Content | Date | Cost | Contractor Rank | Address | Contractor |
---|---|---|---|---|---|
Zoning/use permit Date: July 27, 2012 Client: Maple Hill Group Llc | Permit status: Completed | Permit id: 406241 | |||||
Suppression permit Date: October 25, 2013 Client: Maple Hill Group Llc | Permit status: Completed | Permit id: 486233 | |||||
Mechanical permit Date: October 2, 2013 Client: Maple Hill Group Llc | Permit status: Completed | Permit id: 497890 | |||||
Electrical permit Date: October 31, 2013 Client: Maple Hill Group Llc | Permit status: Completed | Permit id: 503623 | |||||
Plumbing permit Date: September 27, 2013 Client: Maple Hill Group Llc | Permit status: Completed | Permit id: 497446 | |||||
New construction permit Date: July 10, 2013 Client: Maple Hill Group Llc | Permit status: Completed | Permit id: 424724 | |||||
Zoning use permit Date: July 27, 2012 Client: Maple Hill Group Llc | Permit status: Completed | Permit id: 406241 | |||||
Erection of three (3) story structure with cellar, one (1) interior parking space, pilot house, roof deck as per plan for use as a single family dwelling. All work shall be done in accordance with approved plans & bbs variance building is to be fully sprinklered separate permit required for mechancial, electrical, plumbing, and fire supression work. Date: July 10, 2013 Permit type: New construction permit | Permit status: Completed | Completion date: January 31, 2014 | Permit id: 424724 | |||||
SCORE 100 New 5" lateral,5" curb trap, 4" main drain,install 3 toilets,3 vanities, 3 bathtubs,1 washer box, 1 kit snk(sfd) pa1 call#20132671549 Date: September 27, 2013 Contractor: Tommys Plumbing Permit type: Plumbing permit | Permit status: Completed | Completion date: January 31, 2014 | Permit id: 497446 | |||||
For the erection of a sfd front yard setback and front steps to 1st floor and interior parking stall with projected bay at 2nd floor Date: July 27, 2012 Permit type: Zoning/use permit | Permit status: Completed | Completion date: July 27, 2012 | Permit id: 406241 | |||||
SCORE 96 Install 200amp service,53 outlets, lighting fixtures,24 switches,a c & heat,oven,hot water water heater,smoke & carbon detectors per 2008 nec (sfd) Date: October 31, 2013 Contractor: Sfb Wiring Systems Llc Permit type: Electrical permit | Permit status: Completed | Completion date: June 4, 2014 | Permit id: 503623 | |||||
SCORE 100 Install 2 hvac units with ductwork(sfd) Date: October 2, 2013 Contractor: Talgar Inc Permit type: Mechanical permit | Permit status: Completed | Completion date: January 31, 2014 | Permit id: 497890 | |||||
SCORE 82 For the installation of a fire suppression system throughout a single-family dwelling in accodrance with nfpa 13d standards. System to include a 1" copper fire service main line & 1" cpvc risers, cross mains and branch lines. System is also to include a backflow prevention assembly. Date: October 25, 2013 Contractor: United States Sprinklers Permit type: Suppression permit | Permit status: Completed | Completion date: January 31, 2014 | Permit id: 486233 |