Zoning permit Date: March 17, 2015 Client: Triumphant Faith Inter- National Worship Center | Permit status: Completed | Permit id: 594449 | |||||
Electrical permit Date: April 18, 2007 Client: Triumphant Faith Inter- National Worship Center | Permit status: Completed | Permit id: 69932 | |||||
Use permit Date: August 21, 2015 Client: Triumphant Faith Inter- National Worship Center | Permit status: Completed | Permit id: 633589 | |||||
Plumbing permit Date: March 14, 2007 Client: Triumphant Faith Inter- National Worship Center | Permit status: Completed | Permit id: 62108 | |||||
Administrative permit Date: September 20, 2016 Client: Triumphant Faith Inter- National Worship Center | Permit status: Active | Permit id: 720445 | |||||
Administrative permit Date: April 11, 2016 Client: Triumphant Faith Inter- National Worship Center | Permit status: Active | Permit id: 674614 | |||||
Zoning permit Date: March 17, 2015 Client: Triumphant Faith Inter- National Worship Center | Permit status: Completed | Permit id: 594449 | |||||
Plumbing permit Date: March 14, 2007 Client: Triumphant Faith Inter- National Worship Center | Permit status: Completed | Permit id: 62108 | |||||
Use permit Date: August 21, 2015 Client: Triumphant Faith Inter- National Worship Center | Permit status: Completed | Permit id: 633589 | |||||
Electrical permit Date: April 18, 2007 Client: Triumphant Faith Inter- National Worship Center | Permit status: Completed | Permit id: 69932 | |||||
C o for daycare center lower level (exits to outdoors) and 1st floors, and accessory staff office 2nd floor. Additional work may be needed in order to enclose stair exit as noted and to provide accessible ramped entrance as per code. Verify 1 hour separation Date: April 11, 2016 Client: Triumphant Faith Inter- National Worship Center | Permit type: Administrative permit | Permit status: Completed | Completion date: April 10, 2017 | Permit id: 674614 | |||||
Day care center in an existing structure Date: August 21, 2015 Client: Triumphant Faith Inter- National Worship Center | Permit type: Use permit | Permit status: Completed | Completion date: August 21, 2015 | Permit id: 633589 | |||||
SCORE 61 Install new handicap bathroom, toilet and lavatory and associated plumbing Date: March 14, 2007 Contractor: Thomas Stewart Iii Client: Triumphant Faith Inter- National Worship Center | Permit type: Plumbing permit | Permit status: Completed | Completion date: February 29, 2008 | Permit id: 62108 | |||||
Relocation of lot lines to create one(1) lot from five(5) opa accounts. Date: March 17, 2015 Client: Triumphant Faith Inter- National Worship Center | Permit type: Zoning permit | Permit status: Completed | Completion date: March 17, 2015 | Permit id: 594449 | |||||
SCORE 92 Bathroom upgrade: 2 switches, 1 fan & 1 3 baseboard heater. Date: April 18, 2007 Contractor: Troxell Eugene J Jr Client: Triumphant Faith Inter- National Worship Center | Permit type: Electrical permit | Permit status: Completed | Completion date: January 11, 2008 | Permit id: 69932 | |||||
SCORE 86 Amend permit #674614 to include the erection of an accessible ramp for a daycare center as per approved plans. No interior changes on this permit. Date: September 20, 2016 Contractor: One Better Llc Client: Triumphant Faith Inter- National Worship Center | Permit type: Administrative permit | Permit status: Completed | Completion date: March 21, 2017 | Permit id: 720445 |