Plumbing permit Date: January 29, 2016 Client: Ferraro Properties Inc | Permit status: Completed | Permit id: 666674 | |||||
Mechanical permit Date: January 12, 2016 Client: Ferraro Properties Inc | Permit status: Completed | Permit id: 663065 | |||||
Electrical permit Date: March 10, 2016 Client: Ferraro Properties Inc | Permit status: Completed | Permit id: 665112 | |||||
Zoning/use permit Date: July 1, 2015 Client: Ferraro Properties Inc | Permit status: Completed | Permit id: 615906 | |||||
New construction permit Date: July 1, 2015 Client: Ferraro Properties Inc | Permit status: Completed | Permit id: 615369 | |||||
Administrative permit Date: August 13, 2015 Client: Ferraro Properties Inc | Permit status: Completed | Permit id: 624265 | |||||
Plumbing permit Date: October 13, 2015 Client: Ferraro Properties Inc | Permit status: Completed | Permit id: 639761 | |||||
Suppression permit Date: September 4, 2015 Client: Ferraro Properties Inc | Permit status: Completed | Permit id: 629740 | |||||
Plumbing permit Date: October 13, 2015 Client: Ferraro Properties Inc | Permit status: Completed | Permit id: 639761 | |||||
Mechanical permit Date: January 12, 2016 Client: Ferraro Properties Inc | Permit status: Completed | Permit id: 663065 | |||||
Electrical permit Date: March 10, 2016 Client: Ferraro Properties Inc | Permit status: Completed | Permit id: 665112 | |||||
Plumbing permit Date: January 29, 2016 Client: Ferraro Properties Inc | Permit status: Completed | Permit id: 666674 | |||||
Administrative permit Date: August 13, 2015 Client: Ferraro Properties Inc | Permit status: Completed | Permit id: 624265 | |||||
Zoning use permit Date: July 1, 2015 Client: Ferraro Properties Inc | Permit status: Completed | Permit id: 615906 | |||||
Suppression permit Date: September 4, 2015 Client: Ferraro Properties Inc | Permit status: Completed | Permit id: 629740 | |||||
New construction permit Date: July 1, 2015 Client: Ferraro Properties Inc | Permit status: Completed | Permit id: 615369 | |||||
For the erection of an attached structure. Size and location as shown in application. For use as multi-family household living [four (4) dwelling units]. Date: July 1, 2015 Client: Ferraro Properties Inc | Permit type: Zoning/use permit | Permit status: Completed | Completion date: July 1, 2015 | Permit id: 615906 | |||||
SCORE 96 Install 2 1 2 ton heat pump with 10kw for basement and 1st fl for unit a,install 2 ton heatpump with 10kw on 2nd fl in unit b,install 1 1 2 ton heat pump with 8kw for 3rd and 4th stack in unit c,install 1 1 2 heat pump with 8kw for 3rd 4th stack in unit d with full duct work Date: January 12, 2016 Contractor: Balance Point Heating And Air Client: Ferraro Properties Inc | Permit type: Mechanical permit | Permit status: Completed | Completion date: May 28, 2016 | Permit id: 663065 | |||||
SCORE 100 For the installation of an automatic sprinkler system w. Two (2) inch fire service line & backflow prevention (bfp) assembly to serve previously approved four (4) story above grade plane, w. Basement, multi-family building. Automatic sprinkler system installation in accordance with nfpa 13r. Date: September 4, 2015 Contractor: Legacy Fire Sprinkler Services Client: Ferraro Properties Inc | Permit type: Suppression permit | Permit status: Completed | Completion date: May 28, 2016 | Permit id: 629740 | |||||
SCORE 96 Interior plumbing construction to a point 5-0" outside only for a new (4)family dwelling - note: additional permits required for exterior plumbing and sewer water connections to the city mains - the water meter must be located at the front wall of the basement to comply with pwd (philadelphia water department) regulations or special permission must be granted by the pwd - the installation will comply with the approved plans and the philadelphia plumbing code 2004 Date: October 13, 2015 Contractor: Frankie D And Benny G Plumbing And Client: Ferraro Properties Inc | Permit type: Plumbing permit | Permit status: Completed | Completion date: May 30, 2016 | Permit id: 639761 | |||||
Amend permit # 615369 to include underpinning, to be monitored by a licensed professional engineer at all times, as per approved plans. Date: August 13, 2015 Client: Ferraro Properties Inc | Permit type: Administrative permit | Permit status: Completed | Completion date: May 28, 2016 | Permit id: 624265 | |||||
SCORE 96 Install 4-200amp services and 100amp house panel. Install 400amp 5 gang meter pack and smoke detectors,install 1 outlets and 75 switches as per 2008 nec (west district) install fire alarm system as per nfpa72 Date: March 10, 2016 Contractor: Allwire Electric Llc Client: Ferraro Properties Inc | Permit type: Electrical permit | Permit status: Completed | Completion date: May 25, 2016 | Permit id: 665112 | |||||
SCORE 96 Install new 1 1 2" copper domestic water service. 6" lateral new combined brick system and new 4" main drain pa20160260031 (multi family)self certifications are no longer permitted","all excavations and plumbing trenches in excess of 5 ft in depth must have approved shoring in place at the time of inspection" Date: January 29, 2016 Contractor: Frankie D And Benny G Plumbing And Client: Ferraro Properties Inc | Permit type: Plumbing permit | Permit status: Completed | Completion date: May 30, 2016 | Permit id: 666674 | |||||
SCORE 100 New construction of a four (4) story, four (4) family dwelling as per approved plans. Single exit building in accordance with section 1021 of the 2009 ibc. Building to be fully sprinklered. Separate permits required for mep and fire suppression work Date: July 1, 2015 Contractor: David Schwartz Contracting Llc Client: Ferraro Properties Inc | Permit type: New construction permit | Permit status: Completed | Completion date: May 31, 2016 | Permit id: 615369 |