SCORE 100 Demolition of condominium building - laurelon bldg #1 and remove relocate trees(review and process 19 demolition permits under 6254897) Date: September 9, 2010 Contractor: Childrens Hospital Applicant: Neal, David | Permit type: Demolition | Permit status: Permit closed | Current use: Multifamily | Permit id: 6254897 | |||||
SCORE 95 Demolition of condominium building - laurelon bldg #1 and remove / relocate trees(review and process 19 demolition permits under 6254897) Date: December 8, 2010 Contractor: Seattle Childrens Hospital Applicant: Neal, David | Permit type: Demolition | Permit status: Permit closed | Completion date: April 30, 2012 | Expiration date: June 8, 2012 | Current use: Multifamily | Permit id: 6254897 | |||||
SCORE 100 Closed as incomplete - expired permit. Closed as incomplete - expired permit. Side sewer capping - contractor to provide plan of capping locations to inspector. 12 17 mvc: new - add alt to existing san & sd system. Contractor to restore street - ok by donnelly 01 10 11 ksd: non-std conn to psd; dip from core-tap to 9 above water main; ethafoam placed between sd and eater main. 7 17 2012 vjw: extended permit currently street restoration taking place per inspector. Date: December 10, 2010 Contractor: Hos Bros Construction Inc Applicant: Hos Bros Construction Inc | Permit type: Side sewer | Permit status: Permit closed | Expiration date: December 31, 2012 | Current use: Institutional | Permit id: 6268951 | |||||
SCORE 100 Construct addition and alterations to north portion of d-wing for seattle childrens hospital for cath lab, per plans. Applicant: Bres, Carlos | Permit type: Construction | Permit status: Permit closed | Current use: Institutional | Permit id: 6387670 | |||||
SCORE 100 Phased project: construction of new inpatient hospital (childrens hospital) & temporary surface parking and occupy, per plan. Applicant: Neal, David | Permit type: Construction | Permit status: Permit closed | Current use: Commercial | Permit id: 6249699 | |||||
SCORE 84 Shoring and excavation for construction of new inpatient hospital, per plan Applicant: Neal, David | Permit type: Construction | Permit status: Permit closed | Current use: Commercial | Permit id: 6257305 | |||||
Roof top terrace on existing building (building hope) at seattle childrens hospital Applicant: Hutchinson, William | Permit type: Construction | Permit status: Initial information colle | Current use: Institutional | Permit id: 6375862 | |||||
Construct alterations to build out kitchen and accessory areas in forest building on 1st level of existing hospital, per plan Date: June 18, 2015 Value: $10,000,000 Applicant: Neal, David | Permit type: Construction | Permit status: Permit issued | Current use: Commercial | Permit id: 6464914 | |||||
Initial tenant improvements to the 3rd floor of childrens hospital and occupy, per plan. (mechanical included this application) Date: June 4, 2015 Value: $9,000,000 Applicant: Delles, Tony | Permit type: Construction | Permit status: Permit issued | Current use: Institutional | Permit id: 6476431 | |||||
Shoring and excavation for construction of new inpatient hospital, per plan Date: October 12, 2010 Value: $3,300,000 Applicant: Neal, David | Permit type: Construction | Permit status: Permit closed | Current use: Commercial | Permit id: 6257305 | |||||
Roof top terrace on existing building (building hope) at seattle childrens hospital Applicant: Hutchinson, William | Permit type: Construction | Permit status: Initial information colle | Current use: Institutional | Permit id: 6375862 | |||||
SCORE 99 Construct alterations to build out kitchen and accessory areas in forest building on 1st level of existing hospital, per plan. Date: December 9, 2015 Value: $10,000,000 Applicant: Neal, David | Permit type: Construction | Permit status: Permit closed | Completion date: September 20, 2016 | Expiration date: June 9, 2017 | Current use: Commercial | Permit id: 6464914 | |||||
SCORE 99 Initial tenant improvements to the 3rd floor of childrens hospital and occupy, per plan. (mechanical included this application) Date: August 17, 2015 Value: $9,000,000 Applicant: Delles, Tony | Permit type: Construction | Permit status: Permit closed | Completion date: July 8, 2016 | Expiration date: February 17, 2017 | Current use: Institutional | Permit id: 6476431 | |||||
SCORE 95 Construct addition and alterations to north portion of d-wing for seattle childrens hospital for cath lab, per plans. Applicant: Bres, Carlos | Permit type: Construction | Permit status: Permit closed | Completion date: December 26, 2014 | Expiration date: October 1, 2015 | Current use: Institutional | Permit id: 6387670 | |||||
Roof top terrace on existing building (building hope) at seattle childrens hospital Applicant: Hutchinson, William | Permit type: Construction | Permit status: Initial information colle | Current use: Institutional | Permit id: 6375862 | |||||
SCORE 95 Phased project: construction of new inpatient hospital (childrens hospital) & temporary surface parking and occupy, per plan. Applicant: Neal, David | Permit type: Construction | Permit status: Permit closed | Completion date: August 12, 2013 | Expiration date: April 14, 2014 | Current use: Commercial | Permit id: 6249699 | |||||
SCORE 99 Shoring and excavation for construction of new inpatient hospital, per plan Date: February 22, 2011 Value: $3,300,000 Applicant: Neal, David | Permit type: Construction | Permit status: Permit closed | Completion date: July 12, 2012 | Expiration date: August 22, 2012 | Current use: Commercial | Permit id: 6257305 | |||||
SCORE 95 Install cat6 cabling, card reader cabling, and speaker cabling. Veca job # 712015 Date: June 20, 2016 Contractor: Veca Electric Company Inc Permit type: Electrical | Permit status: Permit closed | Completion date: September 12, 2016 | Expiration date: June 20, 2017 | Current use: Commercial | Permit id: 6541666 | |||||
SCORE 100 Installation of all low voltage systems cabling and devices. Date: November 17, 2015 Contractor: Holmes Electric Company Permit type: Electrical | Permit status: Permit closed | Completion date: June 27, 2016 | Expiration date: November 16, 2016 | Current use: Commercial | Permit id: 6505553 | |||||
SCORE 100 Installation of cabling for all low voltage systems. Date: September 8, 2015 Contractor: Holmes Electric Company Permit type: Electrical | Permit status: Permit issued | Expiration date: September 7, 2016 | Current use: Commercial | Permit id: 6493584 | |||||
SCORE 95 Tenant improvement - build out of patient rooms on 3rd floor Permit type: Electrical | Permit status: Permit closed | Completion date: June 26, 2016 | Expiration date: August 24, 2016 | Current use: Institutional | Permit id: 6479452 | |||||
SCORE 100 Installation of low voltage cabling for nurse call, cctv, access control, oh paging, voice and data. Date: December 16, 2014 Contractor: Holmes Electric Company Permit type: Electrical | Permit status: Permit closed | Completion date: June 15, 2015 | Expiration date: December 16, 2015 | Current use: Commercial | Permit id: 6451073 | |||||
SCORE 95 Fire alarm adding devices to the system joint venture between siemens industry and veca electric Date: January 6, 2015 Contractor: Siemens Bldg Technologies Inc Permit type: Electrical | Permit status: Permit closed | Completion date: January 12, 2016 | Expiration date: January 6, 2016 | Current use: Commercial | Permit id: 6450589 | |||||
SCORE 100 Installation of low voltage cabling to include voice, data, access control, cctv and das. Date: November 18, 2014 Contractor: Holmes Electric Company Permit type: Electrical | Permit status: Permit closed | Completion date: June 1, 2015 | Expiration date: November 18, 2015 | Current use: Commercial | Permit id: 6446757 | |||||
SCORE 100 Installation of 572 category 6 cables throughout the 2nd floor Date: October 27, 2014 Contractor: Holmes Electric Company Permit type: Electrical | Permit status: Permit closed | Completion date: January 7, 2015 | Expiration date: October 27, 2015 | Current use: Commercial | Permit id: 6443170 | |||||
SCORE 95 Install low voltage security system - sea-13826 Date: May 28, 2014 Contractor: Aronson Security Group Inc Permit type: Electrical | Permit status: Permit closed | Completion date: September 2, 2014 | Expiration date: May 28, 2015 | Current use: Institutional | Permit id: 6419910 | |||||
SCORE 95 Fire alarm remodel to cath lab on the 6th & 7th floors, joint venture between veca electric & siemens industries Date: May 21, 2014 Contractor: Siemens Industry Inc Permit type: Electrical | Permit status: Permit closed | Completion date: October 8, 2014 | Expiration date: May 21, 2015 | Current use: Institutional | Permit id: 6416252 | |||||
SCORE 95 Day get started for branch circuits only; plan review under #6400895 Date: January 22, 2014 Contractor: Veca Electric Company Inc Permit type: Electrical | Permit status: Permit closed | Completion date: February 5, 2014 | Expiration date: February 22, 2014 | Current use: Institutional | Permit id: 6400896 | |||||
SCORE 95 812878 - emergency department nurse call circuit Date: December 13, 2013 Contractor: Veca Electric Company Inc Permit type: Electrical | Permit status: Permit closed | Completion date: January 22, 2014 | Expiration date: December 13, 2014 | Current use: Institutional | Permit id: 6396204 | |||||
SCORE 95 Replacing speaker with strobes Date: September 12, 2013 Contractor: Siemens Industry Inc Permit type: Electrical | Permit status: Reviews approved | Current use: Institutional | Permit id: 6380935 | |||||
SCORE 95 Install new expansion tank Date: June 13, 2016 Contractor: Mckinstry Company Llc Applicant: Mckinstry Company Llc | Permit type: Boiler / pressure vessel | Permit status: Permit closed | Completion date: June 28, 2016 | Expiration date: December 13, 2017 | Current use: Institutional | Permit id: 6540079 | |||||
SCORE 95 Install new water heater Date: June 13, 2016 Contractor: Mckinstry Company Llc Applicant: Mckinstry Company Llc | Permit type: Boiler / pressure vessel | Permit status: Permit closed | Completion date: June 28, 2016 | Expiration date: December 13, 2017 | Current use: Institutional | Permit id: 6540078 | |||||
SCORE 95 Install new boiler [b9] Date: June 13, 2016 Contractor: Mckinstry Company Llc Applicant: Mckinstry Company Llc | Permit type: Boiler / pressure vessel | Permit status: Permit issued | Expiration date: December 13, 2017 | Current use: Institutional | Permit id: 6540075 | |||||
Stand alone fire sprinkler add/relocate approx. 2 heads. Per plan Date: August 27, 2015 Applicant: Thomas, Jim | Permit type: Mechanical | Permit status: Permit issued | Expiration date: February 27, 2017 | Current use: Commercial | Permit id: 6487188 | |||||
SCORE 95 Stand alone sprinkler Date: November 17, 2014 Contractor: Mckinstry Company Llc Applicant: Thomas, Jim | Permit type: Mechanical | Permit status: Permit closed | Completion date: June 25, 2015 | Expiration date: May 17, 2016 | Current use: Commercial | Permit id: 6440995 | |||||
SCORE 95 Install fire sprinklers - building hope (childrens hospital) add and relocate 173 srinkler heads on level 2.. Date: September 22, 2014 Contractor: Mckinstry Company Llc Applicant: Thomas, Jim | Permit type: Mechanical | Permit status: Permit closed | Completion date: February 18, 2015 | Expiration date: March 22, 2016 | Current use: Institutional | Permit id: 6432562 | |||||
SCORE 95 Stand alone sprinkler adding (1) fire sprinkler head to existing system, level 8 roof garden vestibule. Date: July 25, 2014 Contractor: Mckinstry Company Llc Applicant: Thomas, Jim | Permit type: Mechanical | Permit status: Permit issued | Expiration date: January 25, 2016 | Current use: Commercial | Permit id: 6428053 | |||||
SCORE 100 Stand alone sprinkler: tenant improvements to 25 heads Applicant: Fraser, Melissa | Permit type: Mechanical | Permit status: Permit closed | Completion date: October 15, 2014 | Expiration date: December 25, 2015 | Current use: Commercial | Permit id: 6420662 | |||||
SCORE 95 Refrigeration piping for installation of split system acu serving starbucks tenant space Date: February 28, 2013 Contractor: Mckinstry Company Llc Applicant: Mckinstry Company Llc | Permit type: Refrigeration | Permit status: Permit closed | Completion date: April 16, 2013 | Expiration date: August 28, 2014 | Current use: Institutional | Permit id: 6354992 | |||||
SCORE 95 Install epansion tank et-33 Date: January 25, 2013 Contractor: Mckinstry Company Llc Applicant: Mckinstry Company Llc | Permit type: Boiler / pressure vessel | Permit status: Permit closed | Completion date: February 21, 2013 | Expiration date: July 25, 2014 | Current use: Institutional | Permit id: 6350612 | |||||
SCORE 95 Install epansion tank et-32 Date: January 25, 2013 Contractor: Mckinstry Company Llc Applicant: Mckinstry Company Llc | Permit type: Boiler / pressure vessel | Permit status: Permit closed | Completion date: February 21, 2013 | Expiration date: July 25, 2014 | Current use: Institutional | Permit id: 6350610 | |||||
SCORE 95 Temp operating permit Date: January 24, 2013 Contractor: Otis Elevator Company Applicant: Otis Elevator Company | Permit type: Conveyance | Permit status: Permit closed | Completion date: February 5, 2013 | Expiration date: July 24, 2014 | Permit id: 6349937 | |||||
SCORE 95 Temp operating permit. Date: January 24, 2013 Contractor: Otis Elevator Company Applicant: Otis Elevator Company | Permit type: Conveyance | Permit status: Permit closed | Completion date: February 5, 2013 | Expiration date: July 24, 2014 | Permit id: 6349935 | |||||
SCORE 95 Install plate heat exchanger phx-4 Date: January 4, 2013 Contractor: Mckinstry Company Llc Applicant: Mckinstry Company Llc | Permit type: Boiler / pressure vessel | Permit status: Permit closed | Completion date: February 26, 2013 | Expiration date: July 4, 2014 | Current use: Institutional | Permit id: 6348004 | |||||
SCORE 95 Install plate heat exchanger phx-3 Date: January 4, 2013 Contractor: Mckinstry Company Llc Applicant: Mckinstry Company Llc | Permit type: Boiler / pressure vessel | Permit status: Permit closed | Completion date: February 26, 2013 | Expiration date: July 4, 2014 | Current use: Institutional | Permit id: 6348003 | |||||
SCORE 95 Install plate heat exchanger phx-1 Date: January 4, 2013 Contractor: Mckinstry Company Llc Applicant: Mckinstry Company Llc | Permit type: Boiler / pressure vessel | Permit status: Permit closed | Completion date: February 26, 2013 | Expiration date: July 4, 2014 | Current use: Institutional | Permit id: 6348001 | |||||
SCORE 95 Install plate heat exchanger phx-2 Date: January 4, 2013 Contractor: Mckinstry Company Llc Applicant: Mckinstry Company Llc | Permit type: Boiler / pressure vessel | Permit status: Permit closed | Completion date: February 26, 2013 | Expiration date: July 4, 2014 | Current use: Institutional | Permit id: 6348002 | |||||
SCORE 95 Install medical air storage tank ma-1 Date: January 4, 2013 Contractor: Mckinstry Company Llc Applicant: Mckinstry Company Llc | Permit type: Boiler / pressure vessel | Permit status: Permit closed | Completion date: February 11, 2013 | Expiration date: July 4, 2014 | Current use: Institutional | Permit id: 6348000 | |||||
SCORE 95 Install medical vacuum storage tank mv-1 Date: January 4, 2013 Contractor: Mckinstry Company Llc Applicant: Mckinstry Company Llc | Permit type: Boiler / pressure vessel | Permit status: Permit closed | Completion date: February 26, 2013 | Expiration date: July 4, 2014 | Current use: Institutional | Permit id: 6347998 | |||||
SCORE 95 Install new air separator as-22 Date: August 3, 2012 Contractor: Mckinstry Company Llc Applicant: Mckinstry Company Llc | Permit type: Boiler / pressure vessel | Permit status: Permit closed | Completion date: December 26, 2012 | Expiration date: February 3, 2014 | Current use: Institutional | Permit id: 6329828 | |||||
SCORE 95 Install new air separator as-21 Date: August 3, 2012 Contractor: Mckinstry Company Llc Applicant: Mckinstry Company Llc | Permit type: Boiler / pressure vessel | Permit status: Permit closed | Completion date: December 24, 2012 | Expiration date: February 3, 2014 | Current use: Institutional | Permit id: 6329827 | |||||
SCORE 95 Install new air separator as-20 Date: August 3, 2012 Contractor: Mckinstry Company Llc Applicant: Mckinstry Company Llc | Permit type: Boiler / pressure vessel | Permit status: Permit closed | Completion date: December 26, 2012 | Expiration date: February 3, 2014 | Current use: Institutional | Permit id: 6329826 | |||||
SCORE 95 Install new water treatment tank wt-3 Date: August 3, 2012 Contractor: Mckinstry Company Llc Applicant: Mckinstry Company Llc | Permit type: Boiler / pressure vessel | Permit status: Permit closed | Completion date: December 26, 2012 | Expiration date: February 3, 2014 | Current use: Institutional | Permit id: 6329825 | |||||
SCORE 95 Install new water treatment tank wt-2 Date: August 3, 2012 Contractor: Mckinstry Company Llc Applicant: Mckinstry Company Llc | Permit type: Boiler / pressure vessel | Permit status: Permit closed | Completion date: December 26, 2012 | Expiration date: February 3, 2014 | Current use: Institutional | Permit id: 6329824 | |||||
SCORE 95 Install new water treatment tank wt-1 Date: August 3, 2012 Contractor: Mckinstry Company Llc Applicant: Mckinstry Company Llc | Permit type: Boiler / pressure vessel | Permit status: Permit closed | Completion date: December 26, 2012 | Expiration date: February 3, 2014 | Current use: Institutional | Permit id: 6329823 | |||||
SCORE 95 Install heat exchanger phx-2 Date: August 3, 2012 Contractor: Mckinstry Company Llc Applicant: Mckinstry Company Llc | Permit type: Boiler / pressure vessel | Permit status: Permit closed | Completion date: February 11, 2013 | Expiration date: February 3, 2014 | Current use: Institutional | Permit id: 6329817 | |||||
SCORE 95 Install heat exchanger phx-1 Date: August 3, 2012 Contractor: Mckinstry Company Llc Applicant: Mckinstry Company Llc | Permit type: Boiler / pressure vessel | Permit status: Permit closed | Completion date: February 11, 2013 | Expiration date: February 3, 2014 | Current use: Institutional | Permit id: 6329816 | |||||
SCORE 95 Install expansion tank et-30 Date: August 3, 2012 Contractor: Mckinstry Company Llc Applicant: Mckinstry Company Llc | Permit type: Boiler / pressure vessel | Permit status: Permit closed | Completion date: February 11, 2013 | Expiration date: February 3, 2014 | Current use: Institutional | Permit id: 6329815 | |||||
SCORE 95 Install expansion tank et-29 Date: August 3, 2012 Contractor: Mckinstry Company Llc Applicant: Mckinstry Company Llc | Permit type: Boiler / pressure vessel | Permit status: Permit closed | Completion date: February 11, 2013 | Expiration date: February 3, 2014 | Current use: Institutional | Permit id: 6329814 | |||||
SCORE 95 Install expansion tank et-28 Date: August 3, 2012 Contractor: Mckinstry Company Llc Applicant: Mckinstry Company Llc | Permit type: Boiler / pressure vessel | Permit status: Permit closed | Completion date: February 11, 2013 | Expiration date: February 3, 2014 | Current use: Institutional | Permit id: 6329813 | |||||
SCORE 95 Install expansion tank et-27 Date: August 3, 2012 Contractor: Mckinstry Company Llc Applicant: Mckinstry Company Llc | Permit type: Boiler / pressure vessel | Permit status: Permit closed | Completion date: February 11, 2013 | Expiration date: February 3, 2014 | Current use: Institutional | Permit id: 6329812 | |||||
SCORE 95 Install expansion tank et-26 Date: August 3, 2012 Contractor: Mckinstry Company Llc Applicant: Mckinstry Company Llc | Permit type: Boiler / pressure vessel | Permit status: Permit closed | Completion date: February 11, 2013 | Expiration date: February 3, 2014 | Current use: Institutional | Permit id: 6329811 | |||||
SCORE 95 Install expansion tank et-31 Date: August 3, 2012 Contractor: Mckinstry Company Llc Applicant: Mckinstry Company Llc | Permit type: Boiler / pressure vessel | Permit status: Permit closed | Completion date: February 11, 2013 | Expiration date: February 3, 2014 | Current use: Institutional | Permit id: 6329808 | |||||
SCORE 95 New hydraulic elevator installation Date: June 29, 2012 Contractor: Otis Elevator Company Applicant: Otis Elevator Company | Permit type: Conveyance | Permit status: Permit closed | Completion date: February 5, 2013 | Expiration date: December 29, 2013 | Permit id: 6325418 | |||||
SCORE 95 New installation Date: April 13, 2012 Contractor: Otis Elevator Company Applicant: Otis Elevator Company | Permit type: Conveyance | Permit status: Permit closed | Completion date: February 5, 2013 | Expiration date: October 13, 2013 | Permit id: 6316759 | |||||
SCORE 95 New installation; final layouts pending oshpd acceptance Date: February 8, 2012 Contractor: Otis Elevator Company Applicant: Otis Elevator Company | Permit type: Conveyance | Permit status: Permit closed | Completion date: February 5, 2013 | Expiration date: August 8, 2013 | Permit id: 6309783 | |||||
Sprinkler only to install sprinkler system, per plans. Date: February 16, 2012 Applicant: Thomas, Jim | Permit type: Mechanical | Permit status: Permit closed | Completion date: February 21, 2013 | Expiration date: August 16, 2013 | Current use: Institutional | Permit id: 6301364 | |||||
Install 1 new air terminal unit, relocate air terminal unit, and duct work and disfusers Applicant: Thomas, Jim | Permit type: Mechanical | Current use: Commercial | Permit id: 6402981 | |||||
SCORE 95 Underground fire water storage tank and underground piping for tank and building supply Date: July 11, 2011 Contractor: Mckinstry Company Llc Applicant: Post, Nancy | Permit type: Mechanical | Permit status: Permit closed | Completion date: February 21, 2013 | Expiration date: January 11, 2013 | Current use: Commercial | Permit id: 6282100 | |||||
SCORE 95 2/14/14 jcb; revisions submitted - add connections to recirc pump and water heater per plan; added value 13428. 00. 1/22/14 add 2 amp 4 volt feeder from swbd l1fa3-e3-l3 to domestic booster pump. Permit type: Electrical | Permit status: Permit closed | Completion date: April 7, 2014 | Expiration date: February 5, 2015 | Current use: Institutional | Permit id: 6400895 | |||||
SCORE 95 [joint venture with veca electric company inc. ] tenant improvement to roof of hope building at childrens hospital. Adding audio/visual devices to existing space. Adding fire alarm interface modules for monotoring dry sprinkler switches and unlocking door upon a fire alarm event Date: August 6, 2014 Contractor: Siemens Bldg Technologies Inc Permit type: Electrical | Permit status: Permit issued | Expiration date: August 6, 2015 | Current use: Commercial | Permit id: 6430676 | |||||
SCORE 95 Tenant improvement - build out of patient rooms and offices; building hope/forest a/levels 2, 4 & 5. Permit type: Electrical | Permit status: Permit closed | Completion date: June 15, 2015 | Expiration date: December 9, 2015 | Current use: Institutional | Permit id: 6431802 | |||||
SCORE 95 30-day get started branch circuits only, plan review permit under #6431802 11/10/14 rrj extended to 12/13/14 Date: August 13, 2014 Contractor: Veca Electric Company Inc Permit type: Electrical | Permit status: Permit closed | Completion date: December 9, 2014 | Expiration date: December 13, 2014 | Current use: Institutional | Permit id: 6431806 | |||||
SCORE 95 Sch ed ct scanner build out job 818857 Permit type: Electrical | Permit status: Application accepted | Current use: Commercial | Permit id: 6577000 | |||||
SCORE 95 Day get started permit for branch circuits only, assoc. Permit #6577000. Date: January 20, 2017 Contractor: Veca Electric Company Inc Permit type: Electrical | Permit status: Permit issued | Expiration date: February 20, 2017 | Current use: Commercial | Permit id: 6577230 | |||||
SCORE 99 Shoring and excavation for construction of new inpatient hospital, per plan Date: February 22, 2011 Value: $3,300,000 Applicant: Neal, David | Permit type: Construction | Permit status: Permit closed | Completion date: July 12, 2012 | Expiration date: August 22, 2012 | Current use: Commercial | Permit id: 6257305 | |||||
Roof top terrace on existing building (building hope) at seattle childrens hospital Applicant: Hutchinson, William | Permit type: Construction | Permit status: Initial information colle | Current use: Institutional | Permit id: 6375862 | |||||
SCORE 99 Initial tenant improvements to the 3rd floor of childrens hospital and occupy, per plan. (mechanical included this application) Date: August 17, 2015 Value: $9,000,000 Applicant: Delles, Tony | Permit type: Construction | Permit status: Permit closed | Completion date: July 8, 2016 | Expiration date: February 17, 2017 | Current use: Institutional | Permit id: 6476431 | |||||
SCORE 99 Construct alterations to build out kitchen and accessory areas in forest building on 1st level of existing hospital, per plan. Date: December 9, 2015 Value: $10,000,000 Applicant: Neal, David | Permit type: Construction | Permit status: Permit closed | Completion date: September 20, 2016 | Expiration date: June 9, 2017 | Current use: Commercial | Permit id: 6464914 | |||||
SCORE 95 Alterations to install ct scanner and injector at level 1 of the forest building for childrens hospital, per plan. Applicant: Terao, Maiko | Permit type: Construction | Permit status: Permit issued | Expiration date: May 17, 2018 | Current use: Institutional | Permit id: 6563963 | |||||
SCORE 95 Ti installation of ct and injector and interior construction on level 1 (emergency department) of the forest building, per plan Applicant: Terao, Maiko | Permit type: Mechanical | Permit status: Permit issued | Expiration date: June 9, 2018 | Current use: Commercial | Permit id: 6566808 | |||||
Stand alone fire sprinkler add relocate approx. 2 heads. Per plan Date: August 27, 2015 Applicant: Thomas, Jim | Permit type: Mechanical | Permit status: Permit issued | Expiration date: February 27, 2017 | Current use: Commercial | Permit id: 6487188 | |||||
Install 1 new air terminal unit, relocate air terminal unit, and duct work and disfusers Applicant: Thomas, Jim | Permit type: Mechanical | Current use: Commercial | Permit id: 6402981 | |||||
SCORE 95 Install new boiler b-7 12 18 12 mvc: adding automatic certification for b-7 Date: August 3, 2012 Contractor: Mckinstry Company Llc Applicant: Mckinstry Company Llc | Permit type: Boiler / pressure vessel | Permit status: Permit closed | Completion date: February 11, 2013 | Expiration date: February 3, 2014 | Current use: Institutional | Permit id: 6329820 | |||||
SCORE 95 Install new boiler b-8 in emergency department 12 18 12 mvc: adding automatic certification for b-8 Date: August 3, 2012 Contractor: Mckinstry Company Llc Applicant: Mckinstry Company Llc | Permit type: Boiler / pressure vessel | Permit status: Permit closed | Completion date: February 11, 2013 | Expiration date: February 3, 2014 | Current use: Institutional | Permit id: 6329821 | |||||
SCORE 95 Install new boiler b-5. 12 18 12 mvc: adding automatic certification for b-5. Date: August 3, 2012 Contractor: Mckinstry Company Llc Applicant: Mckinstry Company Llc | Permit type: Boiler / pressure vessel | Permit status: Permit closed | Completion date: February 11, 2013 | Expiration date: February 3, 2014 | Current use: Institutional | Permit id: 6329807 | |||||
SCORE 95 Install plate heat exchanger pl hx-1. 1/3/13 jcb; update unit is actually an et-1, sn 231032. Date: August 3, 2012 Contractor: Mckinstry Company Llc Applicant: Mckinstry Company Llc | Permit type: Boiler / pressure vessel | Permit status: Permit closed | Completion date: February 21, 2013 | Expiration date: February 3, 2014 | Current use: Institutional | Permit id: 6329818 | |||||
SCORE 95 Install new boiler b-6 12 18 12 mvc: adding automatic certification for b-6 Date: August 3, 2012 Contractor: Mckinstry Company Llc Applicant: Mckinstry Company Llc | Permit type: Boiler / pressure vessel | Permit status: Permit closed | Completion date: February 11, 2013 | Expiration date: February 3, 2014 | Current use: Institutional | Permit id: 6329819 | |||||
SCORE 95 Fire sprinklers onlyadd/relocate approx. 6 sprinkler heads on level 4 and 5 Date: August 7, 2014 Contractor: Mckinstry Company Llc Applicant: Thomas, Jim | Permit type: Mechanical | Permit status: Permit closed | Completion date: June 17, 2015 | Expiration date: February 7, 2016 | Current use: Commercial | Permit id: 6427421 | |||||
SCORE 95 Day get started for branch circuits only, plan review permit under #6511101. 2/17/16 sk renewal Date: January 13, 2016 Contractor: Veca Electric Company Inc Permit type: Electrical | Permit status: Permit issued | Expiration date: March 13, 2016 | Current use: Institutional | Permit id: 6513621 | |||||
SCORE 95 Stand alone sprinkler to add/relocate 36 heads, in the main entry canopy tenant (seattle childrens hospital) Date: October 19, 2012 Contractor: Mckinstry Company Llc Applicant: Thomas, Jim | Permit type: Mechanical | Permit status: Permit closed | Completion date: February 21, 2013 | Expiration date: April 19, 2014 | Current use: Commercial | Permit id: 6335241 | |||||
SCORE 95 Days get started for branch circuits only. Plan review done under permit #6479452 extended to 9/21/15 rrj Date: June 15, 2015 Contractor: Veca Electric Company Inc Permit type: Electrical | Permit status: Permit closed | Completion date: August 24, 2015 | Expiration date: September 21, 2015 | Current use: Institutional | Permit id: 6479457 | |||||
Roof top terrace on existing building (building hope) at seattle childrens hospital Applicant: Hutchinson, William | Permit type: Construction | Permit status: Initial information colle | Current use: Institutional | Permit id: 6375862 | |||||
SCORE 95 Ungrounded fuel tanks and transformer relocation (veca job #816906). 3 28 16 cpg applicant submit correction associated contruction permit #6498751. Wgr: extended to 10 18 17 to match construction permit. Wgr extended to 4 18 19 to match building permit. Permit type: Electrical | Permit status: Permit issued | Expiration date: May 16, 2017 | Current use: Industrial | Permit id: 6522127 | |||||
SCORE 95 30day get started for branch circuits only, plan review permit under # 6522127. 4/8/16 sk extend permit. 5/6/16vp extend permit. Date: March 15, 2016 Contractor: Veca Electric Company Inc Permit type: Electrical | Permit status: Permit closed | Completion date: May 16, 2016 | Expiration date: June 15, 2016 | Current use: Industrial | Permit id: 6524002 | |||||
SCORE 100 Addition of (2) 3p 208v 50a circuits and (1) 120v 20a 1p circuit for idf room. Permit type: Electrical | Permit status: Permit issued | Expiration date: August 28, 2018 | Current use: Institutional | Permit id: 6609922 | |||||
SCORE 95 Install cat6 and cat6a cables for security, access control, and workstations. Veca job # 712824 Date: February 27, 2017 Contractor: Veca Electric Company Inc Permit type: Electrical | Permit status: Permit closed | Completion date: May 23, 2017 | Expiration date: February 27, 2018 | Current use: Commercial | Permit id: 6583195 | |||||
SCORE 95 [joint venture with veca electric company inc. ] relocate (1) fire alarm speaker - ceiling mountrelocate (1) strobe - wall mountadd (1) smoke detector Date: February 1, 2017 Contractor: Siemens Bldg Technologies Inc Permit type: Electrical | Permit status: Permit closed | Completion date: May 23, 2017 | Expiration date: February 1, 2018 | Current use: Commercial | Permit id: 6579079 | |||||
Stand alone sprinkler only to install 8 concealed quick response standard spray sprinkler for seattle childrens on the 1st floor, per plans. 2 9 17 hkh; address changed per sullyd from 45 ne 40th st to 45 40th ave ne. Date: February 10, 2017 Applicant: Thomas, Jim | Permit type: Mechanical | Permit status: Permit closed | Completion date: February 10, 2017 | Expiration date: August 10, 2018 | Current use: Institutional | Permit id: 6579966 | |||||
Install 1 new air terminal unit, relocate air terminal unit, and duct work and disfusers Applicant: Thomas, Jim | Permit type: Mechanical | Current use: Commercial | Permit id: 6402981 | |||||
SCORE 95 Shell, core & site electrical, communication & systems rough in. 1 6 12 jcb; revision submitted for cdi 035, increase in job value 240,000. 00. 6 20 12 mvc: revision - revise connections to chiller 6 and add swbd l1fa3-n4-l5, increase in job value 23,000. Permit type: Electrical | Permit status: Permit closed | Completion date: March 1, 2013 | Expiration date: July 12, 2012 | Current use: Institutional | Permit id: 6278691 | |||||
SCORE 95 Temp operating permit. 9/26/12 bew extending top. 11/19/12 jcb; extend top. Date: July 13, 2012 Contractor: Otis Elevator Company Applicant: Otis Elevator Company | Permit type: Conveyance | Permit status: Permit closed | Completion date: February 5, 2013 | Expiration date: January 13, 2014 | Permit id: 6326713 | |||||
SCORE 95 Temp operating permit. 9/26/12 bew extended top. 11/19/12 jcb; extend top. Date: July 13, 2012 Contractor: Otis Elevator Company Applicant: Otis Elevator Company | Permit type: Conveyance | Permit status: Permit closed | Completion date: February 5, 2013 | Expiration date: January 13, 2014 | Permit id: 6326712 | |||||
SCORE 100 Closed - parent permit issued day get started permit for branch circuits only, plan review under 6609922 Date: August 18, 2017 Contractor: Holmes Electric Company Permit type: Electrical | Permit status: Permit closed | Expiration date: September 18, 2017 | Current use: Institutional | Permit id: 6614250 | |||||
SCORE 95 Adding (15) fire alarm devices / strobes [ocean 10th floor lab] Date: July 7, 2015 Contractor: Siemens Bldg Technologies Inc Permit type: Electrical | Permit status: Permit closed | Completion date: August 14, 2015 | Expiration date: July 7, 2016 | Current use: Commercial | Permit id: 6482090 | |||||
SCORE 95 [joint venture with astor electric llc. . ] replace existing power supply Date: February 1, 2017 Contractor: Siemens Bldg Technologies Inc Permit type: Electrical | Permit status: Permit closed | Completion date: February 17, 2017 | Expiration date: February 1, 2018 | Current use: Commercial | Permit id: 6579098 | |||||
SCORE 95 Tenant improvement of rehab therapy space - job #816373 ocean - level 6. 2/29/16 jk notified contractor that plans had been approved and permit had issued. Permit type: Electrical | Permit status: Permit issued | Expiration date: February 28, 2017 | Current use: Institutional | Permit id: 6511101 | |||||
SCORE 95 Closed - parent permit issued day get started for branch circuits only; plan review under 6493203. [job #816136] 10/2/15 hkh; extend days per b. Johnson extended to 12/3/15 rrj Date: September 3, 2015 Contractor: Veca Electric Company Inc Permit type: Electrical | Permit status: Permit closed | Expiration date: December 3, 2015 | Current use: Institutional | Permit id: 6493205 | |||||
SCORE 95 Tenant improvement, build out of kitchen/l1. [job #816136] Permit type: Electrical | Permit status: Permit closed | Completion date: September 14, 2016 | Expiration date: November 16, 2016 | Current use: Institutional | Permit id: 6493203 | |||||
SCORE 95 Day get started for branch circuits plan review under permit 6493203. [kitchen /l1 job #816136]. Date: November 3, 2015 Contractor: Veca Electric Company Inc Permit type: Electrical | Permit status: Permit closed | Completion date: December 2, 2015 | Expiration date: December 3, 2015 | Current use: Institutional | Permit id: 6503273 | |||||
SCORE 56 Relocate (6) grilles, registers and diffusers. Relocate (3) thermostats, controls, test and balance. Work to be done at seattle childrens hospital, level 8, cbdc "d" wing, per plan. Applicant: Perle, Dawn | Permit type: Mechanical | Permit status: Permit issued | Expiration date: May 30, 2019 | Current use: Institutional | Permit id: 6606954 | |||||
SCORE 95 Day get started: for wall & ceiling cover only, ref #6278691 extended to 7 11 11 rrj Date: March 30, 2011 Contractor: Veca Electric Company Inc Permit type: Electrical | Permit status: Permit closed | Completion date: July 12, 2011 | Expiration date: July 11, 2011 | Current use: Institutional | Permit id: 6278695 |