Zoning/use permit Date: August 22, 2012 Client: H Kulp Inc | Permit status: Completed | Permit id: 410590 | |||||
Demolition permit Date: June 25, 2013 Client: H Kulp Inc | Permit status: Completed | Permit id: 479622 | |||||
Sign permit Date: January 4, 2011 Client: H Kulp Inc | Permit status: Completed | Permit id: 311256 | |||||
Use permit Date: July 28, 2015 Client: H Kulp Inc | Permit status: Completed | Permit id: 627777 | |||||
Zoning/use permit Date: March 14, 2016 Client: H Kulp Inc | Permit status: Completed | Permit id: 660420 | |||||
Electrical permit Date: December 7, 2015 Client: H Kulp Inc | Permit status: Completed | Permit id: 649937 | |||||
Plumbing permit Date: October 5, 2015 Client: H Kulp Inc | Permit status: Completed | Permit id: 634481 | |||||
Electrical permit Date: February 17, 2016 Client: H Kulp Inc | Permit status: Expired | Permit id: 668650 | |||||
Suppression permit Date: July 22, 2010 Client: H Kulp Inc | Permit status: Completed | Permit id: 292552 | |||||
Mechanical permit Date: September 17, 2010 Client: H Kulp Inc | Permit status: Completed | Permit id: 301806 | |||||
Mechanical permit Date: August 27, 2013 Client: H Kulp Inc | Permit status: Expired | Permit id: 487604 | |||||
Alteration permit Date: August 5, 2013 Client: H Kulp Inc | Permit status: Expired | Permit id: 482177 | |||||
Sign permit Date: September 10, 2012 Client: H Kulp Inc | Permit status: Completed | Permit id: 424665 | |||||
Plumbing permit Date: November 20, 2013 Client: H Kulp Inc | Permit status: Completed | Permit id: 493918 | |||||
Suppression permit Date: July 24, 2013 Client: H Kulp Inc | Permit status: Expired | Permit id: 485169 | |||||
Use permit Date: March 4, 2014 Client: H Kulp Inc | Permit status: Completed | Permit id: 519495 | |||||
Zoning/use permit Date: November 12, 2010 Client: H Kulp Inc | Permit status: Completed | Permit id: 310174 | |||||
Electrical permit Date: August 8, 2013 Client: H Kulp Inc | Permit status: Completed | Permit id: 480363 | |||||
Administrative permit Date: December 8, 2015 Client: H Kulp Inc | Permit status: Completed | Permit id: 643528 | |||||
Sign permit Date: March 14, 2016 Client: H Kulp Inc | Permit status: Completed | Permit id: 660422 | |||||
Alteration permit Date: August 4, 2010 Client: H Kulp Inc | Permit status: Completed | Permit id: 291219 | |||||
Use permit Date: August 5, 2013 Client: H Kulp Inc | Permit status: Completed | Permit id: 485828 | |||||
Alteration permit Date: July 28, 2015 Client: H Kulp Inc | Permit status: Completed | Permit id: 624117 | |||||
Electrical permit Date: August 17, 2010 Client: H Kulp Inc | Permit status: Completed | Permit id: 296637 | |||||
Alteration permit Date: August 4, 2010 Client: H Kulp Inc | Permit status: Completed | Permit id: 291219 | |||||
Sign permit Date: January 4, 2011 Client: H Kulp Inc | Permit status: Completed | Permit id: 311256 | |||||
Mechanical permit Date: September 17, 2010 Client: H Kulp Inc | Permit status: Completed | Permit id: 301806 | |||||
Alteration permit Date: June 17, 2013 Client: H Kulp Inc | Permit status: Completed | Permit id: 475182 | |||||
Zoning use permit Date: August 22, 2012 Client: H Kulp Inc | Permit status: Completed | Permit id: 410590 | |||||
Plumbing permit Date: July 16, 2013 Client: H Kulp Inc | Permit status: Completed | Permit id: 483395 | |||||
Electrical permit Date: August 8, 2013 Client: H Kulp Inc | Permit status: Completed | Permit id: 480363 | |||||
Use permit Date: July 28, 2015 Client: H Kulp Inc | Permit status: Completed | Permit id: 627777 | |||||
Suppression permit Date: July 24, 2013 Client: H Kulp Inc | Permit status: Expired | Permit id: 485169 | |||||
Demolition permit Date: June 25, 2013 Client: H Kulp Inc | Permit status: Completed | Permit id: 479622 | |||||
Electrical permit Date: February 17, 2016 Client: H Kulp Inc | Permit status: Expired | Permit id: 668650 | |||||
Administrative permit Date: December 8, 2015 Client: H Kulp Inc | Permit status: Completed | Permit id: 643528 | |||||
Use permit Date: February 11, 2014 Client: H Kulp Inc | Permit status: Completed | Permit id: 514664 | |||||
Sign permit Date: September 10, 2012 Client: H Kulp Inc | Permit status: Completed | Permit id: 424665 | |||||
Zoning use permit Date: March 14, 2016 Client: H Kulp Inc | Permit status: Completed | Permit id: 660420 | |||||
Sign permit Date: March 14, 2016 Client: H Kulp Inc | Permit status: Completed | Permit id: 660422 | |||||
Suppression permit Date: July 22, 2010 Client: H Kulp Inc | Permit status: Completed | Permit id: 292552 | |||||
Electrical permit Date: August 17, 2010 Client: H Kulp Inc | Permit status: Completed | Permit id: 296637 | |||||
Electrical permit Date: December 7, 2015 Client: H Kulp Inc | Permit status: Completed | Permit id: 649937 | |||||
Mechanical permit Date: August 2, 2013 Client: H Kulp Inc | Permit status: Completed | Permit id: 484211 | |||||
Use permit Date: August 5, 2013 Client: H Kulp Inc | Permit status: Completed | Permit id: 485828 | |||||
Alteration permit Date: July 28, 2015 Client: H Kulp Inc | Permit status: Completed | Permit id: 624117 | |||||
Zoning use permit Date: November 12, 2010 Client: H Kulp Inc | Permit status: Completed | Permit id: 310174 | |||||
Plumbing permit Date: October 5, 2015 Client: H Kulp Inc | Permit status: Completed | Permit id: 634481 | |||||
SCORE 99 Interior demo of selective non load bearing interior partitions. Date: June 25, 2013 Contractor: The Rc Co Inc Client: H Kulp Inc | Permit type: Demolition permit | Permit status: Completed | Completion date: September 26, 2013 | Permit id: 479622 | |||||
Install interior to existing warehouse and office space Date: August 4, 2010 Client: H Kulp Inc | Permit type: Alteration permit | Permit status: Completed | Completion date: October 22, 2010 | Permit id: 291219 | |||||
SCORE 100 Relocate 14 existing sprinkler heads(commercial) Date: July 22, 2010 Contractor: A And S Sprinkler Co Inc Client: H Kulp Inc | Permit type: Suppression permit | Permit status: Completed | Completion date: October 22, 2010 | Permit id: 292552 | |||||
SCORE 99 Demolition of power relocation of lighting fixtures and outlets addition of (5) new 2x4 lights and (8) outlets all service switchgear is existing to remain with no new work being done(per 2008 nec code) Date: August 17, 2010 Contractor: Steven Keares Client: H Kulp Inc | Permit type: Electrical permit | Permit status: Completed | Completion date: January 27, 2012 | Permit id: 296637 | |||||
Tenant fit out in space 1 for juice manufacturing and accessory storage (limited industrial) Date: August 5, 2013 Client: H Kulp Inc | Permit type: Use permit | Permit status: Completed | Completion date: August 5, 2013 | Permit id: 485828 | |||||
SCORE 100 Rework electrical distribution new and relocated lighting and controls,receptacles,power to equipment per 2008 nec (commercial) Date: December 2, 2013 Contractor: H B Frazer Co Penna Client: H Kulp Inc | Permit type: Electrical permit | Permit status: Revoked | Completion date: February 5, 2014 | Permit id: 487462 | |||||
SCORE 100 Relocate (5) existing sprinkler heads in order to accommodate tenant wall and ceiling layout as per all nfpa no. 13 and local codes. Date: July 24, 2013 Contractor: A And S Sprinkler Co Inc Client: H Kulp Inc | Permit type: Suppression permit | Permit status: Expired | Completion date: May 7, 2014 | Permit id: 485169 | |||||
Level ii alterations for a tenant fitout in space 1 of an existing facility as per approved plans additional permits are required for electrical, plumbing, hvac and plumbing Date: August 5, 2013 Client: H Kulp Inc | Permit type: Alteration permit | Permit status: Expired | Completion date: May 7, 2014 | Permit id: 482177 | |||||
SCORE 65 Interior plumbing alterations - space # 103 - sixt rent a car - replace plumbing fixtures in toilet rooms - replace (1)urinal with a water closet for use in the ladies toilet room - add a floor drain and connect to the sanitary drainage system via an oil separator - the floor drain requires a trap primer per section p-1204. 3. 2 or an approved trap primer alternative complying with the departments code bulletin of information no. 0901 r3 dated 02. 25. 2013 - the floor drain may require venting to comply with section p-1105 of the philadelphia plumbing code 2004 Date: October 5, 2015 Contractor: Ajb Mechanical Inc Client: H Kulp Inc | Permit type: Plumbing permit | Permit status: Completed | Completion date: March 6, 2016 | Permit id: 634481 | |||||
SCORE 100 Install 2 flat wall signs 4x24"-8" 1 freestanding sign 5x10 Date: March 14, 2016 Contractor: Futura Identities Client: H Kulp Inc | Permit type: Zoning/use permit | Permit status: Completed | Completion date: March 14, 2016 | Permit id: 660420 | |||||
SCORE 100 Install one set of channel letters to front wall 28" x 921 8 = 24. 5 sq ft Date: September 10, 2012 Contractor: Pro Sign Co Client: H Kulp Inc | Permit type: Sign permit | Permit status: Completed | Completion date: January 11, 2013 | Permit id: 424665 | |||||
Interior alterations to create three (3) vacant tenant spaces for future use and the creation of two multi-tenant toilet facilities. Certificate of occupancies required prior to occupancy of each tenant space. Separate permits required for electrical, plumbing, mechanical and fire suppression systems. Date: June 17, 2013 Client: H Kulp Inc | Permit type: Alteration permit | Permit status: Completed | Completion date: September 3, 2014 | Permit id: 475182 | |||||
SCORE 100 Relocation of 6 existing supply or return diffusers Date: September 17, 2010 Contractor: Liberty Mechanical Services In Client: H Kulp Inc | Permit type: Mechanical permit | Permit status: Completed | Completion date: October 13, 2010 | Permit id: 301806 | |||||
Creation of three tenant spaces from one. Space #102 to remain as warehouse pennock florist. Space # 100; 101 to remain vacant. Separate use registration permits are required prior to occupancy permissible in the zoning classification of i-2. No additions or alteration to the exterior are planned. No change in the building exterior height or number of stories. Date: February 11, 2014 Client: H Kulp Inc | Permit type: Use permit | Permit status: Completed | Completion date: February 11, 2014 | Permit id: 514664 | |||||
SCORE 86 Install 5- 2- port data jacks, 10- cat 5e cables... In accordance with 2008 nec Date: February 17, 2016 Contractor: Delaney Telecom Client: H Kulp Inc | Permit type: Electrical permit | Permit status: Expired | Completion date: February 17, 2016 | Permit id: 668650 | |||||
SCORE 100 Add recessed lighting & receptacles to reception area. Relocate existing service. 480 277v secondary service to tenant space service is 200amp as per nec 2008 west district Date: December 7, 2015 Contractor: Hawke Electrical Client: H Kulp Inc | Permit type: Electrical permit | Permit status: Completed | Completion date: March 8, 2016 | Permit id: 649937 | |||||
SCORE 61 Interior exterior alterations. New partitions, fit out, finishes, new exterior roll up garage door, doors, window, furnishings for new auto rental spaces in existing tenant space. Building fully sprinklered. Additional permits req: electrical, plumbing, hvac, sprinklers, signs. Date: July 28, 2015 Contractor: Molloy Construction Services Client: H Kulp Inc | Permit type: Alteration permit | Permit status: Completed | Completion date: March 2, 2016 | Permit id: 624117 | |||||
SCORE 61 Alterations to existing unoccupied space to accomodate new car rental business Date: July 28, 2015 Contractor: Molloy Construction Services Client: H Kulp Inc | Permit type: Use permit | Permit status: Completed | Completion date: July 28, 2015 | Permit id: 627777 | |||||
Use for space #101. Reliant headquarters - billing & invoice offices - (#1 & #102 to remain the same as previously permitted #514664 Date: March 4, 2014 Client: H Kulp Inc | Permit type: Use permit | Permit status: Completed | Completion date: March 4, 2014 | Permit id: 519495 | |||||
SCORE 100 Installation of new sinks and floor drains for new tenant fount in existing bldg (juice manufacturing co) Date: November 20, 2013 Contractor: Voegele Mechanical Inc Client: H Kulp Inc | Permit type: Plumbing permit | Permit status: Completed | Completion date: February 5, 2014 | Permit id: 493918 | |||||
SCORE 96 Installation of two bathrooms: (6) water closets, (6)lavatories, (2)urinals, (2)floor drains, (1)drinking fountain Date: July 16, 2013 Contractor: T Kelly Inc Client: H Kulp Inc | Permit type: Plumbing permit | Permit status: Completed | Completion date: October 8, 2013 | Permit id: 483395 | |||||
SCORE 100 Demolish and install new ductwork and diffusers registers within tenant spaces 1 and 101 as per plans. Date: August 2, 2013 Contractor: Cms Mechanical Inc Client: H Kulp Inc | Permit type: Mechanical permit | Permit status: Completed | Completion date: October 8, 2013 | Permit id: 484211 | |||||
SCORE 100 Remove signs and replace with new signs as per plans (2 freestanding and 2 flatwall). Date: January 4, 2011 Contractor: Pro Sign Co Client: H Kulp Inc | Permit type: Sign permit | Permit status: Completed | Completion date: August 10, 2011 | Permit id: 311256 | |||||
Alteration of existing hvac system as part of tenant fit-out as per approved plans. Date: August 27, 2013 Client: H Kulp Inc | Permit type: Mechanical permit | Permit status: Expired | Completion date: October 28, 2014 | Permit id: 487604 | |||||
SCORE 61 Amend permit #624117 for additional accessible work for bathrooms, add one wall for electric utility area. Date: December 8, 2015 Contractor: Molloy Construction Services Client: H Kulp Inc | Permit type: Administrative permit | Permit status: Completed | Completion date: March 5, 2016 | Permit id: 643528 | |||||
SCORE 100 Installation of 4,0 psi concrete footing with bolted plate attachment to anchor rods as hold downs for single steel post with welded gussets and aluminum double-faced sign cabinet (f s sign) and two (2) sets of stud mounted channel letters (wall signs) per engineers plan. Separate permit required for any electrical work. All work contained within property line, no right-of-way encorachments Date: March 14, 2016 Contractor: Futura Identities Client: H Kulp Inc | Permit type: Sign permit | Permit status: Completed | Completion date: July 19, 2016 | Permit id: 660422 | |||||
SCORE 100 Provide (3) distribution panel refeed rtus from new panels lighting and receptacles for new restrooms and electric rooms new meters relocate emergency battery lights add (2) fire alarm horn strobes per 2008 nec & nfpa 72 (warehouse) fa drawing to follow Date: August 8, 2013 Contractor: H B Frazer Co Penna Client: H Kulp Inc | Permit type: Electrical permit | Permit status: Completed | Completion date: November 21, 2015 | Permit id: 480363 |