Content | Date | Cost | Contractor Rank | Address | Contractor |
---|---|---|---|---|---|
SCORE 100 New commercial bldg 21,4 sq ft Applicant: Hpa | Permit status: Finaled | Completion date: December 2, 2002 | Permit id: 0012120028 | |||||
Ret wall 5 x 1 long Date: February 15, 2002 Value: $8,000 Applicant: Same As Owner | Permit status: Finaled | Completion date: December 2, 2002 | Permit id: 0202110003 | |||||
Ti office 2945 sq ft cut in 3x7 ft & 3 x 3 ft window into existing sheer wall Date: October 15, 2002 Value: $183,000 Applicant: Same As Owner | Permit status: Finaled | Completion date: December 2, 2002 | Permit id: 0209130044 | |||||
Ti--add offices 1st & 2nd floor 1292/1003 sq ft Date: September 9, 2003 Value: $70,000 Applicant: Same As Owner | Permit status: Permisud | Permit id: 0307290059 | |||||
SCORE 59 T. I. To install storage racks 3,959 sq ft Applicant: Siqueira Bira | Permit status: Finaled | Completion date: March 19, 2015 | Permit id: 1411030042 | |||||
SCORE 97 Elec for comm bldg 21,4 sq ft Date: June 12, 2002 Contractor: Fouts Electric Corp Applicant: Fouts Electric Corp | Permit status: Finaled | Completion date: December 2, 2002 | Permit id: 0105090035 | |||||
SCORE 100 Ti office 2945 sq ft install (1) transformer,45kva, (1) 100amp,(1) 200amp service panels,and (9) branch circuits. Date: October 16, 2002 Contractor: John Manninger Electric Applicant: John Manninger Electric | Permit status: Finaled | Completion date: December 2, 2002 | Permit id: 0209300010 | |||||
SCORE 64 Ti--electrical,outlets,switches & lighting Date: September 10, 2003 Contractor: First Electric Services Applicant: First Electric Services | Permit status: Permisud | Permit id: 0309100003 | |||||
SCORE 90 Mech for new bldg Date: December 28, 2001 Contractor: Mechanical Air Systems Inc Applicant: Mechanical Air Systems Inc | Permit status: Finaled | Completion date: December 2, 2002 | Permit id: 0112280007 | |||||
SCORE 87 Install new mechanical Date: October 21, 2002 Contractor: Design Air System Applicant: Design Air System | Permit status: Finaled | Completion date: December 2, 2002 | Permit id: 0210210008 | |||||
Ti--add offices 1st & 2nd floor Date: September 9, 2003 Applicant: Same As Owner | Permit status: Permisud | Permit id: 0309080024 | |||||
SCORE 79 Plumbing for new comm bldg Date: August 31, 2001 Contractor: Calstate Plumbing Applicant: Cal-State Plumbing | Permit status: Permisud | Permit id: 0108270010 | |||||
SCORE 99 Plumbing for ti Date: October 16, 2002 Contractor: Kennco Plumbing Applicant: Kennco Plumbing | Permit status: Finaled | Completion date: December 2, 2002 | Permit id: 0210160039 | |||||
SCORE 59 Plumbing for t. I. 1292/1003 sq ft Date: September 10, 2003 Contractor: Alona Plumbing Applicant: Alona Plumbing | Permit status: Permisud | Permit id: 0309100018 | |||||
SCORE 100 Sewer for future use Date: January 22, 2001 Contractor: Mechanical Plumbing Systems Inc Applicant: Mechanical Plumbing System | Permit status: Finaled | Completion date: December 2, 2002 | Permit id: 0101220029 |