Content | Date | Cost | Contractor Rank | Address | Contractor |
---|---|---|---|---|---|
SCORE 78 T. I.-renovation of existing bank Applicant: Laguna,Steven | Permit status: Finaled | Completion date: November 21, 2005 | Permit id: 0312090038 | |||||
SCORE 78 T. I.-install 1 new atm and expand existing atm room for ada compliance Applicant: Laguna,Steve | Permit status: Finaled | Completion date: November 21, 2005 | Permit id: 0504130046 | |||||
SCORE 93 Modify (e) wall conditions to add an atm Applicant: Lopez,Robert | Permit status: Finaled | Completion date: November 30, 2009 | Permit id: 0910300012 | |||||
SCORE 90 Electrical re wire 15 branch circuits, outlets,28 fixtur Date: February 4, 2004 Contractor: Reilly Electric Co Applicant: Reilly,John | Permit status: Finaled | Completion date: May 18, 2004 | Permit id: 0401070007 | |||||
SCORE 90 3 branch circuits,1 exhaust fan Date: April 21, 2005 Contractor: Reilly Electric Co Applicant: Reilly,John | Permit status: Finaled | Completion date: November 21, 2005 | Permit id: 0504210040 | |||||
SCORE 93 Electrical for add of an atm Date: November 6, 2009 Contractor: Niscayah Inc Applicant: Lopez,Robert | Permit status: Finaled | Completion date: November 30, 2009 | Permit id: 0910300005 | |||||
SCORE 81 Plumbing for hc restroom Date: February 18, 2004 Contractor: Arnies Plumbing Service Applicant: Arnies Plumbing Service Inc | Permit status: Finaled | Completion date: May 18, 2004 | Permit id: 0402180030 | |||||
SCORE 93 Modify (e) wall conditions to add an atm Applicant: Lopez, Robert | Permit status: Finaled | Completion date: November 30, 2009 | Expiration date: November 6, 2010 | Permit id: 910300012 | |||||
SCORE 100 Reface pylon 148 sqft, replace 2 channel letter sets 84. 2 sqft and 47. 5 sqft., informational sign. Applicant: Lamson Nguyen | Permit status: Permisud | Expiration date: September 19, 2013 | Permit id: 1209190016 | |||||
SCORE 72 Remove & replace atms, pour new concrete & ramp for ada, remove & re-install glass enclosure, intall new handrail. Applicant: Leon Santiago | Permit status: Finaled | Completion date: September 19, 2014 | Expiration date: June 25, 2015 | Permit id: 1405010035 | |||||
SCORE 90 Electrical re wire 15 branch circuits, outlets, 28 fixtur Date: February 4, 2004 Contractor: Reilly Electric Co Applicant: Reilly, John | Permit status: Finaled | Completion date: May 18, 2004 | Expiration date: August 2, 2004 | Permit id: 401070007 | |||||
SCORE 90 3 branch circuits, 1 exhaust fan Date: April 21, 2005 Contractor: Reilly Electric Co Engineer: Rmj Structural | Applicant: Reilly, John | Permit status: Finaled | Completion date: November 21, 2005 | Expiration date: October 18, 2005 | Permit id: 504210040 | |||||
SCORE 93 Electrical for add of an atm Date: November 6, 2009 Contractor: Niscayah Inc Applicant: Lopez, Robert | Permit status: Finaled | Completion date: November 30, 2009 | Expiration date: November 6, 2010 | Permit id: 910300005 | |||||
SCORE 64 Modify (e) wall conditions to add an atm Applicant: Lopez, Robert | Permit status: Finaled | Completion date: November 30, 2009 | Expiration date: November 6, 2010 | Permit id: 910300012 | |||||
SCORE 100 Reface pylon 148 sqft, replace 2 channel letter sets 84. 2 sqft and 47. 5 sqft., informational sign. Applicant: Lamson Nguyen | Permit status: Permisud | Expiration date: September 19, 2013 | Permit id: 1209190016 | |||||
SCORE 64 Electrical for add of an atm Date: November 6, 2009 Contractor: Niscayah, Inc Applicant: Lopez, Robert | Permit status: Finaled | Completion date: November 30, 2009 | Expiration date: November 6, 2010 | Permit id: 910300005 |