Content | Date | Cost | Contractor Rank | Address | Contractor |
---|---|---|---|---|---|
Mechanical permit Date: August 9, 2013 Client: Wicks Judith A | Permit status: Completed | Permit id: 485245 | |||||
Use permit Date: June 16, 2014 Client: Wicks Judith A | Permit status: Completed | Permit id: 536753 | |||||
Electrical permit Date: April 8, 2010 Client: Wicks Judith A | Permit status: Completed | Permit id: 271451 | |||||
Alteration permit Date: July 9, 2014 Client: Wicks Judith A | Permit status: Completed | Permit id: 544061 | |||||
Plumbing permit Date: July 15, 2014 Client: Wicks Judith A | Permit status: Completed | Permit id: 549366 | |||||
Electrical permit Date: September 8, 2014 Client: Wicks Judith A | Permit status: Completed | Permit id: 550888 | |||||
Mechanical permit Date: October 14, 2014 Client: Wicks Judith A | Permit status: Completed | Permit id: 560677 | |||||
Electrical permit Date: July 21, 2014 Client: Wicks Judith A | Permit status: Completed | Permit id: 550357 | |||||
Mechanical permit Date: October 14, 2014 Client: Wicks Judith A | Permit status: Completed | Permit id: 560677 | |||||
Use permit Date: June 16, 2014 Client: Wicks Judith A | Permit status: Completed | Permit id: 536753 | |||||
Electrical permit Date: April 8, 2010 Client: Wicks Judith A | Permit status: Completed | Permit id: 271451 | |||||
Mechanical permit Date: August 9, 2013 Client: Wicks Judith A | Permit status: Completed | Permit id: 485245 | |||||
Alteration permit Date: July 9, 2014 Client: Wicks Judith A | Permit status: Completed | Permit id: 544061 | |||||
Plumbing permit Date: July 15, 2014 Client: Wicks Judith A | Permit status: Completed | Permit id: 549366 | |||||
SCORE 100 New 200a arial service for temporary construction office, single phase, three wire, 120 2 volt, one meter. Will utilize 4 ser cable for new arial service as per 2008 nec (west district) Date: April 8, 2010 Contractor: Anmar Electrical Contractor In Client: Wicks Judith A | Permit type: Electrical permit | Permit status: Completed | Completion date: July 6, 2010 | Permit id: 271451 | |||||
SCORE 83 For part. Demolition of exist. Hvac system & for installation of heat pump rooftop unit (rtu), one (1) split system ceiling mounted heat pump (hp), one (1) rooftop mounted kitchen exhaust fan (kef) for conn. To exist. Comm. Kitcehn exhaust hood, (11) grilles, registers, diffusers (grds), & all associated supply, return, & exhaust ductwork for a exist. Commercial kitchen space . All permitted work in accordance with plans approved by phc dated 06. 29. 13. Date: August 9, 2013 Contractor: J M Oliver Inc Client: Wicks Judith A | Permit type: Mechanical permit | Permit status: Completed | Completion date: April 15, 2014 | Permit id: 485245 | |||||
Convert existing 2nd and 3rd floor bi-level apartment inot two separate group living units, one grou unit at the second floor and (1) group unit at the third floor. Date: June 16, 2014 Client: Wicks Judith A | Permit type: Use permit | Permit status: Completed | Completion date: June 16, 2014 | Permit id: 536753 | |||||
For a change in occupancy (no change in occ. Classification) on the second and third floors of an existing three-story structure to create a congregate living facility (max 16 persons). Work to include new selective floor infill, interior non-bearing partitions, fire-rated enclosure (and door) construction and skylight installation as shown in plans approved by phila. Historic commission 05. 14. 14. Separate permits required for mechanical, electrical and plumbing systems. Date: July 9, 2014 Client: Wicks Judith A | Permit type: Alteration permit | Permit status: Completed | Completion date: October 21, 2014 | Permit id: 544061 | |||||
SCORE 100 Rough in new waste and water lines for toilet, lavatory, shower, bathtub, kitchen sink, clothes washer. All drainage and water in copper tubing Date: July 15, 2014 Contractor: Luke Barone Client: Wicks Judith A | Permit type: Plumbing permit | Permit status: Completed | Completion date: October 23, 2014 | Permit id: 549366 | |||||
SCORE 100 Separate circuits for 2nd and 3rd floor panels for respective floors, move circuits from panel to panel or re-feed orphaned electrical point. Replace to switches and outlets and to 15 fixtures.. In accordance with 2008 nec Date: July 21, 2014 Contractor: Generation 3 Electric Inc Client: Wicks Judith A | Permit type: Electrical permit | Permit status: Completed | Completion date: September 6, 2014 | Permit id: 550357 | |||||
SCORE 100 1 fa panel, 1 comm cellular dialer, 1 nac power supply panel, 2 annun keypoads, manual pull stations, 14 common area smokes, 17 c. M. Horn strobes & 5 c. M strobes, 2 heat detects, 1 kitchen supp trip, 8-120v combo smoke co detectors as per nfpa72 (west district) Date: September 8, 2014 Contractor: Alert One Protection Inc Client: Wicks Judith A | Permit type: Electrical permit | Permit status: Completed | Completion date: May 27, 2015 | Permit id: 550888 | |||||
SCORE 62 For the installation of one (1) roof top unit as per manufacturers specifications. No ductwork or registers diffusers on this permit. Date: October 14, 2014 Contractor: Adrian Pritchard Construction Client: Wicks Judith A | Permit type: Mechanical permit | Permit status: Completed | Completion date: October 23, 2014 | Permit id: 560677 | |||||
SCORE 100 Add two additional meters for two existing panels as per 2008 nec (west district) Date: November 5, 2014 Contractor: Generation 3 Electric Inc Client: Wicks Judith A | Permit type: Electrical permit | Permit status: Expired | Completion date: November 5, 2014 | Permit id: 571938 | |||||
SCORE 100 Replacement of two (2) existing roof top units and interior air handling units as per approved plans. Date: September 18, 2017 Contractor: Edward B Oreilly And Assoc Inc Client: Wicks Judith A | Permit type: Mechanical permit | Permit status: Active | Completion date: October 13, 2017 | Permit id: 813043 |