Content | Date | Cost | Contractor Rank | Address | Contractor |
---|---|---|---|---|---|
SCORE 95 Re-roof: tear off existing roof of 8 sqft of main office & install gaf timberline asphalt shingle roof astm: d3462 Engineer: Design Division | Applicant: Mike Ferring | Permit status: Finaled | Completion date: July 22, 2014 | Expiration date: August 13, 2014 | Permit id: 1308130073 | |||||
SCORE 95 Re-roof:tear off existing roof of 28 sqft of crew room & install gaf timberline asphalt shingle roof astm: d3462 Engineer: Design Division | Applicant: Mike Ferring | Permit status: Finaled | Completion date: July 22, 2014 | Expiration date: August 13, 2014 | Permit id: 1308130075 | |||||
SCORE 95 Replace wash bay with new wash bay - new steel structure Applicant: Mike Ferrin | Permit status: Finaled | Completion date: July 22, 2014 | Expiration date: February 11, 2015 | Permit id: 1309190079 | |||||
SCORE 95 Remove existing meter service panel board. Install new concr ete pad for diesel fuel standby generator,automatic transfer switch, 200amp panel board,receptacles, conduit, wires, & Engineer: Alberto De La Merced | Applicant: Alberto De La Merced | Permit status: Finaled | Completion date: July 2, 2015 | Expiration date: September 11, 2015 | Permit id: 1402200003 | |||||
SCORE 95 Replace (e) steel canopy for fuel island (e) columns to remain. Engineer: Alberto De La Merced | Applicant: Eduardo Ruvalcaba | Permit status: Finaled | Completion date: July 22, 2014 | Expiration date: June 12, 2015 | Permit id: 1406120050 | |||||
SCORE 82 Underground storage tank upgrades. Job no. Gmdpwtanks Date: May 18, 2004 Contractor: W H Mcalpine Applicant: Mcalpine William | Permit status: Finaled | Completion date: May 27, 2004 | Expiration date: November 14, 2004 | Permit id: 405120045 | |||||
SCORE 95 Install light fixture on canopy Date: June 12, 2014 Contractor: Torres Construction Corp Engineer: Alberto De La Merced | Applicant: Eduardo Ruvalcaba | Permit status: Finaled | Completion date: July 22, 2014 | Expiration date: June 12, 2015 | Permit id: 1406120083 | |||||
SCORE 95 Install new diesel stand-by generator & new 200amp panel Date: September 11, 2014 Contractor: Torres Construction Corp Engineer: Alberto De La Merced | Applicant: Alberto De La Merced | Permit status: Finaled | Completion date: July 2, 2015 | Expiration date: September 11, 2015 | Permit id: 1409110046 | |||||
SCORE 82 Remove & replace 20 gal gas tank, install 40 gal diesel 5 gal waste oil tanks to remain. Remove & replace piping tank appurtenances, electrical, fuel island and fuel mgmt sy Engineer: Fred Fiedler And Associates | Applicant: Guerrero Jolene | Permit status: Finaled | Completion date: May 27, 2004 | Expiration date: October 1, 2004 | Permit id: 308140061 | |||||
SCORE 100 Re-roof: tear off existing roof of 8 sqft of main office & install gaf timberline asphalt shingle roof astm: d3462 Engineer: Design Division | Applicant: Mike Ferring | Permit status: Finaled | Completion date: July 22, 2014 | Expiration date: August 13, 2014 | Permit id: 1308130073 | |||||
SCORE 100 Re-roof:tear off existing roof of 28 sqft of crew room & install gaf timberline asphalt shingle roof astm: d3462 Engineer: Design Division | Applicant: Mike Ferring | Permit status: Finaled | Completion date: July 22, 2014 | Expiration date: August 13, 2014 | Permit id: 1308130075 | |||||
SCORE 100 Replace wash bay with new wash bay - new steel structure Applicant: Mike Ferrin | Permit status: Finaled | Completion date: July 22, 2014 | Expiration date: February 11, 2015 | Permit id: 1309190079 | |||||
Install 200a, 480v 277v Date: February 23, 2016 Applicant: Same As Owner | Permit status: Permisud | Expiration date: February 22, 2017 | Permit id: 1602230010 | |||||
Install 3 inch gas line for cng station. Date: March 23, 2016 Applicant: Same As Owner | Permit status: Permisud | Expiration date: March 23, 2017 | Permit id: 1509210009 |