New construction permit Date: September 19, 2016 Client: Qcsi One Llc | Permit status: Active | Permit id: 672234 | |||||
Zoning/use permit Date: September 19, 2016 Client: Qcsi One Llc | Permit status: Completed | Permit id: 672233 | |||||
Alteration permit Date: December 7, 2015 Client: Qcsi One Llc | Permit status: Completed | Permit id: 656260 | |||||
Mechanical permit Date: May 24, 2011 Client: Qcsi One Llc | Permit status: Completed | Permit id: 336958 | |||||
New construction permit Date: May 24, 2011 Client: Qcsi One Llc | Permit status: Completed | Permit id: 342291 | |||||
Electrical permit Date: September 21, 2011 Client: Qcsi One Llc | Permit status: Completed | Permit id: 364343 | |||||
Permit for the documentation of the complete demolition of an existing detached structure. For the erection of a new detached structure (fueling island canopy) as part of an existing vehicle fueling station on the same lot with existing retail sales of food, beverages, groceries, pharmaceuticals, sundries and convenience items in a detached structure with a total of eleven (11) accessory surface parking spaces including one (1) accessible space as preivously approved. Size and location as shown in application / plan. Date: May 17, 2016 Client: Qcsi One Llc | Applicant: Laurel Walyga | Permit type: Appeal | Permit status: Granted/prov | Completion date: August 12, 2016 | Permit id: 27864 | |||||
New construction permit Date: September 19, 2016 Client: Qcsi One Llc | Permit status: Completed | Permit id: 672234 | |||||
Sign permit Date: January 12, 2017 Client: Qcsi One Llc | Permit status: Active | Permit id: 730551 | |||||
Electrical permit Date: November 15, 2016 Client: Qcsi One Llc | Permit status: Active | Permit id: 721749 | |||||
Electrical permit Date: September 21, 2011 Client: Qcsi One Llc | Permit status: Completed | Permit id: 364343 | |||||
Mechanical permit Date: May 24, 2011 Client: Qcsi One Llc | Permit status: Completed | Permit id: 336958 | |||||
Alteration permit Date: December 7, 2015 Client: Qcsi One Llc | Permit status: Completed | Permit id: 656260 | |||||
New construction permit Date: May 24, 2011 Client: Qcsi One Llc | Permit status: Completed | Permit id: 342291 | |||||
Zoning use permit Date: September 19, 2016 Client: Qcsi One Llc | Permit status: Completed | Permit id: 672233 | |||||
Permit for the documentation of the complete demolition of an existing detached structure. For the erection of a new detached structure (fueling island canopy) as part of an existing vehicle fueling station on the same lot with existing retail sales of food, beverages, groceries, pharmaceuticals, sundries and convenience items in a detached structure with a total of eleven (11) accessory surface parking spaces including one (1) accessible space as preivously approved. Size and location as shown in application plan. Date: May 17, 2016 Client: Qcsi One Llc | Applicant: Laurel Walyga | Permit type: Appeal | Permit status: Granted/prov | Completion date: August 12, 2016 | Permit id: 27864 | |||||
SCORE 100 Replacement of led lights with no additional wiring as per 2008 nec (west district) Date: September 21, 2011 Contractor: Livewire Electric Llc Client: Qcsi One Llc | Permit type: Electrical permit | Permit status: Completed | Completion date: June 24, 2015 | Permit id: 364343 | |||||
SCORE 78 Removal of damaged canopy over gasoline pump area. Date: December 7, 2015 Contractor: Doncor Inc Client: Qcsi One Llc | Permit type: Alteration permit | Permit status: Completed | Completion date: February 27, 2016 | Permit id: 656260 | |||||
SCORE 99 New construction of a steel frame fueling island overhead canopy on reinforced concrete foundations with associated roof trim, concrete pad and dispenser protection (u-bollards). All special inspection reports shall be furnished to field inspector; amended permit required for any unnamed inspectors separate permits required for any mechanical, electrical, plumbing and fire suppression systems. Date: September 19, 2016 Contractor: Christopher Constr. Co Inc Client: Qcsi One Llc | Permit type: New construction permit | Permit status: Completed | Completion date: January 9, 2017 | Permit id: 672234 | |||||
SCORE 67 Replacement storefront sign, replacement signs on existing freestanding sign. Existing steel support poles and concrete footer to remain. Fuel canopy signs Date: October 20, 2016 Contractor: Ua Projects Company Llc Client: Qcsi One Llc | Permit type: Zoning/use permit | Permit status: Completed | Completion date: October 20, 2016 | Permit id: 677210 | |||||
SCORE 100 Disconnect and reconnect 2 dispenser. Disconnect and re connect 2 interior speakers. Wire 6 canopy lights and 4 future signs per 2008 nec (gas station)east district Date: November 15, 2016 Contractor: Vitale Philip J Client: Qcsi One Llc | Permit type: Electrical permit | Permit status: Completed | Completion date: April 6, 2017 | Permit id: 721749 | |||||
SCORE 67 For the erection of one (1) freestanding sign and two (2) wall signs as per approved plans. Separate permit required for any electrical work. Date: January 12, 2017 Contractor: Ua Projects Company Llc Client: Qcsi One Llc | Permit type: Sign permit | Permit status: Completed | Completion date: October 30, 2017 | Permit id: 730551 | |||||
SCORE 100 Removal of existing underground piping and dispensers. Installation of new piping, dispensers for convenience store gas station. Date: May 24, 2011 Contractor: Monridge Construction Inc Client: Qcsi One Llc | Permit type: Mechanical permit | Permit status: Completed | Completion date: December 27, 2011 | Permit id: 336958 | |||||
SCORE 100 Removal of existing underground storage tanks and installation of new underground storage tank. See a p 336958 for plans Date: May 24, 2011 Contractor: Monridge Construction Inc Client: Qcsi One Llc | Permit type: New construction permit | Permit status: Completed | Completion date: July 5, 2011 | Permit id: 342291 | |||||
SCORE 100 Remove exist gasoline disps elect conduit from tanks dispensers to bldg,run new elec conduit from bldg to tanks disps,pull new twisted wire belden cable to tanks disps inst 2-gilbarco encore 3 disps,2-intrins safe atg probes,2-fe petro 1. 5 hp turbine pumps,install 1 emerg stop Date: May 24, 2011 Contractor: Lai John Client: Qcsi One Llc | Permit type: Electrical permit | Permit status: Expired | Completion date: July 9, 2012 | Permit id: 336929 |