Content | Date | Cost | Contractor Rank | Address | Contractor |
---|---|---|---|---|---|
Zoning/use permit Date: July 27, 2012 Client: Maple Hill Group Llc | Permit status: Completed | Permit id: 406244 | |||||
Electrical permit Date: November 12, 2013 Client: Maple Hill Group Llc | Permit status: Completed | Permit id: 505358 | |||||
Plumbing permit Date: September 27, 2013 Client: Maple Hill Group Llc | Permit status: Completed | Permit id: 497114 | |||||
Suppression permit Date: October 25, 2013 Client: Maple Hill Group Llc | Permit status: Completed | Permit id: 486229 | |||||
New construction permit Date: July 10, 2013 Client: Maple Hill Group Llc | Permit status: Completed | Permit id: 424687 | |||||
Mechanical permit Date: October 2, 2013 Client: Maple Hill Group Llc | Permit status: Completed | Permit id: 497886 | |||||
On 11/6/12 department of licenses and inspections issued notice of refusal for application #424724. Date: December 21, 2012 Client: Maple Hill Group Llc | Applicant: Harman Deutsch | Permit type: Appeal | Permit status: Approved | Completion date: February 11, 2013 | Permit id: 19560 | |||||
On 11/6/12 department of licenses and inspections issued notice of refusal for application #424699. Date: December 21, 2012 Client: Maple Hill Group Llc | Applicant: Harman Deutsch | Permit type: Appeal | Permit status: Approved | Completion date: February 11, 2013 | Permit id: 19559 | |||||
On 11/6/12 department of licenses and inspections issued notice of refusal for application #424687. Date: December 21, 2012 Client: Maple Hill Group Llc | Applicant: Harman Deutsch | Permit type: Appeal | Permit status: Approved | Completion date: February 7, 2013 | Permit id: 19558 | |||||
Zoning use permit Date: July 27, 2012 Client: Maple Hill Group Llc | Permit status: Completed | Permit id: 406244 | |||||
On 11 6 12 department of licenses and inspections issued notice of refusal for application #424699. Date: December 21, 2012 Client: Maple Hill Group Llc | Applicant: Harman Deutsch | Permit type: Appeal | Permit status: Approved | Completion date: February 11, 2013 | Permit id: 19559 | |||||
On 11 6 12 department of licenses and inspections issued notice of refusal for application #424724. Date: December 21, 2012 Client: Maple Hill Group Llc | Applicant: Harman Deutsch | Permit type: Appeal | Permit status: Approved | Completion date: February 11, 2013 | Permit id: 19560 | |||||
On 11 6 12 department of licenses and inspections issued notice of refusal for application #424687. Date: December 21, 2012 Client: Maple Hill Group Llc | Applicant: Harman Deutsch | Permit type: Appeal | Permit status: Approved | Completion date: February 7, 2013 | Permit id: 19558 | |||||
Erection of three (3) story structure with cellar, one (1) interior parking space, pilot house, roof deck as per plan for use as a single family dwelling. All work shall be done in accordance with approved plans & bbs variance building is to be fully sprinklered separate permit required for mechanical, electrical, plumbing, and fire suppression work. Date: July 10, 2013 Permit type: New construction permit | Permit status: Completed | Completion date: January 31, 2014 | Permit id: 424687 | |||||
SCORE 82 For the installation of a fire suppression system throughout a single-family dwelling in accodrance with nfpa 13d standards. System to include a 1" copper fire service main line & 1" cpvc risers, cross mains and branch lines. System is also to include a backflow prevention assembly. Date: October 25, 2013 Contractor: United States Sprinklers Permit type: Suppression permit | Permit status: Completed | Completion date: January 31, 2014 | Permit id: 486229 | |||||
SCORE 100 New 5" lateral,5" curb trap, 4" main drain,install 3 toilets,3 vanities, 3 bathtubs,1 washer box, 1 kit snk(sfd) pa1 call#20132671549 Date: September 27, 2013 Contractor: Tommys Plumbing Permit type: Plumbing permit | Permit status: Completed | Completion date: January 31, 2014 | Permit id: 497114 | |||||
SCORE 100 Install 2 hvac units with ductwork(sfd) Date: October 2, 2013 Contractor: Talgar Inc Permit type: Mechanical permit | Permit status: Completed | Completion date: January 31, 2014 | Permit id: 497886 | |||||
SCORE 96 Install new 200amp service, outlets,45 light fixtures,25 switches,electric range,hot water,dryer,3 ton hvac unit smoke & carbon detectors as per 2008 nec (sfd) Date: November 12, 2013 Contractor: Sfb Wiring Systems Llc Permit type: Electrical permit | Permit status: Completed | Completion date: April 8, 2014 | Permit id: 505358 | |||||
For the erection of a sfd front yard setback and front steps to 1st floor and interior parking stall with projected bay at 2nd floor Date: July 27, 2012 Permit type: Zoning/use permit | Permit status: Completed | Completion date: September 25, 2012 | Permit id: 406244 |