SCORE 100 Temp occupy alley and e side of 5th for demo construction Date: July 6, 2011 Contractor: Miller Enterprises Permit type: Row occupancy | Permit status: Issued | Permit id: En11-0574 | |||||
SCORE 92 Install new sanitary sewer service Date: September 23, 2011 Contractor: Lexington Construction Co Permit type: Sanitary sewer | Permit status: Issued | Permit id: En11-0845 | |||||
SCORE 98 Install new mh for storm sewer connection Date: October 6, 2011 Contractor: Hillshire Construction Permit type: Storm sewer | Permit status: Finaled | Completion date: October 5, 2011 | Permit id: En11-0880 | |||||
SCORE 100 Renew service Date: April 23, 2012 Contractor: Shaw Brothers Construction Permit type: Row excavation | Permit status: Issued | Permit id: En12-0394 | |||||
SCORE 100 Pavement degradation fee Date: November 8, 2012 Contractor: Shaw Brothers Construction Permit type: Row excavation | Permit status: Issued | Permit id: En12-1145 | |||||
SCORE 100 Pavement degradation fee Date: April 17, 2012 Contractor: Shaw Brothers Construction Permit type: Row excavation | Permit status: Issued | Permit id: En12-0348 | |||||
SCORE 100 Demo/sfd Client: Carl Hill | Permit type: Demo 1f2f | Permit status: Finaled | Completion date: February 16, 2012 | Permit id: Bs11-1216 |