Content | Date | Cost | Contractor Rank | Address | Contractor |
---|---|---|---|---|---|
Plumbing permit Date: December 7, 2011 Client: Delmar Development Llc | Permit status: Completed | Permit id: 377600 | |||||
Electrical permit Date: April 5, 2012 Client: Delmar Development Llc | Permit status: Completed | Permit id: 397619 | |||||
New construction permit Date: September 12, 2011 Client: Delmar Development Llc | Permit status: Completed | Permit id: 319649 | |||||
Zoning/use permit Date: December 22, 2010 Client: Delmar Development Llc | Permit status: Completed | Permit id: 306769 | |||||
Mechanical permit Date: November 29, 2011 Client: Delmar Development Llc | Permit status: Completed | Permit id: 376004 | |||||
Plumbing permit Date: December 7, 2011 Client: Delmar Development Llc | Permit status: Completed | Permit id: 377600 | |||||
Zoning use permit Date: December 22, 2010 Client: Delmar Development Llc | Permit status: Completed | Permit id: 306769 | |||||
Electrical permit Date: April 5, 2012 Client: Delmar Development Llc | Permit status: Completed | Permit id: 397619 | |||||
New construction permit Date: September 12, 2011 Client: Delmar Development Llc | Permit status: Completed | Permit id: 319649 | |||||
Mechanical permit Date: November 29, 2011 Client: Delmar Development Llc | Permit status: Completed | Permit id: 376004 | |||||
SCORE 93 3toilets, 3 lavs, 2 tubs, 1 ks, 1 laundry(sfd) Date: December 7, 2011 Contractor: Cesars Plumbing Inc Permit type: Plumbing permit | Permit status: Completed | Completion date: November 3, 2015 | Permit id: 377600 | |||||
SCORE 100 Installation of 1 hvac unit, btu 80,0 (york gas heat, a c), with ductwork included. Date: November 29, 2011 Contractor: Rosenberg Neil Permit type: Mechanical permit | Permit status: Completed | Completion date: July 11, 2012 | Permit id: 376004 | |||||
SCORE 100 Install 200a svc, ckts,45 outlets,15 switches, recessed lights, surface lights,7-120v smokes Date: April 5, 2012 Contractor: Sean Kearns Permit type: Electrical permit | Permit status: Completed | Completion date: July 6, 2012 | Permit id: 397619 | |||||
Construction of (1) sfd per plans if a design or construction contract for proposed work was signed between december 31, 2006 and december 30, 2009, the 2006 international codes must be complied with. Date: September 12, 2011 Permit type: New construction permit | Permit status: Completed | Completion date: September 14, 2012 | Permit id: 319649 | |||||
For the erection of a three (3) story attached structure with cellar (nothing above the 3rd floor) and 3rd floor terrace with 42" high railing maximum height not to exceed 35 feet for use as a single family dwelling with one (1) accessory off street parking space 86"x18 Date: December 22, 2010 Permit type: Zoning/use permit | Permit status: Completed | Completion date: December 23, 2010 | Permit id: 306769 |