Content | Date | Cost | Contractor Rank | Address | Contractor |
---|---|---|---|---|---|
Zoning/use permit Date: January 21, 2015 Client: Haviv David | Permit status: Completed | Permit id: 584807 | |||||
Suppression permit Date: November 13, 2015 Client: Haviv David | Permit status: Completed | Permit id: 628890 | |||||
Plumbing permit Date: November 18, 2015 Client: Haviv David | Permit status: Completed | Permit id: 652952 | |||||
Electrical permit Date: October 28, 2015 Client: Haviv David | Permit status: Completed | Permit id: 641662 | |||||
Mechanical permit Date: September 8, 2015 Client: Haviv David | Permit status: Completed | Permit id: 637237 | |||||
Zoning permit Date: December 18, 2014 Client: Haviv David | Permit status: Completed | Permit id: 565141 | |||||
New construction permit Date: April 21, 2015 Client: Haviv David | Permit status: Completed | Permit id: 586093 | |||||
Plumbing permit Date: September 27, 2016 Client: Haviv David | Permit status: Active | Permit id: 724939 | |||||
Permit for the lot adjustment to create two(2) lots ( parcel c and parcel d) from one(1) opa account (2325 frankford ave) and from one(1) deeded lot (2326 frankford ave) as follows; parcelc: (frankford ave frontage of the building)(the lot will be cmc-2 commercial district) for the erection of attached structure ( nte 38 high); pilot house access to roof deck only for a vacant commercial use and two(2) family household living from second floor through to third floors (one(1) dwelling unit each on second and third floor). Parceld: (collins street frontage of building)( the lot d is more than 20% rsa-5 residential district) for the erection of an attached structure with cellar(nte 38 high); pilot house access to roof deck; bay windows at 2nd and 3rd floors for a single family household living from first floor through to third floor. Size and location as shown in the application Date: November 3, 2014 Client: Haviv David | Applicant: Shawn D. Ward, Esquire | Permit type: Appeal | Permit status: Granted | Completion date: December 15, 2014 | Permit id: 23993 | |||||
New construction permit Date: April 21, 2015 Client: Haviv David | Permit status: Completed | Permit id: 586093 | |||||
Suppression permit Date: November 13, 2015 Client: Haviv David | Permit status: Completed | Permit id: 628890 | |||||
Electrical permit Date: October 28, 2015 Client: Haviv David | Permit status: Completed | Permit id: 641662 | |||||
Plumbing permit Date: September 27, 2016 Client: Haviv David | Permit status: Active | Permit id: 724939 | |||||
Zoning use permit Date: January 21, 2015 Client: Haviv David | Permit status: Completed | Permit id: 584807 | |||||
Zoning permit Date: December 18, 2014 Client: Haviv David | Permit status: Completed | Permit id: 565141 | |||||
Plumbing permit Date: August 25, 2015 Client: Haviv David | Permit status: Completed | Permit id: 632723 | |||||
Mechanical permit Date: September 8, 2015 Client: Haviv David | Permit status: Completed | Permit id: 637237 | |||||
Permit for the lot adjustment to create two(2) lots ( parcel c and parcel d) from one(1) opa account (2325 frankford ave) and from one(1) deeded lot (2326 frankford ave) as follows; parcelc: (frankford ave frontage of the building)(the lot will be cmc-2 commercial district) for the erection of attached structure ( nte 38 high); pilot house access to roof deck only for a vacant commercial use and two(2) family household living from second floor through to third floors (one(1) dwelling unit each on second and third floor). Parceld: (collins street frontage of building)( the lot d is more than 20% rsa-5 residential district) for the erection of an attached structure with cellar(nte 38 high); pilot house access to roof deck; bay windows at 2nd and 3rd floors for a single family household living from first floor through to third floor. Size and location as shown in the application Date: November 3, 2014 Client: Haviv David | Applicant: Shawn D. Ward, Esquire | Permit type: Appeal | Permit status: Granted | Completion date: December 15, 2014 | Permit id: 23993 | |||||
SCORE 96 1" domestic water servcie,main drain and lateral pa20153220301(mixed use)self certifications are no longer permitted","all excavations and plumbing trenches in excess of 5 ft in depth must have approved shoring in place at the time of inspection" Date: November 18, 2015 Contractor: Frankie D And Benny G Plumbing And Client: Haviv David | Permit type: Plumbing permit | Permit status: Completed | Completion date: June 17, 2016 | Permit id: 652952 | |||||
SCORE 96 Install 1" backflow preventor. Rpz watts lf909. The installation will comply with the philadephia plubming code 2004 Date: September 27, 2016 Contractor: Frankie D And Benny G Plumbing And Client: Haviv David | Permit type: Plumbing permit | Permit status: Completed | Completion date: March 7, 2017 | Permit id: 724939 | |||||
New construction fit-out of first floor shell commercial space for a nail salon (personal services) as per approved plans. Existing building fully sprinklered. Separate permits required for any mep or fire suppression work Date: August 7, 2017 Client: Haviv David | Permit type: New construction permit | Permit status: Active | Completion date: September 1, 2017 | Permit id: 791683 | |||||
SCORE 86 Wiring throughout of 2 apts and the future store per 2008 nec (mixed use)install fire alarm and exit sign per npfa 72 400amp. Service Date: October 28, 2015 Contractor: Sigma Electric Group Inc Client: Haviv David | Permit type: Electrical permit | Permit status: Completed | Completion date: March 30, 2016 | Permit id: 641662 | |||||
Installation of new ventilation system for nail salon fit-out on the first floor of a new building as per approved plans. Date: August 7, 2017 Client: Haviv David | Permit type: Mechanical permit | Permit status: Active | Completion date: September 1, 2017 | Permit id: 794756 | |||||
SCORE 100 For the installation of a fire suppression system in accordance with nfpa 2007, standard 13 and 13r, with new 2-inch diameter service line connection and new backflow prevention assembly. Date: November 13, 2015 Contractor: Brothers Mechanical Client: Haviv David | Permit type: Suppression permit | Permit status: Completed | Completion date: April 12, 2016 | Permit id: 628890 | |||||
Construction of a new three story building with a cellar and roof top deck for use of a mixed use building. First floor and cellar to be a commercial space with no specific use defined as of yet. Roof top deck accessed by a pilot house used for stair accessory only. Date: April 21, 2015 Client: Haviv David | Permit type: New construction permit | Permit status: Completed | Completion date: June 17, 2016 | Permit id: 586093 | |||||
Subdivision with a proposed three story (3) unit mixed use building with a cellar and roof top deck fronting frankford ave, and a proposed three story sfd a cellar and roof top deck frontig collins st. Building on frankford ave. Commercial space on the 1st floor and cellar- no designated use and no proposed sign. One residential unit on each of the 2nd and 3rd floors. Date: December 18, 2014 Client: Haviv David | Permit type: Zoning permit | Permit status: Completed | Completion date: December 18, 2014 | Permit id: 565141 | |||||
For the erection of attached structure ( nte 38 high); pilot house access to roof deck only for a vacant commercial use and two(2) family household living from second floor through to third floors ( one(1) dwelling unit each on second and third floor). Date: January 21, 2015 Client: Haviv David | Permit type: Zoning/use permit | Permit status: Completed | Completion date: January 21, 2015 | Permit id: 584807 | |||||
SCORE 96 Interior plumbing construction to a point 5-0" outside only for a new three-story mixed-use property (vacant commercial & two-family) - note: backflow prevention containment device, fuel gas, exterior and sewer water connections to the city mains require separate permit(s) - the installation will comply with the phila plumbing code 2004 Date: August 25, 2015 Contractor: Frankie D And Benny G Plumbing And Client: Haviv David | Permit type: Plumbing permit | Permit status: Completed | Completion date: June 17, 2016 | Permit id: 632723 | |||||
SCORE 89 Ez permit ductwork & (3 heat pumps and associated air handlers) warm-air appliances- for the installation of new ductwork, registers grilles diffusers, and warm-air appliances as per attached standard. Deviations from this standard will result in permit revocation and require submission of construction plans. Date: September 8, 2015 Contractor: Silvis Construction Llc Client: Haviv David | Permit type: Mechanical permit | Permit status: Completed | Completion date: April 6, 2016 | Permit id: 637237 | |||||
For a personal service at first floor in the same building with all other uses as previously approved. No sign on this application. Date: June 13, 2017 Client: Haviv David | Permit type: Use permit | Permit status: Completed | Completion date: June 13, 2017 | Permit id: 791686 |