Content | Date | Cost | Contractor Rank | Address | Contractor |
---|---|---|---|---|---|
SCORE 86 Baylands workshed: construction of a new 625 sf workshed. Space is not conditioned electricity is provided from (e) subpanel Date: August 7, 2012 Contractor: Pete Moffat Construction Permit status: Permit issued | Permit id: 12000-01950 | |||||
SCORE 95 Install commercial pv system (21 panels) Date: April 9, 2012 Contractor: Clean Solar Inc Permit status: Permit issued | Permit id: 12000-00797 | |||||
SCORE 86 12000-01950: shift location of workshed due to field conditions Date: September 11, 2012 Contractor: Pete Moffat Construction Permit status: Permit issued | Permit id: 12rev-00504 | |||||
SCORE 99 07-03210: add barrier railings to second floor to reducethe exit egress travel distance Date: January 10, 2012 Contractor: Cody Brock Inc Permit status: Permit issued | Permit id: 12rev-00016 |