Content | Date | Cost | Contractor Rank | Address | Contractor |
---|---|---|---|---|---|
New sfd plan 1dx 1991/615 sq ft 5wider than plan 1 Date: March 31, 2000 Value: $162,000 Applicant: Same As Owner | Permit status: Finaled | Completion date: November 15, 2000 | Permit id: 0003310064 | |||||
SCORE 100 Shade bar patio 6x12 and 4x12 Applicant: Scott Construction | Permit status: Finaled | Completion date: July 9, 2001 | Permit id: 0106130051 | |||||
SCORE 99 Swimming pool and spa 3 sq ft laco std plan 26077 Applicant: Mhb Construction | Permit status: Finaled | Completion date: April 16, 2010 | Permit id: 0912080001 | |||||
SCORE 82 Electrical for new sfd Date: October 18, 2000 Contractor: Brennan Electric Applicant: Brennan Electric,Inc. | Permit status: Finaled | Completion date: November 15, 2000 | Permit id: 0010120012 | |||||
SCORE 99 Electrical for a/c (move location) Date: March 5, 2010 Contractor: Mhb Construction Applicant: Mhb Construction | Permit status: Finaled | Completion date: April 16, 2010 | Permit id: 1003050004 | |||||
SCORE 82 Mechanical for new sfd Date: August 31, 2000 Contractor: Sentry Mechanical Inc Applicant: Sentry Mechanical Inc, | Permit status: Finaled | Completion date: November 15, 2000 | Permit id: 0008290020 | |||||
SCORE 99 Move a/c unit Date: March 5, 2010 Contractor: Mhb Construction Applicant: Mhb Construction | Permit status: Finaled | Completion date: April 16, 2010 | Permit id: 1003050001 | |||||
SCORE 86 Plumbing for new sfd Date: May 24, 2000 Contractor: Addington Construction Applicant: Addington Construction Inc. | Permit status: Finaled | Completion date: November 15, 2000 | Permit id: 0005240006 | |||||
SCORE 86 Sewer for new sfd Date: June 14, 2000 Contractor: Addington Construction Applicant: Addington Construction Inc. | Permit status: Finaled | Completion date: November 15, 2000 | Permit id: 0006140005 |