Content | Date | Cost | Contractor Rank | Address | Contractor |
---|---|---|---|---|---|
Supplemental permit to 10010-10002-01604. Deferred submittal for exte Date: October 27, 2011 Value: $501 Permit type: Bldg-alter/repair | Permit status: Permit finaled | Current use: Commercial | Permit id: 10010-10006-016 | |||||
SCORE 100 Interior renovation of existing manufacturing area. Add exits, relocat Permit type: Bldg-alter/repair | Permit status: Permit finaled | Current use: Commercial | Permit id: 10016-10000-166 | |||||
SCORE 56 New 120,0 gallon underground fire water storage tank (33x48x15-2" Permit type: Nonbldg-new | Permit status: Permit finaled | Current use: Commercial | Permit id: 10020-10000-007 | |||||
SCORE 67 New 2-story manufacturing facility with partial basement and two equip Date: February 24, 2011 Contractor: Daniel Burson Permit type: Electrical | Permit status: Permit finaled | Current use: Commercial | Permit id: 10041-10000-225 | |||||
SCORE 97 Electrical Date: July 13, 2010 Contractor: Steve Permit status: Permit finaled | Current use: Commercial | Permit id: 10041-10002-109 | |||||
SCORE 92 Plumbing Date: May 10, 2011 Contractor: Shaabini Alford Permit status: Issued | Current use: Commercial | Permit id: 11042-90000-080 | |||||
SCORE 89 Fire sprinkler Date: July 22, 2010 Contractor: Frank J. Mone Permit status: Permit finaled | Current use: Commercial | Permit id: 10043-90000-015 | |||||
SCORE 98 Fire sprinkler Date: August 26, 2010 Contractor: Joseph Peterson Permit status: Refund completed | Current use: Commercial | Permit id: 10043-90000-018 | |||||
Fire sprinkler installation. Baxter building. Add 2305 heads. Add 21-2 Date: December 19, 2012 Value: $15,000 Permit type: Fire sprinkler | Permit status: Permit finaled | Current use: Commercial | Permit id: 12043-10000-022 | |||||
SCORE 59 Renovation of manufac. Area(s). Add new compressors, air handlers,and Date: August 29, 2012 Contractor: Steve Tomco Permit type: Hvac | Permit status: Permit expired | Current use: Commercial | Permit id: 10044-10000-123 | |||||
SCORE 56 Proposed maximum 5 high retaining wall at baxter site. Total 1 lf. Permit type: Nonbldg-new | Permit status: Permit expired | Current use: Commercial | Permit id: 10020-10000-026 | |||||
SCORE 100 Interior tenant improvement to add two doors and partition within exis Permit type: Bldg-alter/repair | Permit status: Permit finaled | Current use: Commercial | Permit id: 10016-10000-074 | |||||
Renovation of existing storage room within building b1 into an in-proc Date: July 19, 2010 Value: $300,000 Permit type: Bldg-alter/repair | Permit status: Permit finaled | Current use: Commercial | Permit id: 10016-10000-111 | |||||
SCORE 62 Electrical Date: July 20, 2010 Contractor: Frank Gandara Permit status: Permit finaled | Current use: Commercial | Permit id: 10041-90000-139 | |||||
SCORE 67 Install new plumbing system for new 2 story building + 2 levels of me Date: February 24, 2011 Contractor: Daniel Burson Permit type: Plumbing | Permit status: Permit finaled | Current use: Commercial | Permit id: 10042-10000-194 | |||||
SCORE 93 Relocate existing ductbanks to make room for future buildingds. Instal Date: July 7, 2010 Contractor: Rand Permit type: Electrical | Permit status: Permit finaled | Current use: Commercial | Permit id: 10041-10000-061 | |||||
Install new steel framed platorm (48 x 73 ) to support mechanical eq Date: July 23, 2010 Value: $546,000 Permit type: Bldg-addition | Permit status: Cofo issued | Current use: Commercial | Permit id: 10010-10000-010 | |||||
Electrical Date: September 13, 2010 Permit status: Permit closed | Current use: Commercial | Permit id: 10041-10000-180 | |||||
SCORE 75 Construct new 5-story, type i-b, office bldg. Nfpa-13 automatic fire s Permit type: Bldg-new | Permit status: Cofo issued | Current use: Commercial | Permit id: 12010-10000-000 | |||||
SCORE 86 Plumbing Date: February 6, 2012 Contractor: Gerardus Opzeeland Permit status: Permit finaled | Current use: Commercial | Permit id: 12042-90000-022 | |||||
SCORE 100 Renovate existing area for gowning rooms; remove interior ceiling supp Permit type: Bldg-alter/repair | Permit status: Permit finaled | Current use: Commercial | Permit id: 11016-10000-113 | |||||
Electrical Date: December 1, 2011 Permit status: Permit finaled | Current use: Commercial | Permit id: 11041-10000-256 | |||||
SCORE 100 Baxter lamp bldg 4 alteration and renovation. Two panels and 56 fa dev Date: August 4, 2010 Contractor: Veronica Cobian Permit type: Electrical | Permit status: Permit finaled | Current use: Commercial | Permit id: 10041-10000-151 | |||||
SCORE 59 Electrical Date: March 29, 2012 Contractor: Murray Demchuk Permit status: Permit closed | Current use: Commercial | Permit id: 12041-20000-071 | |||||
New 2-story manufacturing facility with partial basement and two equip Date: February 28, 2011 Value: $40,000,000 Permit type: Bldg-addition | Permit status: Issued | Current use: Commercial | Permit id: 10010-10000-016 | |||||
SCORE 100 Tenant improvement for nurses station (4 sf) within existing manufa Permit type: Bldg-alter/repair | Permit status: Permit finaled | Current use: Commercial | Permit id: 10016-10000-083 | |||||
SCORE 75 Supplemental permit to #12010-10000-00078 to revise portion of office Permit type: Bldg-alter/repair | Permit status: Permit finaled | Current use: Commercial | Permit id: 12010-10002-000 | |||||
Temporary shoring for the proposed building b-8 basement excavation an Date: February 25, 2011 Value: $592,000 Permit type: Nonbldg-new | Permit status: Permit expired | Current use: Commercial | Permit id: 11020-10000-001 | |||||
SCORE 100 Construct exterior stairway. Permit type: Bldg-alter/repair | Permit status: Permit finaled | Current use: Commercial | Permit id: 10016-10000-059 | |||||
SCORE 80 Partial renovation of existing 2-story building, approximately 1117 sf Permit type: Bldg-alter/repair | Permit status: Permit finaled | Current use: Commercial | Permit id: 10016-10000-206 | |||||
SCORE 78 Electrical Date: October 28, 2011 Contractor: Kristen Nelson Permit status: Permit closed | Current use: Special equipment | Permit id: 11041-90000-231 | |||||
SCORE 100 Electrical Date: September 7, 2012 Contractor: Glen Permit status: Permit closed | Current use: Commercial | Permit id: 12041-10001-207 | |||||
SCORE 59 T. I within a single story office/lab. Added two type ii hoods and a f Date: September 21, 2010 Contractor: Shawn Xu Permit type: Hvac | Permit status: Permit finaled | Current use: Commercial | Permit id: 10044-10000-041 | |||||
Electrical Date: February 22, 2012 Permit status: Permit finaled | Current use: Commercial | Permit id: 12041-10000-039 | |||||
SCORE 99 Plancheck/permit for ventilation and combustion air for pre-fabricated Date: May 26, 2011 Contractor: Jose Gutierrez Permit type: Hvac | Permit status: Permit finaled | Current use: Commercial | Permit id: 11044-10000-057 | |||||
New 2-story manufacturing facility with partial basement and two equip Date: April 22, 2011 Value: $400,000 Permit type: Bldg-alter/repair | Permit status: Permit finaled | Current use: Commercial | Permit id: 10010-10003-016 | |||||
SCORE 92 Install hvac system for a new 5-story office building with cafeteria ( Date: July 2, 2012 Contractor: Eric Harley Permit type: Hvac | Permit status: Permit finaled | Current use: Commercial | Permit id: 12044-10000-016 | |||||
SCORE 59 T. I within bldg 4 within an existing single story office/lab building. Date: June 25, 2010 Contractor: Shawn Xu Permit type: Plumbing | Permit status: Permit finaled | Current use: Commercial | Permit id: 10042-10000-071 | |||||
Installation of a new cartlift mono-column in room 1103 (2nd floor) of Date: January 24, 2012 Value: $20,000 Permit type: Bldg-alter/repair | Permit status: Permit finaled | Current use: Commercial | Permit id: 11016-10000-184 | |||||
SCORE 100 Electrical Date: April 16, 2012 Contractor: Mahmoud Fazlali Permit status: Permit finaled | Current use: Commercial | Permit id: 12041-10000-086 | |||||
Install new hvac system and fume hoods for new 2 story building + 2 l Date: April 14, 2011 Permit type: Hvac | Permit status: Permit finaled | Current use: Commercial | Permit id: 10044-10000-111 | |||||
Work in this phase of construction will include all underground infras Date: December 21, 2010 Permit type: Fire sprinkler | Permit status: Issued | Current use: Commercial | Permit id: 10043-10000-007 | |||||
SCORE 97 Hvac Date: August 17, 2011 Contractor: Dan Permit status: Permit finaled | Current use: Commercial | Permit id: 11044-10000-093 | |||||
Early start permit to remove interior non-structural partition walls, Date: May 26, 2010 Value: $650,000 Permit type: Bldg-alter/repair | Permit status: Permit finaled | Current use: Commercial | Permit id: 10016-10001-077 | |||||
SCORE 100 Proposed to construct new irregular-shaped 17-6" x16-8" equipment ve Permit type: Bldg-addition | Permit status: Permit finaled | Current use: Commercial | Permit id: 12014-10000-000 | |||||
SCORE 75 Supplemental permit to #12010-10000-00078 to revise proposed 12" thick Permit type: Bldg-alter/repair | Permit status: Permit finaled | Current use: Commercial | Permit id: 12010-10001-000 | |||||
SCORE 96 Install 2 ft of 12" potable water service line and (2) r. P. Backflow Permit type: Plumbing | Permit status: Permit finaled | Current use: Commercial | Permit id: 12042-10000-015 | |||||
SCORE 56 Electrical Date: September 23, 2010 Contractor: Mike Doninelli Permit status: Permit closed | Current use: Commercial | Permit id: 10041-10000-188 | |||||
Relocate interior partitions to make room for new tanks. New mechanica Date: August 11, 2010 Value: $300,000 Permit type: Bldg-alter/repair | Permit status: Permit finaled | Current use: Commercial | Permit id: 10016-10000-111 | |||||
Fire sprinkler Date: August 2, 2012 Value: $15,000 Permit status: Permit finaled | Current use: Commercial | Permit id: 12043-10002-022 | |||||
SCORE 100 Modified rooftop equipment & pipe support. Permit type: Bldg-alter/repair | Permit status: Permit finaled | Current use: Commercial | Permit id: 10016-10001-166 | |||||
SCORE 91 Electrical Date: September 10, 2010 Contractor: Mike Amdor Permit status: Permit finaled | Current use: Commercial | Permit id: 10041-90000-179 | |||||
SCORE 91 Supplemental to 10010-10003-01604. Construct light-gauge interstitia Permit type: Bldg-alter/repair | Permit status: Permit finaled | Current use: Commercial | Permit id: 10010-10007-016 | |||||
SCORE 75 Removal and re-compaction of new building pad. Total of 8,700cy. Permit type: Grading | Permit status: Permit finaled | Current use: Commercial | Permit id: 12030-10000-031 | |||||
SCORE 61 Plan check for rerouting of sewer fixtures to new onsite connection. Date: February 9, 2012 Contractor: Bill Albert Permit type: Plumbing | Permit status: Permit finaled | Current use: Commercial | Permit id: 11042-10000-007 | |||||
SCORE 72 Electrical Date: June 27, 2012 Contractor: Ramon Salceda Permit status: Permit closed | Current use: Commercial | Permit id: 12041-10000-150 | |||||
SCORE 56 Plumbing Date: January 18, 2012 Contractor: Enrique Arenas Permit status: Permit finaled | Current use: Commercial | Permit id: 12042-10000-010 | |||||
SCORE 56 Demolition of existing butler building. Method of demolition by handw Permit type: Bldg-demolition | Permit status: Permit finaled | Current use: Commercial | Permit id: 10019-10000-020 | |||||
SCORE 96 Add 4" domestic water service line. A= 3. 92 psi/1 ft. 81/48 psi. 3" Date: May 17, 2012 Contractor: Barbara Hall Permit type: Plumbing | Permit status: Permit finaled | Current use: Commercial | Permit id: 12042-10000-086 | |||||
Supplemental to permit #10010-10000-01604 to revise the on-site total Date: May 23, 2012 Value: $501 Permit type: Bldg-alter/repair | Permit status: Permit finaled | Current use: Commercial | Permit id: 10010-10008-016 | |||||
SCORE 73 Tenant improvement. Add 4 heads in vestibule. Office space. "baxter he Date: February 14, 2012 Contractor: Art Stoll Permit type: Fire sprinkler | Permit status: Permit finaled | Current use: Commercial | Permit id: 12043-10000-004 | |||||
Electrical Date: August 11, 2011 Value: $1,000,000 Permit status: Permit finaled | Current use: Commercial | Permit id: 11041-10000-160 | |||||
SCORE 75 New 5-story, 87,7 sf type i-b office building (baxter b6). Epc is fo Date: July 2, 2012 Contractor: Boon Lim Permit type: Electrical | Permit status: Permit finaled | Current use: Commercial | Permit id: 12041-10000-027 | |||||
SCORE 60 Plumbing Date: June 1, 2012 Contractor: Gary Scott Permit status: Permit closed | Current use: Commercial | Permit id: 12042-10000-099 | |||||
SCORE 96 Construct sanitary sewer pipng from building 8 to site sanitary sewer Permit type: Plumbing | Permit status: Permit finaled | Current use: Commercial | Permit id: 12042-10000-058 | |||||
SCORE 74 Deferred submittal steel stairs Permit type: Bldg-alter/repair | Permit status: Permit expired | Current use: Commercial | Permit id: 11016-10000-019 | |||||
SCORE 100 Electrical Date: December 8, 2011 Contractor: Russell Wright Permit status: Permit expired | Current use: Commercial | Permit id: 11041-90000-261 | |||||
SCORE 96 Fire sprinkler Date: February 10, 2012 Contractor: Patrick Heller Permit status: Permit finaled | Current use: Commercial | Permit id: 12043-90000-004 | |||||
SCORE 98 Fire sprinkler Date: November 21, 2011 Contractor: Joseph Peterson Permit status: Permit expired | Current use: Commercial | Permit id: 11043-90000-030 | |||||
Renovation and partial demolition of one-story existing building #4. W Date: June 22, 2010 Value: $1,950,000 Permit type: Bldg-alter/repair | Permit status: Permit finaled | Current use: Commercial | Permit id: 10016-10000-077 | |||||
SCORE 62 Plan check for overhead fire sprinkler system mechanical platform. Can Date: August 19, 2010 Contractor: Rich Peterson Permit type: Fire sprinkler | Permit status: Permit finaled | Current use: Commercial | Permit id: 10043-10000-018 | |||||
New industrial/process plumbing system in new 2 story building. Bldg #8 Date: September 9, 2011 Permit type: Plumbing | Permit status: Permit finaled | Current use: Commercial | Permit id: 11042-10000-116 | |||||
Supplemental to 10010-10003-01604 for the deferred plan check. Stair # Date: February 27, 2012 Value: $501 Permit type: Bldg-alter/repair | Permit status: Permit finaled | Current use: Commercial | Permit id: 10010-10004-016 | |||||
Supplemental to permit #10016-10000-07765 to delete proposed restroom Date: July 7, 2010 Value: $501 Permit type: Bldg-alter/repair | Permit status: Permit finaled | Current use: Commercial | Permit id: 10016-10002-077 | |||||
SCORE 62 Electrical Date: February 11, 2011 Contractor: Frank Gandara Permit status: Permit finaled | Current use: Commercial | Permit id: 11041-90000-027 | |||||
Use of land for the emergency generator pad on 6 drilled piles and gra Date: February 27, 2012 Value: $70,000 Permit type: Nonbldg-new | Permit status: Permit finaled | Current use: Commercial | Permit id: 12020-10000-003 | |||||
SCORE 92 Plumbing for a new 5-story office building with cafeteria (bldg #6). Date: July 2, 2012 Contractor: Eric Harley Permit type: Plumbing | Permit status: Permit finaled | Current use: Commercial | Permit id: 12042-10000-027 | |||||
Installation of a temporary standpipe system for a 2 story building. Date: January 3, 2012 Permit type: Fire sprinkler | Permit status: Permit finaled | Current use: Commercial | Permit id: 12043-10000-000 | |||||
SCORE 59 Plumbing Date: August 29, 2012 Contractor: Steve Tomco Permit status: Permit finaled | Current use: Commercial | Permit id: 12042-10000-158 | |||||
SCORE 63 Plumbing Date: February 1, 2012 Contractor: Dan Flores Permit status: Permit finaled | Current use: Commercial | Permit id: 12042-10000-019 | |||||
SCORE 59 Plumbing Date: May 18, 2011 Contractor: Andres Robles Permit status: Permit finaled | Current use: Commercial | Permit id: 11042-10000-086 | |||||
SCORE 59 New 800a subpanel. Plan check for power only. Date: March 30, 2012 Contractor: Murray Demchuk Permit type: Electrical | Permit status: Permit finaled | Current use: Commercial | Permit id: 12041-20000-069 | |||||
SCORE 86 Hvac Date: July 22, 2010 Contractor: Gerardus Opzeeland Permit status: Permit finaled | Current use: Commercial | Permit id: 10044-90000-069 | |||||
SCORE 100 New structural footing for new hoist (equipment) rated at 15 lbs. Permit type: Nonbldg-new | Permit status: Issued | Current use: Commercial | Permit id: 12020-10000-001 | |||||
Partial renovation and partial demolition of one-story existing buildi Date: July 1, 2010 Value: $1,000,000 Permit type: Bldg-alter/repair | Permit status: Issued | Current use: Commercial | Permit id: 10016-10000-077 | |||||
SCORE 100 Install (12) fire sprinklers below new recycling area canopy with cont Date: August 25, 2011 Contractor: Frank Mone Permit type: Fire sprinkler | Permit status: Permit finaled | Current use: Commercial | Permit id: 11043-10000-021 | |||||
SCORE 99 Hvac Date: January 26, 2012 Contractor: Scott Permit status: Permit finaled | Current use: Commercial | Permit id: 12044-10000-009 | |||||
Grading permit for new building site prep, removal and re-compaction, Date: February 28, 2011 Value: $9,600 Permit type: Grading | Permit status: Permit finaled | Current use: Commercial | Permit id: 11030-10000-004 | |||||
SCORE 80 Remove portion of the existing one-story unlimited floor area buildi Permit type: Bldg-alter/repair | Permit status: Permit expired | Current use: Commercial | Permit id: 11016-10000-019 | |||||
SCORE 95 Addition of a new ln ( liquid nitrogen) 2 exhaust fan mechanical unit Permit type: Bldg-alter/repair | Permit status: Permit finaled | Current use: Commercial | Permit id: 11016-10000-234 | |||||
Supplemental to permit #10016-10000-11198 to revise the framing of ste Date: August 27, 2010 Value: $501 Permit type: Bldg-alter/repair | Permit status: Permit finaled | Current use: Commercial | Permit id: 10016-10001-111 | |||||
SCORE 64 Foundation for 10,0 gal h tank; foundation for still h processo Permit type: Nonbldg-new | Permit status: Permit finaled | Current use: Commercial | Permit id: 11020-10000-023 | |||||
SCORE 56 Construct sanitary sewer pipng from building 8 to site sanitary sewer Permit type: Plumbing | Permit status: Permit finaled | Current use: Commercial | Permit id: 12042-10001-058 | |||||
SCORE 100 Fire sprinkler Date: September 13, 2012 Contractor: Maxine Brown Permit status: Permit finaled | Current use: Commercial | Permit id: 12043-10003-022 | |||||
SCORE 73 Installation of fire sprinklers in (6) existing cooling towers on roof Date: November 22, 2011 Contractor: Art Stoll Permit type: Fire sprinkler | Permit status: Permit finaled | Current use: Commercial | Permit id: 11043-10000-030 | |||||
SCORE 100 Electrical Date: October 31, 2012 Contractor: Mahmoud Fazlali Permit status: Issued | Current use: Commercial | Permit id: 12041-10000-261 | |||||
SCORE 93 Ti in an existing "b" occupancy of building 4 of "baxter". Install p Date: July 7, 2010 Contractor: Mike Shea Permit type: Electrical | Permit status: Permit finaled | Current use: Commercial | Permit id: 10041-10000-081 | |||||
SCORE 100 Interior tenant improvement; convert portion of existing offices to t Permit type: Bldg-alter/repair | Permit status: Permit finaled | Current use: Commercial | Permit id: 11016-10000-207 | |||||
SCORE 67 Supplemental plan check for addition of shower, trap primers, floor dr Date: June 11, 2012 Contractor: Daniel Burson Permit type: Plumbing | Permit status: Permit finaled | Current use: Commercial | Permit id: 10042-10002-194 | |||||
SCORE 100 Supplemental to permit #10016-10000-16647 to review plans and to add a Permit type: Bldg-alter/repair | Permit status: Permit expired | Current use: Commercial | Permit id: 10016-10002-166 | |||||
SCORE 100 New fire alarm system for a 2-story healthcare office building. Date: December 10, 2012 Contractor: Veronica Cobian Permit type: Electrical | Permit status: Permit expired | Current use: Commercial | Permit id: 12041-10000-083 | |||||
SCORE 67 Installation of mv emergency generator and associated ats to supply e Date: January 26, 2012 Contractor: Daniel Burson Permit type: Electrical | Permit status: Permit finaled | Current use: Commercial | Permit id: 10041-10001-225 | |||||
Supplemental to permit # 10010-10000-01086: structural alteration for Date: August 13, 2010 Value: $50,000 Permit type: Bldg-alter/repair | Permit status: Permit finaled | Current use: Commercial | Permit id: 10010-70001-010 | |||||
Adding heads under canopy (wash area) Date: January 12, 2011 Permit type: Fire sprinkler | Permit status: Permit finaled | Current use: Commercial | Permit id: 11043-10000-000 | |||||
SCORE 68 Plumbing Date: March 8, 2012 Contractor: Mark Magnuson Permit status: Permit finaled | Current use: Commercial | Permit id: 12042-10000-043 | |||||
T. I added and relocated sprinklers Date: February 16, 2011 Permit type: Fire sprinkler | Permit status: Permit finaled | Current use: Commercial | Permit id: 11043-10000-003 | |||||
SCORE 99 Installation of (1) 3-stop hydraulic elevator. Date: September 10, 2012 Contractor: Maricela Estrada Permit type: Elevator | Permit status: Permit finaled | Current use: Commercial | Permit id: 12046-10000-009 | |||||
SCORE 99 Electrical Date: July 2, 2012 Contractor: Rolando Sotelo Permit status: Permit finaled | Current use: Commercial | Permit id: 12041-10000-021 | |||||
SCORE 64 Alteration to the exterior of the building, close off existing door a Permit type: Bldg-alter/repair | Permit status: Permit finaled | Current use: Commercial | Permit id: 11016-10000-227 | |||||
SCORE 100 Supplemental to permit #10016-10001-16647 to modify rooftop equipment Permit type: Bldg-alter/repair | Permit status: Permit expired | Current use: Commercial | Permit id: 10016-10003-166 | |||||
SCORE 99 Replace/upgrade existing fire pump. New fire sprinklers in fire pump r Date: May 16, 2011 Contractor: Jose Gutierrez Permit type: Fire sprinkler | Permit status: Permit finaled | Current use: Commercial | Permit id: 11043-10000-010 | |||||
SCORE 64 Removal and recompaction under proposed tank Permit type: Grading | Permit status: Permit finaled | Current use: Commercial | Permit id: 11030-10000-053 | |||||
SCORE 99 Install (1) elevator (4) stops. Permit type: Elevator | Permit status: Permit finaled | Current use: Apartment | Permit id: 12046-10000-009 | |||||
SCORE 64 New switchboards and m. C. Panels for a water treatment plant. Date: January 26, 2012 Contractor: Timothy Gutkowski Permit type: Electrical | Permit status: Permit closed | Current use: Commercial | Permit id: 11041-10000-240 | |||||
SCORE 73 Relocate an existing 6" riser and cross main. Relocate (21) fire spri Date: September 15, 2011 Contractor: Art Stoll Permit type: Fire sprinkler | Permit status: Permit finaled | Current use: Commercial | Permit id: 11043-10000-023 | |||||
SCORE 100 Interior renovation of existing manufacturing area. Add circuits, moto Date: October 25, 2012 Contractor: Steve Tomko Permit type: Electrical | Permit status: Permit finaled | Current use: Commercial | Permit id: 10041-10000-248 | |||||
SCORE 82 Temporary shoring for max 11 deep excavation along portion of the eas Permit type: Nonbldg-new | Permit status: Permit finaled | Current use: Commercial | Permit id: 12020-10000-012 | |||||
SCORE 100 Hvac Date: January 17, 2012 Contractor: Russell Wright Permit status: Permit finaled | Current use: Commercial | Permit id: 12044-90000-004 | |||||
SCORE 59 Supplemental application to add perimeter drain system and duplex sump Date: July 13, 2011 Contractor: Andres Robles Permit type: Plumbing | Permit status: Permit finaled | Current use: Commercial | Permit id: 10042-10001-194 | |||||
SCORE 56 Temporary constuction service for a 4 story building (bldg 8) Date: November 22, 2011 Contractor: Mark Voegele Permit type: Electrical | Permit status: Permit closed | Current use: Commercial | Permit id: 11041-10000-234 | |||||
SCORE 100 Voluntary structural improvements to existing rooftop mechanical platf Permit type: Bldg-alter/repair | Permit status: Permit finaled | Current use: Commercial | Permit id: 10016-10000-220 | |||||
SCORE 93 Add water curtain heads inside boiler room. Date: July 1, 2013 Contractor: Brad Brown Permit type: Fire sprinkler | Permit status: Permit finaled | Current use: Commercial | Permit id: 13043-10000-018 | |||||
Electrical Date: July 8, 2013 Permit status: Permit closed | Current use: Commercial | Permit id: 13041-10000-178 | |||||
SCORE 99 Electrical Date: September 13, 2013 Contractor: German Permit status: Permit expired | Current use: Commercial | Permit id: 13041-10000-252 | |||||
SCORE 97 Electrical Date: June 16, 2015 Contractor: Robert Nichols Permit status: Permit finaled | Current use: Commercial | Permit id: 15041-90000-186 | |||||
SCORE 98 Fire sprinkler Date: July 8, 2013 Contractor: Joseph Peterson Permit status: Permit finaled | Current use: Commercial | Permit id: 13043-90000-021 | |||||
Electrical Date: July 3, 2014 Permit status: Permit finaled | Current use: Commercial | Permit id: 14041-20000-180 | |||||
Electrical Date: June 15, 2015 Permit status: Permit finaled | Current use: Commercial | Permit id: 15041-10000-184 | |||||
SCORE 98 Electrical Date: April 17, 2015 Contractor: Michael Permit status: Permit finaled | Current use: Commercial | Permit id: 15041-10000-114 | |||||
SCORE 79 Hvac Date: June 26, 2013 Contractor: Nolan Borden Permit status: Permit finaled | Current use: Commercial | Permit id: 13044-90000-066 | |||||
SCORE 100 Renovation of existing building for new boiler; relocate door, constru Permit type: Bldg-alter/repair | Permit status: Issued | Current use: Commercial | Permit id: 13016-10000-148 | |||||
SCORE 100 Hvac Date: July 22, 2014 Contractor: Russell Wright Permit status: Issued | Current use: Commercial | Permit id: 14044-90000-072 | |||||
SCORE 91 Installation of 3" gas piping to serve a new listed gas train in boile Date: September 27, 2013 Contractor: Saum Nour Permit type: Plumbing | Permit status: Issued | Current use: Commercial | Permit id: 13042-10000-189 | |||||
Installation of an oil sperator (rr#5360), and revisions to venting Date: September 26, 2013 Permit type: Plumbing | Permit status: Permit finaled | Current use: Commercial | Permit id: 13042-10001-120 | |||||
SCORE 79 Electrical Date: July 10, 2014 Contractor: Nolan Borden Permit status: Permit finaled | Current use: Commercial | Permit id: 14041-90000-186 | |||||
SCORE 100 Hvac Date: June 6, 2014 Contractor: Richard Fazzolare Permit status: Permit finaled | Current use: Commercial | Permit id: 14044-90000-054 | |||||
SCORE 77 Electrical Date: July 2, 2015 Contractor: Jason Tan Permit status: Permit finaled | Current use: Commercial | Permit id: 15041-90000-211 | |||||
SCORE 100 Electrical Date: July 10, 2014 Contractor: Mahmoud Fazlali Permit status: Permit finaled | Current use: Commercial | Permit id: 14041-10000-185 | |||||
SCORE 93 Installation of esfr dry pendent heads and mains serving frozen storag Date: June 26, 2014 Contractor: Brad Brown Permit type: Fire sprinkler | Permit status: Permit finaled | Current use: Commercial | Permit id: 14043-10000-020 | |||||
At the baxter pharmaucetical facility, expanding the existing fire war Date: January 24, 2013 Permit type: Electrical | Permit status: Issued | Current use: Public safety only | Permit id: 13041-10000-019 | |||||
SCORE 87 Electrical Date: July 11, 2013 Contractor: Barry Balcom Permit status: Permit finaled | Current use: Commercial | Permit id: 13041-90000-183 | |||||
SCORE 93 Electrical Date: April 24, 2013 Contractor: Lance Miller Permit status: Permit finaled | Current use: Commercial | Permit id: 13041-90000-105 | |||||
SCORE 91 Pressure vessel Date: August 29, 2013 Contractor: William Albert Permit status: Permit finaled | Current use: Commercial | Permit id: 13045-10000-002 | |||||
Install emergency drain line. Date: July 2, 2013 Value: $40,000 Permit type: Plumbing | Permit status: Permit finaled | Current use: Commercial | Permit id: 13042-20000-120 | |||||
SCORE 98 Electrical Date: December 29, 2014 Contractor: Michael Permit status: Permit finaled | Current use: Commercial | Permit id: 14041-20000-357 | |||||
SCORE 59 Deffered submittal of cold-formed framing of all exterior walls & cano Permit type: Bldg-alter/repair | Permit status: Permit finaled | Current use: Commercial | Permit id: 13016-10000-004 | |||||
SCORE 93 Fire sprinkler Date: August 2, 2013 Contractor: Brad Brown Permit status: Permit finaled | Current use: Commercial | Permit id: 13043-10000-021 | |||||
SCORE 76 Plan check for new switchboard and equipment for building 1 at baxter Date: December 10, 2013 Contractor: German Garcia Permit type: Electrical | Permit status: Permit finaled | Current use: Commercial | Permit id: 13041-10000-252 | |||||
SCORE 91 Electrical Date: July 28, 2014 Contractor: Veronica Cobain Permit status: Permit finaled | Current use: Commercial | Permit id: 14041-10000-202 | |||||
SCORE 74 Install storage rack inside existing freezer & cold storage rooms. Permit type: Bldg-alter/repair | Permit status: Permit finaled | Current use: Commercial | Permit id: 14016-10000-207 | |||||
SCORE 59 Hvac Date: June 16, 2015 Contractor: Michael Gadalla Permit status: Permit finaled | Current use: Commercial | Permit id: 15044-10000-058 | |||||
T. I., install new hvac system in 7 sq ft, rooms 1183 &1184, located Date: July 16, 2013 Permit type: Hvac | Permit status: Permit finaled | Current use: Commercial | Permit id: 13044-10000-068 | |||||
SCORE 98 Fire sprinkler Date: July 10, 2015 Contractor: Joseph Peterson Permit status: Permit finaled | Current use: Commercial | Permit id: 15043-90000-030 | |||||
SCORE 92 Hvac Date: August 13, 2013 Contractor: Eric Harley Permit status: Permit finaled | Current use: Commercial | Permit id: 12044-10003-016 | |||||
SCORE 59 Extension of exterior loading dock with new extended canopy. New elev Permit type: Bldg-addition | Permit status: Issued | Current use: Commercial | Permit id: 13014-10000-021 | |||||
SCORE 59 Tenant improvement (43 sf) of an existing 168,368 sf manufacturing b Permit type: Bldg-alter/repair | Permit status: Permit finaled | Current use: Commercial | Permit id: 13016-10000-088 | |||||
SCORE 99 Curtain wall and glazing; deferred permit Permit type: Bldg-alter/repair | Permit status: Permit finaled | Current use: Commercial | Permit id: 12010-10003-000 | |||||
SCORE 100 Electrical Date: July 24, 2013 Contractor: Mahmoud Fazlali Permit status: Permit finaled | Current use: Commercial | Permit id: 13041-10000-196 | |||||
SCORE 100 Perform voluntary structural strengthening of existing roof equipment Permit type: Bldg-alter/repair | Permit status: Permit finaled | Current use: Commercial | Permit id: 13016-10000-085 | |||||
Install fire sprinkler in new 5-story manufacturing support building. Date: January 10, 2013 Value: $15,000 Permit type: Fire sprinkler | Permit status: Permit finaled | Current use: Commercial | Permit id: 12043-10000-039 | |||||
SCORE 91 Tenant improvement of 3rd floor of existing office building. Permit type: Bldg-alter/repair | Permit status: Issued | Current use: Commercial | Permit id: 13016-10000-046 | |||||
SCORE 77 Electrical Date: March 20, 2014 Contractor: Jason Tan Permit status: Permit finaled | Current use: Commercial | Permit id: 14041-10000-074 | |||||
SCORE 59 Supplemental to permit# 12010-10000-00078 to plan check deferred submi Permit type: Bldg-alter/repair | Permit status: Permit finaled | Current use: Commercial | Permit id: 12010-10004-000 | |||||
SCORE 100 Tenant improvement for basement mechanical shop area, 803 s. F. Permit type: Bldg-alter/repair | Permit status: Permit finaled | Current use: Commercial | Permit id: 13016-10000-246 | |||||
SCORE 100 New fire alarm system for a 2-story healthcare office building.((((((( Date: April 25, 2013 Contractor: Veronica Cobian Permit type: Electrical | Permit status: Permit expired | Current use: Commercial | Permit id: 12041-10001-083 | |||||
SCORE 65 Interior remodel (1,375 sf) of existing gown rooms into both de-gown a Permit type: Bldg-alter/repair | Permit status: Issued | Current use: Commercial | Permit id: 15016-10000-072 | |||||
SCORE 64 Two new non-illuminated wall signs (46"x5-0" & 2-0"x2-3"). Sign re Permit type: Sign | Permit status: Permit finaled | Current use: Onsite | Permit id: 13048-10000-007 | |||||
SCORE 59 Plumbing Date: August 28, 2013 Contractor: Jack Brunner Permit status: Permit finaled | Current use: Commercial | Permit id: 13042-90000-170 | |||||
SCORE 100 Plumbing Date: July 8, 2013 Contractor: Jeff Riddle Permit status: Permit finaled | Current use: Commercial | Permit id: 13042-90000-130 | |||||
SCORE 100 Proposed install new bearing partitions around equipment to control ai Permit type: Bldg-alter/repair | Permit status: Permit finaled | Current use: Commercial | Permit id: 14016-10000-108 | |||||
New packaged unit for "teardown" room. Positive pressure relative to Date: April 17, 2015 Permit type: Hvac | Permit status: Issued | Current use: Commercial | Permit id: 15044-10000-005 | |||||
SCORE 59 Install a hazardous material storage pre fab building Permit type: Bldg-new | Permit status: Cofo in progress | Current use: Commercial | Permit id: 14010-10000-032 | |||||
SCORE 65 Plumbing Date: July 1, 2014 Contractor: Scott Stevenson Permit status: Permit finaled | Current use: Commercial | Permit id: 14042-10000-123 | |||||
SCORE 100 (1) set of illum channel ltr wall sign with exterior raceway, 42. 65 sf Permit type: Sign | Permit status: Permit finaled | Current use: Onsite | Permit id: 13048-10000-011 | |||||
SCORE 91 Interior non-structural tenant improvement to existing manufacturing b Permit type: Bldg-alter/repair | Permit status: Permit finaled | Current use: Commercial | Permit id: 13016-10000-141 | |||||
SCORE 100 Addition of an air handling unit and replacing one existing chiller wi Permit type: Hvac | Permit status: Issued | Current use: Commercial | Permit id: 14044-20000-066 | |||||
Interior remodel to create 7 sqft mechancial equipment room at 2nd f Date: June 7, 2013 Value: $120,000 Permit type: Bldg-alter/repair | Permit status: Permit finaled | Current use: Commercial | Permit id: 13016-10000-077 | |||||
Max high site light pole bases (total of 10) near north and west o Date: June 19, 2013 Value: $40,000 Permit type: Nonbldg-new | Permit status: Issued | Current use: Commercial | Permit id: 13020-10000-014 | |||||
SCORE 61 Electrical Date: June 26, 2015 Contractor: Michael Mcmahan Permit status: Permit finaled | Current use: Commercial | Permit id: 15041-20000-202 | |||||
SCORE 96 Civiil site plan for building sewer. Baxter health care corp. Date: June 19, 2015 Contractor: Barbara Hall Permit type: Plumbing | Permit status: Permit finaled | Current use: Commercial | Permit id: 15042-20000-123 | |||||
SCORE 75 Supplemental to permit #12010-10000-00078 to revise west entry stair, Permit type: Bldg-alter/repair | Permit status: Permit finaled | Current use: Commercial | Permit id: 12010-10005-000 | |||||
SCORE 100 Fire sprinkler Date: January 20, 2015 Contractor: Frank Mone Permit status: Permit finaled | Current use: Commercial | Permit id: 15043-90000-002 | |||||
SCORE 91 Pharmaceutical manufacturing. Expansion of 800a bus. Ti of 7 sq ft. Date: July 11, 2013 Contractor: William Albert Permit type: Electrical | Permit status: Permit finaled | Current use: Commercial | Permit id: 13041-10000-105 | |||||
SCORE 100 Install new vertical material lift for (e) platform & install new non Permit type: Bldg-alter/repair | Permit status: Permit finaled | Current use: Commercial | Permit id: 14016-10000-127 | |||||
SCORE 100 Replace rooftop hvac unit on existing platform with structural upgrade Permit type: Bldg-alter/repair | Permit status: Issued | Current use: Commercial | Permit id: 14016-10000-126 | |||||
Install (1) illuminated channel letters wall sign (28" x 16). Sign Date: January 18, 2013 Value: $3,200 Permit type: Sign | Permit status: Permit finaled | Current use: Onsite | Permit id: 13048-10000-001 | |||||
SCORE 100 Install new fume hood & roof-top exhaust fan in existing building. Permit type: Bldg-alter/repair | Permit status: Permit finaled | Current use: Commercial | Permit id: 14016-10000-046 | |||||
Hvac Date: July 3, 2013 Value: $250,000 Permit status: Permit finaled | Current use: Commercial | Permit id: 13044-20000-069 | |||||
SCORE 97 Replace mechanical air compressor and heat exchange equipment on exist Permit type: Bldg-alter/repair | Permit status: Issued | Current use: Commercial | Permit id: 13016-10000-153 | |||||
SCORE 99 3 traction elevators. Date: April 12, 2013 Contractor: Maricela Estrada Permit type: Elevator | Permit status: Permit finaled | Current use: Commercial | Permit id: 13046-10000-002 | |||||
SCORE 100 Replace rooftop hvac equipment and add structural bracing to exist pla Permit type: Bldg-alter/repair | Permit status: Issued | Current use: Commercial | Permit id: 14016-10000-105 | |||||
SCORE 96 Fire protection system. Rereoute underground fire protection piping. Permit type: Fire sprinkler | Permit status: Permit finaled | Current use: Commercial | Permit id: 13043-10000-009 | |||||
SCORE 59 Installation of 1 fume hood in building 8 on the 2nd floor of a 2 sto Date: May 28, 2014 Contractor: Libby Virtue Permit type: Hvac | Permit status: Permit finaled | Current use: Commercial | Permit id: 14044-10000-023 | |||||
SCORE 69 Electrical Date: July 17, 2013 Contractor: Karol Unilowski Permit status: Permit finaled | Current use: Commercial | Permit id: 13041-10000-189 | |||||
SCORE 59 Hvac Date: April 9, 2013 Contractor: Christian Raabe Permit status: Permit finaled | Current use: Commercial | Permit id: 13044-10000-036 | |||||
Building drains and sewer lines. Construct 6" sanitary sewer piping f Date: May 9, 2013 Value: $40,000 Permit type: Plumbing | Permit status: Permit finaled | Current use: Commercial | Permit id: 13042-20000-089 | |||||
SCORE 100 Plancheckf for power and energy. Tenant improvement . Adding 3 new pu Date: December 30, 2014 Contractor: Steve Tomko Permit type: Electrical | Permit status: Permit finaled | Current use: Commercial | Permit id: 14041-10000-216 | |||||
SCORE 100 Replace rooftop hvac one (1) equipment, and add structural steel suppo Permit type: Bldg-alter/repair | Permit status: Issued | Current use: Commercial | Permit id: 14016-10000-110 | |||||
SCORE 64 Remodel existing bathrooms, painting existing corridor (walls and door Permit type: Bldg-alter/repair | Permit status: Permit finaled | Current use: Commercial | Permit id: 13014-10000-012 | |||||
SCORE 96 Install 4" wm and 4" potable water service stub out. Building # 8 wate Permit type: Plumbing | Permit status: Permit finaled | Current use: Commercial | Permit id: 13042-10000-000 | |||||
SCORE 86 Plumbing Date: May 26, 2014 Contractor: Daniel Hall Permit status: Permit finaled | Current use: Commercial | Permit id: 14042-90000-097 | |||||
SCORE 100 Remove interior partitions for larger mfg suite with new header beam Permit type: Bldg-alter/repair | Permit status: Permit finaled | Current use: Commercial | Permit id: 13016-10000-092 | |||||
SCORE 59 Tenant improvement-installation of restroom water fixtures on office s Date: April 9, 2013 Contractor: Russ Gault Permit type: Plumbing | Permit status: Permit finaled | Current use: Commercial | Permit id: 13042-10000-059 | |||||
SCORE 63 Install (1) in-house 66" diameter x 510" height (660-gallon) tank on Permit type: Bldg-alter/repair | Permit status: Issued | Current use: Commercial | Permit id: 15016-20000-128 | |||||
SCORE 89 Elevator Date: July 10, 2013 Contractor: Christina Siebold Permit status: Permit finaled | Current use: Commercial | Permit id: 13046-90000-009 | |||||
SCORE 67 Electrical Date: August 1, 2016 Contractor: Roger Villanueva Permit status: Issued | Current use: Commercial | Permit id: 16041-10000-270 | |||||
SCORE 75 Electrical Date: August 10, 2016 Contractor: Jerzy Tarlowski Permit status: Issued | Current use: Commercial | Permit id: 16041-10000-283 | |||||
SCORE 95 Electrical Date: June 4, 2014 Contractor: Red Hawk Fire And Security Ca Llc Permit status: Permit finaled | Current use: Commercial | Permit id: 14041-10000-148 | |||||
SCORE 82 At the baxter pharmaucetical facility, expanding the existing fire war Date: January 24, 2013 Contractor: Chubb Fire And Security Ca Inc Permit type: Electrical | Permit status: Issued | Current use: Public safety only | Permit id: 13041-10000-019 | |||||
SCORE 95 Electrical Date: April 17, 2015 Contractor: Red Hawk Fire And Security Ca Llc Permit status: Permit finaled | Current use: Commercial | Permit id: 15041-10000-114 | |||||
SCORE 95 Electrical Date: March 21, 2013 Contractor: Red Hawk Fire And Security Ca Llc Permit status: Issued | Current use: Public safety only | Permit id: 13041-10001-019 | |||||
SCORE 59 New packaged unit for "teardown" room. Positive pressure relative to Date: April 17, 2015 Permit type: Hvac | Permit status: Issued | Current use: Commercial | Permit id: 15044-10000-005 | |||||
SCORE 96 Electrical Date: July 8, 2013 Contractor: California Electrical Services Permit status: Permit closed | Current use: Commercial | Permit id: 13041-10000-178 | |||||
SCORE 77 Electrical Date: July 3, 2014 Contractor: Diamond Bar Electric Inc Permit status: Permit finaled | Current use: Commercial | Permit id: 14041-20000-180 | |||||
SCORE 96 Electrical Date: June 15, 2015 Contractor: California Electrical Services Permit status: Permit finaled | Current use: Commercial | Permit id: 15041-10000-184 | |||||
SCORE 88 Installation of an oil sperator (rr#5360), and revisions to venting Date: September 26, 2013 Contractor: D P R Construction A General Partnership Permit type: Plumbing | Permit status: Permit finaled | Current use: Commercial | Permit id: 13042-10001-120 | |||||
SCORE 88 Electrical Date: July 11, 2013 Contractor: Vertical Construction Inc Permit status: Permit expired | Current use: Commercial | Permit id: 13041-10000-183 | |||||
SCORE 69 Hvac Date: June 11, 2015 Contractor: Master Cooling Permit status: Permit finaled | Current use: Commercial | Permit id: 15044-20000-057 | |||||
SCORE 93 Electrical Date: February 3, 2015 Contractor: Building Electronic Controls Inc Permit status: Issued | Current use: Commercial | Permit id: 15041-10000-031 | |||||
SCORE 86 Plumbing Date: January 29, 2013 Contractor: De Bella Mechanical Inc Permit status: Permit finaled | Current use: Commercial | Permit id: 13042-10000-016 | |||||
SCORE 100 Construct floor access hatch and ladder at inerior mechanical room at Permit type: Bldg-alter/repair | Permit status: Permit finaled | Current use: Commercial | Permit id: 16016-10000-145 | |||||
SCORE 89 Construct new equipment pad (2-1. 5" x 2-0") on site. Permit type: Nonbldg-new | Permit status: Permit finaled | Current use: Commercial | Permit id: 16020-10000-026 | |||||
SCORE 70 Construct new equipment platform on 1st floor of building b5. Permit type: Bldg-alter/repair | Permit status: Permit finaled | Current use: Commercial | Permit id: 16016-10000-175 | |||||
SCORE 64 Construct new retaining wall and enlarge ( e ) concrete vehicle contai Permit type: Nonbldg-new | Permit status: Issued | Current use: Commercial | Permit id: 16020-10000-031 | |||||
SCORE 64 Site grading for new retaining wall and conrete containment dad . Permit type: Grading | Permit status: Issued | Current use: Commercial | Permit id: 16030-10000-075 | |||||
SCORE 95 Electrical Date: July 5, 2013 Contractor: Sasco Permit status: Permit finaled | Current use: Commercial | Permit id: 13041-10000-177 | |||||
SCORE 98 T. I., install new hvac system in 7 sq ft, rooms 1183 &1184, located Date: July 16, 2013 Contractor: Thermalair Inc Permit type: Hvac | Permit status: Permit finaled | Current use: Commercial | Permit id: 13044-10000-068 | |||||
SCORE 100 Electrical Date: March 13, 2014 Contractor: Dynalectric Company Permit status: Permit finaled | Current use: Commercial | Permit id: 14041-20000-067 | |||||
SCORE 96 Electrical Date: May 23, 2014 Contractor: California Electrical Services Permit status: Permit finaled | Current use: Commercial | Permit id: 14041-10000-138 | |||||
SCORE 94 Electrical Date: September 27, 2013 Contractor: A R Construction Permit status: Permit finaled | Current use: Commercial | Permit id: 13041-10000-268 | |||||
SCORE 72 Install fire sprinkler in new 5-story manufacturing support building. Permit type: Fire sprinkler | Permit status: Permit finaled | Current use: Commercial | Permit id: 12043-10000-039 | |||||
SCORE 93 Max high site light pole bases (total of 10) near north and west o Permit type: Nonbldg-new | Permit status: Issued | Current use: Commercial | Permit id: 13020-10000-014 | |||||
SCORE 93 Hvac Permit status: Permit finaled | Current use: Commercial | Permit id: 13044-20000-069 | |||||
SCORE 89 Pressure vessel Date: September 10, 2013 Contractor: Cannon Building Services Inc Permit status: Permit finaled | Current use: Commercial | Permit id: 13045-10000-002 | |||||
SCORE 65 Plumbing Date: September 4, 2015 Contractor: Hall B L Inc Permit status: Issued | Current use: Commercial | Permit id: 15042-10000-179 | |||||
SCORE 59 Plumbing Date: July 10, 2013 Contractor: Tonkin Plumbing Inc Permit status: Permit finaled | Current use: Commercial | Permit id: 13042-10000-132 | |||||
SCORE 65 Building drains and sewer lines. Construct 6" sanitary sewer piping f Permit type: Plumbing | Permit status: Permit finaled | Current use: Commercial | Permit id: 13042-20000-089 | |||||
SCORE 88 Install emergency drain line. Permit type: Plumbing | Permit status: Permit finaled | Current use: Commercial | Permit id: 13042-20000-120 | |||||
SCORE 74 Hvac Date: April 9, 2014 Contractor: Tricor Mechanical Inc Permit status: Permit expired | Current use: Commercial | Permit id: 14044-10000-032 | |||||
SCORE 100 Tenant improvement - install roof top dehumidifiction unit with associ Permit type: Hvac | Permit status: Permit expired | Current use: Commercial | Permit id: 14044-20000-066 | |||||
SCORE 95 Electrical Date: June 4, 2014 Contractor: Red Hawk Fire And Security Ca Llc Permit status: Permit finaled | Current use: Commercial | Permit id: 14041-10000-148 | |||||
SCORE 91 Interior remodel to create 7 sqft mechancial equipment room at 2nd f Permit type: Bldg-alter/repair | Permit status: Permit finaled | Current use: Commercial | Permit id: 13016-10000-077 | |||||
SCORE 99 Tenant improvements/ remodel. Add (2) new 120/208v, 150a pannelboards Date: July 5, 2013 Contractor: Nolan Permit type: Electrical | Permit status: Permit finaled | Current use: Commercial | Permit id: 13041-10000-115 | |||||
SCORE 95 Electrical Date: March 21, 2013 Contractor: Red Hawk Fire And Security Ca Llc Permit status: Issued | Current use: Public safety only | Permit id: 13041-10001-019 | |||||
SCORE 63 Cut non-bearing partitions for new interior door/frames; relocated equ Permit type: Bldg-alter/repair | Permit status: Permit finaled | Current use: Commercial | Permit id: 14016-10000-091 | |||||
SCORE 97 (1) illuminated wall sign located @ parking structure Permit type: Sign | Permit status: Issued | Current use: Onsite | Permit id: 16048-10000-026 | |||||
SCORE 95 Electrical Date: April 17, 2015 Contractor: Red Hawk Fire And Security Ca Llc Permit status: Permit finaled | Current use: Commercial | Permit id: 15041-10000-114 | |||||
SCORE 100 Install (1) illuminated channel letters wall sign (28" x 16). Sign Permit type: Sign | Permit status: Permit finaled | Current use: Onsite | Permit id: 13048-10000-001 | |||||
SCORE 95 Install mechanical platform/lift in rooms #1008 and #1009 Permit type: Bldg-alter/repair | Permit status: Permit finaled | Current use: Commercial | Permit id: 13016-10000-059 | |||||
SCORE 95 Electrical Date: May 15, 2013 Contractor: Red Hawk Fire And Security Ca Llc Permit status: Permit finaled | Current use: Commercial | Permit id: 13041-10000-125 | |||||
SCORE 97 (1) illuminated single faced monument sign 5-9" x 11-3"; reading "b Permit type: Sign | Permit status: Permit finaled | Current use: Onsite | Permit id: 15048-10000-015 | |||||
SCORE 56 Date: November 3, 2017 Contractor: Steve Moody Permit status: Issued | Current use: Commercial | Permit id: 17042-10000-273 | |||||
SCORE 100 Date: October 30, 2017 Contractor: Russell Wright Permit status: Issued | Current use: Commercial | Permit id: 17044-90000-136 | |||||
SCORE 79 Date: November 14, 2017 Contractor: Rachel Fuhriman Permit status: Issued | Current use: Public safety only | Permit id: 17041-90000-412 | |||||
SCORE 95 Date: December 7, 2017 Contractor: Thermal Concepts Inc Permit status: Issued | Current use: Commercial | Permit id: 17044-40000-152 | |||||
SCORE 64 Plan check for power and title 24. T. I. Within building 7 for compute Date: October 12, 2017 Contractor: Ayal Erlich Permit status: Issued | Current use: Commercial | Permit id: 17041-10000-203 | |||||
SCORE 100 Tenant improvement within bldg 7, work includes new non-bearing partit Permit status: Issued | Current use: Commercial | Permit id: 17016-10000-161 | |||||
SCORE 88 Minor tenant imrpovement within (e) warehouse, new electrical room, no Permit status: Issued | Current use: Commercial | Permit id: 17016-10000-176 | |||||
SCORE 88 Proposed equipment pads for backup generator and equipments on site. Permit status: Issued | Current use: Commercial | Permit id: 17020-10000-019 | |||||
SCORE 63 Adding two w12x 26 beams to an existing platform to set new water filt Permit status: Issued | Current use: Commercial | Permit id: 17016-10000-312 | |||||
SCORE 56 Tenant improvement for 2nd floor. Relocation of doors and partition i Permit status: Issued | Current use: Commercial | Permit id: 17016-10000-359 | |||||
SCORE 56 Pc for power for install of new computer server room system. Installin Date: December 15, 2017 Contractor: Pius Kiefel Permit status: Issued | Current use: Commercial | Permit id: 17041-10000-396 | |||||
SCORE 97 Date: October 24, 2017 Contractor: Jack Permit status: Permit finaled | Current use: Commercial | Permit id: 17044-10000-134 | |||||
SCORE 100 Date: December 18, 2017 Contractor: Frank Mone Permit status: Issued | Current use: Commercial | Permit id: 17043-90000-064 | |||||
SCORE 93 Add water curtain heads inside boiler room. Date: July 1, 2013 Contractor: Brad Brown Permit status: Permit finaled | Current use: Commercial | Permit id: 13043-10000-018 | |||||
SCORE 99 Date: September 13, 2013 Contractor: German Permit status: Permit expired | Current use: Commercial | Permit id: 13041-10000-252 | |||||
SCORE 97 Date: June 16, 2015 Contractor: Robert Nichols Permit status: Permit finaled | Current use: Commercial | Permit id: 15041-90000-186 | |||||
SCORE 61 Pumbing tenant improvement on 5th floor for lab renovation. Date: March 31, 2017 Contractor: Bill Albert Permit status: Permit finaled | Current use: Commercial | Permit id: 16042-10000-233 | |||||
SCORE 98 Date: July 8, 2013 Contractor: Joseph Peterson Permit status: Permit finaled | Current use: Commercial | Permit id: 13043-90000-021 | |||||
SCORE 91 Hvac tenant improvement on 5th floor of existing 5-story commercial bu Date: March 2, 2017 Contractor: William Albert Permit status: Permit finaled | Current use: Commercial | Permit id: 16044-10000-124 | |||||
SCORE 96 Date: July 8, 2013 Contractor: California Electrical Services Permit status: Permit closed | Current use: Commercial | Permit id: 13041-10000-178 | |||||
SCORE 77 Date: July 3, 2014 Contractor: Diamond Bar Electric Inc Permit status: Permit finaled | Current use: Commercial | Permit id: 14041-20000-180 | |||||
SCORE 100 Renovation of existing building for new boiler; relocate door, constru Permit status: Permit finaled | Current use: Commercial | Permit id: 13016-10000-148 | |||||
SCORE 96 Date: June 15, 2015 Contractor: California Electrical Services Permit status: Permit finaled | Current use: Commercial | Permit id: 15041-10000-184 | |||||
SCORE 98 Date: April 17, 2015 Contractor: Michael Permit status: Permit finaled | Current use: Commercial | Permit id: 15041-10000-114 | |||||
SCORE 59 New packaged unit for "teardown" room. Positive pressure relative to Date: April 17, 2015 Permit status: Issued | Current use: Commercial | Permit id: 15044-10000-005 | |||||
SCORE 100 Fire sprinkler system tenant improvement to 5th floor. Date: April 5, 2017 Contractor: Frank Mone Permit status: Permit finaled | Current use: Commercial | Permit id: 17043-10000-017 | |||||
SCORE 65 Interior remodel (1,375 sf) of existing gown rooms into both de-gown a Permit status: Permit finaled | Current use: Commercial | Permit id: 15016-10000-072 | |||||
SCORE 59 Install a hazardous material storage pre fab building Permit status: Cofo in progress | Current use: Commercial | Permit id: 14010-10000-032 | |||||
SCORE 65 Date: July 1, 2014 Contractor: Scott Stevenson Permit status: Permit finaled | Current use: Commercial | Permit id: 14042-10000-123 | |||||
SCORE 100 (1) set of illum channel ltr wall sign with exterior raceway, 42. 65 sf Permit status: Permit finaled | Current use: Onsite | Permit id: 13048-10000-011 | |||||
SCORE 91 Interior non-structural tenant improvement to existing manufacturing b Permit status: Permit finaled | Current use: Commercial | Permit id: 13016-10000-141 | |||||
SCORE 70 Construct new equipment platform on 1st floor of building b5. Permit status: Permit finaled | Current use: Commercial | Permit id: 16016-10000-175 | |||||
SCORE 91 Interior remodel to create 7 sqft mechancial equipment room at 2nd f Permit status: Permit finaled | Current use: Commercial | Permit id: 13016-10000-077 | |||||
SCORE 64 Construct new retaining wall and enlarge ( e ) concrete vehicle contai Permit status: Permit finaled | Current use: Commercial | Permit id: 16020-10000-031 | |||||
SCORE 93 Max high site light pole bases (total of 10) near north and west o Permit status: Issued | Current use: Commercial | Permit id: 13020-10000-014 | |||||
SCORE 61 Date: June 26, 2015 Contractor: Michael Mcmahan Permit status: Permit finaled | Current use: Commercial | Permit id: 15041-20000-202 | |||||
SCORE 96 Civiil site plan for building sewer. Baxter health care corp. Date: June 19, 2015 Contractor: Barbara Hall Permit status: Permit finaled | Current use: Commercial | Permit id: 15042-20000-123 | |||||
SCORE 75 Supplemental to permit #12010-10000-00078 to revise west entry stair, Permit status: Permit finaled | Current use: Commercial | Permit id: 12010-10005-000 | |||||
SCORE 100 Date: January 20, 2015 Contractor: Frank Mone Permit status: Permit finaled | Current use: Commercial | Permit id: 15043-90000-002 | |||||
SCORE 91 Pharmaceutical manufacturing. Expansion of 800a bus. Ti of 7 sq ft. Date: July 11, 2013 Contractor: William Albert Permit status: Permit finaled | Current use: Commercial | Permit id: 13041-10000-105 | |||||
SCORE 100 Install new vertical material lift for (e) platform & install new non Permit status: Permit finaled | Current use: Commercial | Permit id: 14016-10000-127 | |||||
SCORE 100 Date: June 27, 2013 Contractor: Mahmoud Fazlali Permit status: Permit finaled | Current use: Commercial | Permit id: 13041-10000-170 | |||||
SCORE 100 Install (1) illuminated channel letters wall sign (28" x 16). Sign Permit status: Permit finaled | Current use: Onsite | Permit id: 13048-10000-001 | |||||
SCORE 95 Date: May 15, 2013 Contractor: Red Hawk Fire And Security Ca Llc Permit status: Permit finaled | Current use: Commercial | Permit id: 13041-10000-125 | |||||
SCORE 100 Install new fume hood & roof-top exhaust fan in existing building. Permit status: Permit finaled | Current use: Commercial | Permit id: 14016-10000-046 | |||||
SCORE 93 Permit status: Permit finaled | Current use: Commercial | Permit id: 13044-20000-069 | |||||
SCORE 97 Replace mechanical air compressor and heat exchange equipment on exist Permit status: Issued | Current use: Commercial | Permit id: 13016-10000-153 | |||||
SCORE 99 3 traction elevators. Date: April 12, 2013 Contractor: Maricela Estrada Permit status: Permit finaled | Current use: Commercial | Permit id: 13046-10000-002 | |||||
SCORE 75 Date: August 10, 2016 Contractor: Jerzy Tarlowski Permit status: Permit finaled | Current use: Commercial | Permit id: 16041-10000-283 | |||||
SCORE 95 Date: May 15, 2013 Contractor: Sasco Permit status: Permit finaled | Current use: Commercial | Permit id: 13041-10000-126 | |||||
SCORE 100 Replace rooftop hvac unit on existing platform with structural upgrade Permit status: Permit finaled | Current use: Commercial | Permit id: 14016-10000-126 | |||||
SCORE 89 Date: September 10, 2013 Contractor: Cannon Building Services Inc Permit status: Permit finaled | Current use: Commercial | Permit id: 13045-10000-002 | |||||
SCORE 65 Date: September 4, 2015 Contractor: Hall B L Inc Permit status: Issued | Current use: Commercial | Permit id: 15042-10000-179 | |||||
SCORE 96 Fire protection system. Rereoute underground fire protection piping. Permit status: Permit finaled | Current use: Commercial | Permit id: 13043-10000-009 | |||||
SCORE 59 Installation of 1 fume hood in building 8 on the 2nd floor of a 2 sto Date: May 28, 2014 Contractor: Libby Virtue Permit status: Permit finaled | Current use: Commercial | Permit id: 14044-10000-023 | |||||
SCORE 100 Addition of an air handling unit and replacing one existing chiller wi Permit status: Permit expired | Current use: Commercial | Permit id: 14044-20000-066 | |||||
SCORE 95 Date: May 28, 2015 Contractor: Red Hawk Fire And Security Ca Llc Permit status: Permit finaled | Current use: Commercial | Permit id: 15041-10000-162 | |||||
SCORE 69 Date: July 17, 2013 Contractor: Karol Unilowski Permit status: Permit finaled | Current use: Commercial | Permit id: 13041-10000-189 | |||||
SCORE 59 Date: July 10, 2013 Contractor: Tonkin Plumbing Inc Permit status: Permit finaled | Current use: Commercial | Permit id: 13042-10000-132 | |||||
SCORE 59 Date: April 9, 2013 Contractor: Christian Raabe Permit status: Permit finaled | Current use: Commercial | Permit id: 13044-10000-036 | |||||
SCORE 65 Building drains and sewer lines. Construct 6" sanitary sewer piping f Permit status: Permit finaled | Current use: Commercial | Permit id: 13042-20000-089 | |||||
SCORE 74 Date: April 9, 2014 Contractor: Tricor Mechanical Inc Permit status: Permit expired | Current use: Commercial | Permit id: 14044-10000-032 | |||||
SCORE 59 Date: June 16, 2015 Contractor: Michael Gadalla Permit status: Permit finaled | Current use: Commercial | Permit id: 15042-10000-120 | |||||
SCORE 100 Plancheckf for power and energy. Tenant improvement . Adding 3 new pu Date: December 30, 2014 Contractor: Steve Tomko Permit status: Permit finaled | Current use: Commercial | Permit id: 14041-10000-216 | |||||
SCORE 100 Replace rooftop hvac one (1) equipment, and add structural steel suppo Permit status: Issued | Current use: Commercial | Permit id: 14016-10000-110 | |||||
SCORE 64 Remodel existing bathrooms, painting existing corridor (walls and door Permit status: Permit finaled | Current use: Commercial | Permit id: 13014-10000-012 | |||||
SCORE 96 Install 4" wm and 4" potable water service stub out. Building # 8 wate Permit status: Permit finaled | Current use: Commercial | Permit id: 13042-10000-000 | |||||
SCORE 86 Date: May 26, 2014 Contractor: Daniel Hall Permit status: Permit finaled | Current use: Commercial | Permit id: 14042-90000-097 | |||||
SCORE 77 Date: March 20, 2014 Contractor: Jason Tan Permit status: Permit finaled | Current use: Commercial | Permit id: 14041-10000-074 | |||||
SCORE 100 Remove interior partitions for larger mfg suite with new header beam Permit status: Permit finaled | Current use: Commercial | Permit id: 13016-10000-092 | |||||
SCORE 97 (1) illuminated wall sign located @ parking structure Permit status: Issued | Current use: Onsite | Permit id: 16048-10000-026 | |||||
SCORE 59 Tenant improvement-installation of restroom water fixtures on office s Date: April 9, 2013 Contractor: Russ Gault Permit status: Permit finaled | Current use: Commercial | Permit id: 13042-10000-059 | |||||
SCORE 100 Replace storage shed w new state approved unit with ada ramp. Permit status: Issued | Current use: Commercial | Permit id: 16010-10000-054 | |||||
SCORE 89 Date: July 10, 2013 Contractor: Christina Siebold Permit status: Permit finaled | Current use: Commercial | Permit id: 13046-90000-009 | |||||
SCORE 88 Install emergency drain line. Permit status: Permit finaled | Current use: Commercial | Permit id: 13042-20000-120 | |||||
SCORE 98 Date: December 29, 2014 Contractor: Michael Permit status: Permit finaled | Current use: Commercial | Permit id: 14041-20000-357 | |||||
SCORE 59 Deffered submittal of cold-formed framing of all exterior walls & cano Permit status: Permit finaled | Current use: Commercial | Permit id: 13016-10000-004 | |||||
SCORE 79 Date: June 26, 2013 Contractor: Nolan Borden Permit status: Permit finaled | Current use: Commercial | Permit id: 13044-90000-066 | |||||
SCORE 99 Tenant improvements remodel. Add (2) new 120 208v, 150a pannelboards Date: July 5, 2013 Contractor: Nolan Permit status: Permit finaled | Current use: Commercial | Permit id: 13041-10000-115 | |||||
SCORE 67 Date: August 1, 2016 Contractor: Roger Villanueva Permit status: Issued | Current use: Commercial | Permit id: 16041-10000-270 | |||||
SCORE 88 Installation of an oil sperator (rr#5360), and revisions to venting Date: September 26, 2013 Contractor: D P R Construction A General Partnership Permit status: Permit finaled | Current use: Commercial | Permit id: 13042-10001-120 | |||||
SCORE 93 Date: February 3, 2015 Contractor: Building Electronic Controls Inc Permit status: Permit expired | Current use: Commercial | Permit id: 15041-10000-031 | |||||
SCORE 79 Date: July 10, 2014 Contractor: Nolan Borden Permit status: Permit finaled | Current use: Commercial | Permit id: 14041-90000-186 | |||||
SCORE 95 Date: June 4, 2014 Contractor: Red Hawk Fire And Security Ca Llc Permit status: Permit finaled | Current use: Commercial | Permit id: 14041-10000-148 | |||||
SCORE 100 Date: June 6, 2014 Contractor: Richard Fazzolare Permit status: Permit finaled | Current use: Commercial | Permit id: 14044-90000-054 | |||||
SCORE 91 Installation of 3" gas piping to serve a new listed gas train in boile Date: September 27, 2013 Contractor: Saum Nour Permit status: Permit finaled | Current use: Commercial | Permit id: 13042-10000-189 | |||||
SCORE 77 Date: July 2, 2015 Contractor: Jason Tan Permit status: Permit finaled | Current use: Commercial | Permit id: 15041-90000-211 | |||||
SCORE 100 Date: July 10, 2014 Contractor: Mahmoud Fazlali Permit status: Permit finaled | Current use: Commercial | Permit id: 14041-10000-185 | |||||
SCORE 88 Date: July 11, 2013 Contractor: Vertical Construction Inc Permit status: Permit expired | Current use: Commercial | Permit id: 13041-10000-183 | |||||
SCORE 93 Installation of esfr dry pendent heads and mains serving frozen storag Date: June 26, 2014 Contractor: Brad Brown Permit status: Permit finaled | Current use: Commercial | Permit id: 14043-10000-020 | |||||
SCORE 82 At the baxter pharmaucetical facility, expanding the existing fire war Date: January 24, 2013 Contractor: Chubb Fire And Security Ca Inc Permit status: Issued | Current use: Public safety only | Permit id: 13041-10000-019 | |||||
SCORE 69 Date: June 11, 2015 Contractor: Master Cooling Permit status: Permit finaled | Current use: Commercial | Permit id: 15044-20000-057 | |||||
SCORE 95 Date: April 17, 2015 Contractor: Red Hawk Fire And Security Ca Llc Permit status: Permit finaled | Current use: Commercial | Permit id: 15041-10000-114 | |||||
SCORE 87 Date: July 11, 2013 Contractor: Barry Balcom Permit status: Permit finaled | Current use: Commercial | Permit id: 13041-90000-183 | |||||
SCORE 86 Date: January 29, 2013 Contractor: De Bella Mechanical Inc Permit status: Permit finaled | Current use: Commercial | Permit id: 13042-10000-016 | |||||
SCORE 93 Date: April 24, 2013 Contractor: Lance Miller Permit status: Permit finaled | Current use: Commercial | Permit id: 13041-90000-105 | |||||
SCORE 100 Construct floor access hatch and ladder at inerior mechanical room at Permit status: Permit finaled | Current use: Commercial | Permit id: 16016-10000-145 | |||||
SCORE 91 Date: August 29, 2013 Contractor: William Albert Permit status: Permit finaled | Current use: Commercial | Permit id: 13045-10000-002 | |||||
SCORE 61 Pc for ti to office, lab space. New 800a distribution board with step Date: February 1, 2017 Contractor: Bill Albert Permit status: Permit finaled | Current use: Commercial | Permit id: 16041-10000-380 | |||||
SCORE 95 Install mechanical platform lift in rooms #1008 and #1009 Permit status: Permit finaled | Current use: Commercial | Permit id: 13016-10000-059 | |||||
SCORE 100 Date: July 28, 2014 Contractor: Russell Wright Permit status: Permit finaled | Current use: Commercial | Permit id: 14044-90000-074 | |||||
SCORE 100 Date: April 25, 2017 Contractor: Mahmoud Fazlali Permit status: Permit finaled | Current use: Commercial | Permit id: 17041-10000-134 | |||||
SCORE 93 Date: August 2, 2013 Contractor: Brad Brown Permit status: Permit finaled | Current use: Commercial | Permit id: 13043-10000-021 | |||||
SCORE 76 Plan check for new switchboard and equipment for building 1 at baxter Date: December 10, 2013 Contractor: German Garcia Permit status: Permit finaled | Current use: Commercial | Permit id: 13041-10000-252 | |||||
SCORE 64 Warehouse and t. I. To manufacturing building infill door. New exit doo Permit status: Issued | Current use: Commercial | Permit id: 17016-10000-060 | |||||
SCORE 91 Date: July 28, 2014 Contractor: Veronica Cobain Permit status: Permit finaled | Current use: Commercial | Permit id: 14041-10000-202 | |||||
SCORE 100 Replace rooftop hvac equipment and add structural bracing to exist pla Permit status: Permit finaled | Current use: Commercial | Permit id: 14016-10000-105 | |||||
SCORE 74 Install storage rack inside existing freezer & cold storage rooms. Permit status: Permit finaled | Current use: Commercial | Permit id: 14016-10000-207 | |||||
SCORE 98 T. I., install new hvac system in 7 sq ft, rooms 1183 &1184, located Date: July 16, 2013 Contractor: Thermalair Inc Permit status: Permit finaled | Current use: Commercial | Permit id: 13044-10000-068 | |||||
SCORE 63 Cut non-bearing partitions for new interior door frames; relocated equ Permit status: Permit finaled | Current use: Commercial | Permit id: 14016-10000-091 | |||||
SCORE 95 Date: March 21, 2013 Contractor: Red Hawk Fire And Security Ca Llc Permit status: Issued | Current use: Public safety only | Permit id: 13041-10001-019 | |||||
SCORE 98 Date: July 10, 2015 Contractor: Joseph Peterson Permit status: Permit finaled | Current use: Commercial | Permit id: 15043-90000-030 | |||||
SCORE 100 Date: March 13, 2014 Contractor: Dynalectric Company Permit status: Permit finaled | Current use: Commercial | Permit id: 14041-20000-067 | |||||
SCORE 92 Date: August 13, 2013 Contractor: Eric Harley Permit status: Permit finaled | Current use: Commercial | Permit id: 12044-10003-016 | |||||
SCORE 59 Extension of exterior loading dock with new extended canopy. New elev Permit status: Issued | Current use: Commercial | Permit id: 13014-10000-021 | |||||
SCORE 59 Tenant improvement (43 sf) of an existing 168,368 sf manufacturing b Permit status: Permit finaled | Current use: Commercial | Permit id: 13016-10000-088 | |||||
SCORE 96 Date: May 23, 2014 Contractor: California Electrical Services Permit status: Permit finaled | Current use: Commercial | Permit id: 14041-10000-138 | |||||
SCORE 99 Curtain wall and glazing; deferred permit Permit status: Permit finaled | Current use: Commercial | Permit id: 12010-10003-000 | |||||
SCORE 97 (1) illuminated single faced monument sign 5-9" x 11-3"; reading "b Permit status: Permit finaled | Current use: Onsite | Permit id: 15048-10000-015 | |||||
SCORE 64 Site grading for new retaining wall and conrete containment dad . Permit status: Issued | Current use: Commercial | Permit id: 16030-10000-075 | |||||
SCORE 94 Date: September 27, 2013 Contractor: A R Construction Permit status: Permit finaled | Current use: Commercial | Permit id: 13041-10000-268 | |||||
SCORE 56 Change of use from office to control test lab; full floor tenant impro Permit status: Cofo issued | Current use: Commercial | Permit id: 16016-10000-257 | |||||
SCORE 63 Install (1) in-house 66" diameter x 510" height (660-gallon) tank on Permit status: Permit finaled | Current use: Commercial | Permit id: 15016-20000-128 | |||||
SCORE 100 Perform voluntary structural strengthening of existing roof equipment Permit status: Permit finaled | Current use: Commercial | Permit id: 13016-10000-085 | |||||
SCORE 72 Install fire sprinkler in new 5-story manufacturing support building. Permit status: Permit finaled | Current use: Commercial | Permit id: 12043-10000-039 | |||||
SCORE 91 Tenant improvement of 3rd floor of existing office building. Permit status: Issued | Current use: Commercial | Permit id: 13016-10000-046 | |||||
SCORE 100 Tenant improvement - install a roof top air handeling unit with associ Permit status: Permit expired | Current use: Commercial | Permit id: 14044-20000-066 | |||||
SCORE 59 Supplemental to permit# 12010-10000-00078 to plan check deferred submi Permit status: Permit finaled | Current use: Commercial | Permit id: 12010-10004-000 | |||||
SCORE 100 Tenant improvement for basement mechanical shop area, 803 s. F. Permit status: Permit finaled | Current use: Commercial | Permit id: 13016-10000-246 | |||||
SCORE 89 Construct new equipment pad (2-1. 5" x 2-0") on site. Permit status: Permit finaled | Current use: Commercial | Permit id: 16020-10000-026 | |||||
SCORE 100 New fire alarm system for a 2-story healthcare office building.((((((( Date: April 25, 2013 Contractor: Veronica Cobian Permit status: Permit expired | Current use: Commercial | Permit id: 12041-10001-083 | |||||
SCORE 64 Two new non-illuminated wall signs (46"x5-0" & 2-0"x2-3"). Sign re Permit status: Permit finaled | Current use: Onsite | Permit id: 13048-10000-007 | |||||
SCORE 59 Date: August 28, 2013 Contractor: Jack Brunner Permit status: Permit finaled | Current use: Commercial | Permit id: 13042-90000-170 | |||||
SCORE 100 Date: July 8, 2013 Contractor: Jeff Riddle Permit status: Permit finaled | Current use: Commercial | Permit id: 13042-90000-130 | |||||
SCORE 100 Proposed install new bearing partitions around equipment to control ai Permit status: Permit finaled | Current use: Commercial | Permit id: 14016-10000-108 |