | |||||
SCORE 97 Electrical Date: April 25, 2016 Contractor: Linda Permit status: Issued | Current use: Commercial | Permit id: 16041-20000-143 | |||||
SCORE 78 Electrical Date: November 7, 2014 Contractor: Sam Khurana Permit status: Permit finaled | Current use: Commercial | Permit id: 14041-10000-309 | |||||
SCORE 62 Proposed to remove 12" of claysoil in an existing pond and install new Permit type: Grading | Permit status: Issued | Current use: Commercial | Permit id: 14030-10000-033 | |||||
SCORE 61 Remove old motor loads and add new 150hp motor loads for water pumps. Date: October 23, 2013 Contractor: Peter Maguire Permit type: Electrical | Permit status: Permit finaled | Current use: Commercial | Permit id: 12041-20000-237 | |||||
Hvac Date: May 5, 2015 Permit status: Issued | Current use: Commercial | Permit id: 15044-10000-041 | |||||
SCORE 64 Grading permit for excavation and backfill. Permit type: Grading | Permit status: Issued | Current use: Commercial | Permit id: 14030-30000-010 | |||||
SCORE 97 Plumbing Date: May 21, 2015 Contractor: Greg Permit status: Issued | Current use: Commercial | Permit id: 15042-10000-096 | |||||
SCORE 84 Construction of equipment pads for electrical substation 1. Construct Permit type: Nonbldg-new | Permit status: Permit finaled | Current use: Commercial | Permit id: 13020-10000-009 | |||||
SCORE 98 Re-roof with class a or b material weighing less than 6 pounds per sq. Permit type: Bldg-alter/repair | Permit status: Issued | Current use: Commercial | Permit id: 15016-20000-190 | |||||
SCORE 84 Replace unit substations construct new 5kv switch gear. Original plan Date: July 11, 2013 Contractor: Ricardo Acosta Permit type: Electrical | Permit status: Permit finaled | Current use: Commercial | Permit id: 13041-10000-081 | |||||
SCORE 61 Electrical Date: January 8, 2016 Contractor: Herendira Molina Permit status: Issued | Current use: Commercial | Permit id: 16041-10000-006 | |||||
SCORE 64 Shoring for temp. Excavation. Permit type: Nonbldg-new | Permit status: Permit finaled | Current use: Commercial | Permit id: 14020-30000-004 | |||||
SCORE 78 3 new 1,5 hp blowers at the ladwp water reclamation plant at 4,000vo Date: October 21, 2013 Contractor: Sam Khurana Permit type: Electrical | Permit status: Permit finaled | Current use: Commercial | Permit id: 12041-10000-098 | |||||
SCORE 59 Enlarge exterior openings (3 total) of (e) treatment plan; provide pi Permit type: Bldg-alter/repair | Permit status: Permit finaled | Current use: Commercial | Permit id: 12016-10000-083 | |||||
SCORE 97 Installation of a 60 gallon liquid nitrogen tank on conc pad Permit type: Nonbldg-alter/repair | Permit status: Issued | Current use: Commercial | Permit id: 14024-10000-000 | |||||
SCORE 59 Install new state-approved 24 x modular office building with stat Permit type: Bldg-new | Permit status: Issued | Current use: Commercial | Permit id: 15010-10000-028 | |||||
Electrical Date: June 29, 2016 Permit status: Permit finaled | Current use: Commercial | Permit id: 16041-10000-228 | |||||
SCORE 75 Electrical Date: June 29, 2016 Contractor: Halsted Construction Inc Permit status: Permit finaled | Current use: Commercial | Permit id: 16041-10000-228 | |||||
SCORE 97 Install 2 ton air cooled chiller Date: October 13, 2016 Contractor: Steve Permit type: Hvac | Permit status: Issued | Current use: Commercial | Permit id: 16044-20000-113 | |||||
SCORE 59 Installation of foundation pad and anchorage for equipment Permit type: Nonbldg-new | Permit status: Issued | Current use: Commercial | Permit id: 16020-10000-031 | |||||
SCORE 67 Pc for power only. Scope includes new 1200a switch board installatio Date: November 18, 2016 Contractor: Jim Megordon Permit type: Electrical | Permit status: Issued | Current use: Commercial | Permit id: 16041-10000-373 | |||||
SCORE 70 Hvac Date: May 5, 2015 Contractor: Accountable Air Conditioning Incorporated Permit status: Issued | Current use: Commercial | Permit id: 15044-10000-041 | |||||
SCORE 73 Electrical Date: September 25, 2015 Contractor: Green Building Corporation Permit status: Issued | Current use: Commercial | Permit id: 15041-10000-318 |