SCORE 86 A c change out, like for like (2) units Date: September 14, 2001 Contractor: Calair Conditioning Co Applicant: Cal-Air Conitioning Co | Permit status: Finaled | Completion date: February 6, 2006 | Expiration date: March 13, 2002 | Permit id: 109140012 | |||||
SCORE 79 New ft combo hose tower. 4 new equipment cabinets. 6 new antennas and a new generator. Engineer: Mitchell J Architecture | Applicant: Tracy Gordon | Permit status: Permisud | Expiration date: March 24, 2016 | Permit id: 1411170028 | |||||
SCORE 99 Re roof fire station #111 Applicant: Lang Roofing Inc | Permit status: Finaled | Completion date: February 6, 2006 | Expiration date: April 30, 2002 | Permit id: 111010058 | |||||
SCORE 62 Plumbing for medium pressure gas system and 1 additional outlet. Date: September 29, 2009 Contractor: Applied Environmental Technologies Applicant: Jeff Kenney | Permit status: Finaled | Completion date: May 4, 2010 | Expiration date: September 29, 2010 | Permit id: 909280006 | |||||
SCORE 99 Re roof fire station #111 Applicant: Lang Roofing Inc | Permit status: Finaled | Completion date: February 6, 2006 | Expiration date: April 30, 2002 | Permit id: 111010058 | |||||
SCORE 62 Install extraction/treatment system, construct a 6ft wood fence Date: February 3, 2010 Contractor: Applied Environmental Technologies Applicant: Donahue Bailey | Permit status: Finaled | Completion date: May 14, 2010 | Expiration date: February 3, 2011 | Permit id: 1002030035 | |||||
SCORE 93 Re-install temp power pole for extraction/treatment system Date: December 18, 2012 Contractor: Frey Environmental Applicant: Andy Wittmann | Permit status: Finaled | Completion date: December 27, 2012 | Expiration date: December 18, 2013 | Permit id: 1212100040 | |||||
SCORE 93 Install temp power pole for extraction/treatment system Date: November 20, 2013 Contractor: Frey Environmental Applicant: Andy Wittmann | Permit status: Finaled | Completion date: December 19, 2013 | Expiration date: November 20, 2014 | Permit id: 1311200042 | |||||
SCORE 93 Install 3-phase temp power pole for extraction/treatment system Date: July 9, 2014 Contractor: Frey Environmental Applicant: Andy Wittmann | Permit status: Finaled | Completion date: July 22, 2014 | Expiration date: July 9, 2015 | Permit id: 1407090026 | |||||
SCORE 93 Change out 3-phase temp power pole to 1-phase for extraction /treatment system Date: September 18, 2014 Contractor: Frey Environmental Applicant: Andy Wittmann | Permit status: Finaled | Completion date: September 24, 2014 | Expiration date: September 18, 2015 | Permit id: 1409180045 |