SCORE 93 Digging (2) 1x1 test holes to check the water main elevation due to dpw project Date: July 13, 2011 Contractor: Abby Cudworth Client: North American Islamic Trust Inc The % S A Shah | Permit type: Right of way | Permit status: Complete | Permit id: Row11-03883 | |||||
SCORE 93 Dig 1 1x1 test hole to check the water main elevation nate schiller 317-213-1624 Date: August 24, 2011 Contractor: Abby Cudworth Client: Kamal Petroleum Inc | Permit type: Right of way | Permit status: Complete | Permit id: Row11-04835 | |||||
Row traffic lane use for southern most lane of 30th st just west of cold springs rd for flora remova Date: August 20, 2010 Client: North American Islamic Trust Inc The | Permit type: Right of way | Permit status: Complete | Permit id: Row10-04934 | |||||
SCORE 96 6x18 cut in asphalt street for main repair Date: January 14, 2011 Contractor: Sandy Briggs Client: Kamal Petroleum Inc | Permit type: Right of way | Permit status: Issued | Permit id: Row11-00252 | |||||
SCORE 93 Lowering (2) 12 water mains due to dpw storm water improvement project Date: September 2, 2011 Contractor: Abby Cudworth Client: Kamal Petroleum Inc | Permit type: Right of way | Permit status: Complete | Permit id: Row11-05053 | |||||
SCORE 96 Fire line retiral alice nicks 317-263-6389 Date: August 4, 2014 Contractor: Sandy Briggs Client: Kamal Petroleum Inc | Permit type: Right of way | Permit status: Complete | Permit id: Row14-04249 | |||||
SCORE 96 Service repair vicky burton 317-927-4624 Date: November 21, 2012 Contractor: Vicky Burton Client: Kamal Petroleum Inc | Permit type: Right of way | Permit status: Complete | Permit id: Row12-06751 | |||||
Clear and fill of site - proposing to place non-compacted clean fill property. It should be noted t Date: September 22, 2011 Client: North American Islamic Trust Inc The % S A Shah | Permit type: Drainage | Permit status: Issued | Permit id: Drn11-01359 | |||||
Placement of fill at imca placement of approx. 100 cubic yards of fill over 3 acres. Date: April 9, 2010 Client: Imca | Permit type: Drainage | Permit status: Review | Permit id: Drn10-00402 | |||||
SCORE 89 Gratis permit total road closure dpw project #ss-24-001g: north belmont relief interceptor sec Date: July 20, 2010 Contractor: Patrick Merryman Client: Kamal Petroleum Inc | Permit type: Right of way | Permit status: Issued | Permit id: Row10-04124 | |||||
SCORE 80 Gratis permit total road closure dpw project #ss-24-001g: north belmont relief interceptor sec Date: July 20, 2010 Contractor: Ted Harmon Client: Kamal Petroleum Inc | Permit type: Right of way | Permit status: Issued | Permit id: Row10-04124 | |||||
SCORE 96 Gratis permit for united water per j. Lopez manhole repair for united water kent haste 317-223 Date: February 14, 2013 Contractor: Janet Haste Client: Kamal Petroleum Inc | Permit type: Right of way | Permit status: Complete | Permit id: Row13-00823 |