SCORE 89 Sewer for sfr Date: April 16, 2003 Contractor: Rcr Companies Applicant: Rcr Companies | Permit status: Finaled | Completion date: August 26, 2003 | Expiration date: October 13, 2003 | Permit id: 304160018 | |||||
Relocate existing a/c units Date: January 9, 2004 Engineer: Dawn Pasol | Applicant: Same As Owner | Permit status: Finaled | Completion date: January 14, 2004 | Expiration date: July 7, 2004 | Permit id: 401090001 | |||||
Electrical for a/c relocation Date: January 9, 2004 Engineer: Dawn Pasol | Applicant: Same As Owner | Permit status: Finaled | Completion date: January 14, 2004 | Expiration date: July 7, 2004 | Permit id: 401090001 | |||||
SCORE 100 Electrical outlets at bbq Date: October 14, 2003 Contractor: Scv Pools And Spa Inc Engineer: Dawn Pasol | Applicant: Scv Pools | Permit status: Finaled | Completion date: January 14, 2004 | Expiration date: April 11, 2004 | Permit id: 310140058 | |||||
SCORE 100 New pool and spa 6 sq ft standard plan 26077 Engineer: Dawn Pasol | Applicant: Scv Pools | Permit status: Finaled | Completion date: January 14, 2004 | Expiration date: April 11, 2004 | Permit id: 310140012 | |||||
New sfd/garage plan 2 c 2488/631 sq ft Date: March 20, 2003 Value: $207,000 Engineer: Bbg Architects | Applicant: Same As Owner | Permit status: Finaled | Completion date: August 26, 2003 | Expiration date: September 16, 2003 | Permit id: 302100004 | |||||
New roof mount solar pv 5. 75 kw, 23 panels, 411 sq ft Date: August 6, 2013 Value: $23,000 Applicant: Same As Owner | Permit status: Finaled | Completion date: November 18, 2013 | Expiration date: August 6, 2014 | Permit id: 1308060042 | |||||
Attached shade bar patio cover 456 sq ft Date: March 11, 2009 Value: $9,000 Applicant: Same As Owner | Permit status: Finaled | Completion date: March 16, 2009 | Expiration date: September 7, 2009 | Permit id: 903110003 | |||||
Add option x 2nd floor excercise room 1 sq ft Date: August 1, 2003 Value: $13,000 Engineer: Bbg Architects | Applicant: Same As Owner | Permit status: Finaled | Completion date: August 26, 2003 | Expiration date: July 26, 2004 | Permit id: 308010009 | |||||
Electrical for roof mount solar pv 23 panels, 5. 75 kw Date: August 6, 2013 Applicant: Same As Owner | Permit status: Finaled | Completion date: November 18, 2013 | Expiration date: August 6, 2014 | Permit id: 1308060030 | |||||
Electrical for main panel upgrade to 2 amp new 2 amp subpanel, and 125 amp subpanel Date: October 28, 2013 Applicant: Same As Owner | Permit status: Finaled | Completion date: November 18, 2013 | Expiration date: October 28, 2014 | Permit id: 1310280004 | |||||
New sfd garage plan 2 c 2488 631 sq ft Date: March 20, 2003 Value: $207,000 Engineer: Bbg Architects | Applicant: Same As Owner | Permit status: Finaled | Completion date: August 26, 2003 | Expiration date: September 16, 2003 | Permit id: 302100004 | |||||
SCORE 100 New pool and spa 6 sq ft standard plan 26077 Engineer: Dawn Pasol | Applicant: Scv Pools | Permit status: Finaled | Completion date: January 14, 2004 | Expiration date: April 11, 2004 | Permit id: 310140012 | |||||
SCORE 100 Electrical outlets at bbq Date: October 14, 2003 Contractor: Scv Pools And Spa, Inc Engineer: Dawn Pasol | Applicant: Scv Pools | Permit status: Finaled | Completion date: January 14, 2004 | Expiration date: April 11, 2004 | Permit id: 310140058 | |||||
Electrical for a c relocation Date: January 9, 2004 Engineer: Dawn Pasol | Applicant: Same As Owner | Permit status: Finaled | Completion date: January 14, 2004 | Expiration date: July 7, 2004 | Permit id: 401090001 | |||||
Relocate existing a c units Date: January 9, 2004 Engineer: Dawn Pasol | Applicant: Same As Owner | Permit status: Finaled | Completion date: January 14, 2004 | Expiration date: July 7, 2004 | Permit id: 401090001 |