Content | Date | Cost | Contractor Rank | Address | Contractor |
---|---|---|---|---|---|
Zoning/use permit Date: July 17, 2008 Client: Rubin Seymore | Permit status: Completed | Permit id: 164699 | |||||
Electrical permit Date: April 25, 2008 Client: Rubin Seymore | Permit status: Completed | Permit id: 145164 | |||||
Plumbing permit Date: March 7, 2008 Client: Rubin Seymore | Permit status: Completed | Permit id: 134342 | |||||
Fast form building permit Date: January 21, 2009 Client: Rubin Seymore | Permit status: Completed | Permit id: 197589 | |||||
Mechanical permit Date: January 18, 2008 Client: Rubin Seymore | Permit status: Completed | Permit id: 126845 | |||||
Use permit Date: December 6, 2007 Client: Rubin Seymore | Permit status: Completed | Permit id: 112455 | |||||
Alteration permit Date: January 18, 2008 Client: Rubin Seymore | Permit status: Completed | Permit id: 122557 | |||||
Sign permit Date: August 7, 2008 Client: Rubin Seymore | Permit status: Completed | Permit id: 165126 | |||||
Permit for an outpatient dalysis clinic with accessory parking as previously approved. Date: November 20, 2007 Client: Rubin Seymore | Applicant: Stephen G. Pollock, Esquire | Permit type: Appeal | Permit status: Granted/prov | Completion date: December 5, 2007 | Permit id: 4068 | |||||
Mechanical permit Date: January 18, 2008 Client: Rubin Mark H | Permit status: Completed | Permit id: 126845 | |||||
Zoning use permit Date: January 5, 2017 Client: Rubin Mark H | Permit status: Completed | Permit id: 727479 | |||||
Plumbing permit Date: March 7, 2008 Client: Rubin Mark H | Permit status: Completed | Permit id: 134342 | |||||
Zoning use permit Date: July 17, 2008 Client: Rubin Mark H | Permit status: Completed | Permit id: 164699 | |||||
Electrical permit Date: June 25, 2008 Client: Rubin Mark H | Permit status: Completed | Permit id: 159773 | |||||
Fast form building permit Date: January 21, 2009 Client: Rubin Mark H | Permit status: Completed | Permit id: 197589 | |||||
Alteration permit Date: January 18, 2008 Client: Rubin Mark H | Permit status: Completed | Permit id: 122557 | |||||
Use permit Date: December 6, 2007 Client: Rubin Mark H | Permit status: Completed | Permit id: 112455 | |||||
Sign permit Date: August 7, 2008 Client: Rubin Mark H | Permit status: Completed | Permit id: 165126 | |||||
Zoning permit Date: December 5, 2016 Client: Rubin Mark H | Permit status: Completed | Permit id: 708170 | |||||
Permit for an outpatient dalysis clinic with accessory parking as previously approved. Date: November 20, 2007 Client: Rubin Mark H | Applicant: Stephen G. Pollock, Esquire | Permit type: Appeal | Permit status: Granted/prov | Completion date: December 5, 2007 | Permit id: 4068 | |||||
SCORE 100 Install outlets and lighting. Install 4 amp 480 277v svs. Install 3 panels and (2) 4 to 120 208 75 kva transformer. (cc dist) Date: April 25, 2008 Contractor: Mcgoldrick Electric Inc Client: Rubin Mark H | Permit type: Electrical permit | Permit status: Completed | Completion date: August 12, 2008 | Permit id: 145164 | |||||
SCORE 59 Fit-out for dialsis center with accessory facilities Date: January 18, 2008 Contractor: K And K Franchise Construction Client: Rubin Mark H | Permit type: Alteration permit | Permit status: Completed | Completion date: July 3, 2008 | Permit id: 122557 | |||||
SCORE 59 Duct work as per plan. Date: January 18, 2008 Contractor: K And K Franchise Construction Client: Rubin Mark H | Permit type: Mechanical permit | Permit status: Completed | Completion date: August 11, 2008 | Permit id: 126845 | |||||
SCORE 100 Rough in & install 4 wc, 4 lavs, fl dr, 15 f. S, 17 sinks, 1 mop sink, 2 hwh and all related piping. Hd, stack Date: March 7, 2008 Contractor: Tandem Associates Inc Client: Rubin Mark H | Permit type: Plumbing permit | Permit status: Completed | Completion date: July 7, 2008 | Permit id: 134342 | |||||
To correct permit #727479 to revise the permit language to the following: for the erection of a semi-detached structure with balconies at each floor, accessory pool at the fourth floor roof level and enclosed parking garage. Structure to utilize public space, mixed-income housing, retail space (min. 10-6" finished ceiling height), stormwater open space, and green building (platinum) bonuses for increased floor area. All required agreements and documentation to be submitted before final permit issuance. Size and location as shown in plans. Structure to be used as retail sales on floors 1-2 (use registration permit required to register specific sub-category), parking garage on floors 1-4 (including one (1) floor of underground parking), and multi-family household living (four hundred, fifty-four (454) units) on floors 3-26. For the creation of three (3) new off-street loading spaces, the creation of one hundred, fifty-two (152) class ia bicycle parking spaces (located along an accessible Date: February 21, 2017 Client: Rubin Mark H | Permit type: Zoning admin review | Permit status: Completed | Completion date: February 21, 2017 | Permit id: 761074 | |||||
SCORE 100 Fast form building permit Date: January 21, 2009 Contractor: A And S Sprinkler Co Inc Client: Rubin Mark H | Permit status: Completed | Completion date: September 21, 2010 | Permit id: 197589 | |||||
For the lot adjustment to create one (1) lot from two (2) existing lots (309-15 callowhill street and 444 n. 3rd street, five (5) deeded lots: 309-15 & 317-29 callowhill street, 409 n. 4th street, and 411-41 & 418-36 n. 3rd street) and the complete demolition of all existing structures. Size and location as shown in plans. Date: December 5, 2016 Client: Rubin Mark H | Permit type: Zoning permit | Permit status: Completed | Completion date: December 5, 2016 | Permit id: 708170 | |||||
SCORE 89 Install (70) category 5e plenum voice data cables to various locations. As per 2005 nec articles 300. 21 & 800 Date: April 24, 2008 Contractor: Crystal Ball Contracting Inc Client: Rubin Mark H | Permit type: Electrical permit | Permit status: Expired | Completion date: April 24, 2008 | Permit id: 147531 | |||||
SCORE 100 Fire alarm: install horn strobes and initiating devices as per nfpa-72 (cc dist) Date: June 25, 2008 Contractor: Mcgoldrick Electric Inc Client: Rubin Mark H | Permit type: Electrical permit | Permit status: Completed | Completion date: December 26, 2008 | Permit id: 159773 | |||||
SCORE 99 1 awning, 1 flat wall sign (single face)1 set of interior glass door vinyl graphics Date: August 7, 2008 Contractor: Forman Signs Client: Rubin Mark H | Permit type: Sign permit | Permit status: Completed | Completion date: June 10, 2014 | Permit id: 165126 | |||||
For the erection of a semi-detached structure with balconies at each floor, community pool at the fourth floor roof level and enclosed parking garage. Structure to utilize public space, mixed-income housing, retail space (min. 10-6" finished ceiling height), stormwater open space, and green building (platinum) bonuses for increased floor area. All required agreements and documentation to be submitted before final permit issuance. Size and location as shown in plans. Structure to be used as retail sales on floors 1-2 (use registration permit required to register specific sub-category), parking garage on floors 1-4 (including one (1) floor of underground parking), and multi-family household living (four hundred, fifty-four (454) units) on floors 3-24. For the creation of three (3) new off-street loading spaces, the creation of one hundred, fifty-two (152) class ia bicycle parking spaces (located along an accessible route), and two hundred, thirty-three (233) off-street parking spaces (to Date: January 5, 2017 Client: Rubin Mark H | Permit type: Zoning/use permit | Permit status: Completed | Completion date: January 5, 2017 | Permit id: 727479 |