Content | Date | Cost | Contractor Rank | Address | Contractor |
---|---|---|---|---|---|
Alteration permit Date: September 28, 2016 Client: Gly Investments Llc | Permit status: Active | Permit id: 710501 | |||||
Alteration permit Date: September 28, 2016 Client: Gly Investments Llc | Permit status: Active | Permit id: 710501 | |||||
SCORE 74 Make safe per submitted engineers report to comply id case # 428586. No other work permitted under this application. All work per plans and report submitted by alex rong, pe. Scope includes concrete parging, partial framing on 1st, 2nd, & 3rd floors and new roof. No more than 2 3 of joist to be replaced, otherwise a separate permit is required for demolition. Separate permits required for interior alteration. Height and footprint not to exceed existing structure. Date: September 28, 2016 Contractor: Millennial Investment Group Client: Gly Investments Llc | Permit type: Alteration permit | Permit status: Completed | Completion date: March 21, 2017 | Permit id: 710501 | |||||
Use to 4 units Date: April 3, 2017 Client: Gly Investments Llc | Permit type: Use permit | Permit status: Completed | Completion date: April 3, 2017 | Permit id: 771433 | |||||
For a complete change in occupancy classification to create a three-family dwelling in an existing three-story attached structure. Work to include interior alterations and selective reconstruction of exterior walls. Building shall be fully sprinklered (nfpa 13r min.). Separate permits required for mechanical, electrical, plumbing, and fire suppression systems. All asbestos to be treated and removed prior to commencement of work. Date: June 7, 2017 Client: Gly Investments Llc | Permit type: Alteration permit | Permit status: Active | Completion date: November 20, 2017 | Permit id: 762430 | |||||
For use as three(3) dwelling units in an existing three story structure. Date: April 26, 2017 Client: Gly Investments Llc | Permit type: Use permit | Permit status: Completed | Completion date: April 26, 2017 | Permit id: 778511 | |||||
SCORE 100 Install (3) hvac systems with ductwork. (multi-family) Date: August 8, 2017 Contractor: Above And Below Heating And Air Client: Gly Investments Llc | Permit type: Mechanical permit | Permit status: Active | Completion date: November 27, 2017 | Permit id: 806554 | |||||
SCORE 100 Alterations: interior plumbing;change in occupancy; create a three-family dwelling; three-story attached structure; replace water and drain lines to 29 fixtures 3 washers,3 kitchen sinks,8 lavs and 7 toilets - the installation will comply with the philadephia plubming code 2004 Date: September 21, 2017 Contractor: Best Choice Plumbing Inc Client: Gly Investments Llc | Permit type: Plumbing permit | Permit status: Active | Completion date: November 15, 2017 | Permit id: 806606 | |||||
SCORE 100 Install new fire alrm pane, 1 remote annuniciator, 1 smoke, 2 pulls, 2 horn strobes, 12 horns, 2 monitor modules as per nfpa72 (west district) Date: November 30, 2017 Contractor: B H Holding Company Client: Gly Investments Llc | Permit type: Electrical permit | Permit status: Active | Completion date: November 30, 2017 | Permit id: 828491 |