Content | Date | Cost | Contractor Rank | Address | Contractor |
---|---|---|---|---|---|
SCORE 98 Construct new 5756 sq ft sfr. 5 bedrooms,4. 5 bath,living room,familyroom,dining room,library,w/ att 6 sf garage. Applicant: Sanyao International | Permit status: Finaled | Completion date: January 28, 2002 | Permit id: 0005240010 | |||||
SCORE 98 3 ft. Retaining wall,between 3. 5&6. 5 feet high Applicant: Mur-Sol Construction | Permit status: Finaled | Completion date: January 28, 2002 | Permit id: 0009080010 | |||||
SCORE 98 Fire sprinkler permit Applicant: Sanyao International | Permit status: Finaled | Completion date: January 11, 2002 | Permit id: 0201110018 | |||||
SCORE 94 Retaining walls (various heights) 3 ft long Applicant: Dibaei Ali | Permit status: Finaled | Completion date: September 2, 2005 | Permit id: 0407220049 | |||||
SCORE 98 New retaining wall 6 high x 127 long Applicant: Contreras Humberto | Permit status: Finaled | Completion date: August 8, 2012 | Permit id: 1112200027 | |||||
SCORE 100 Remove exist tile roof on house and garage,resheat & install new underlayment and re-install same tile Applicant: Ta Mandy | Permit status: Finaled | Completion date: September 10, 2012 | Permit id: 1208140016 | |||||
SCORE 66 Convert 215 s. F. Of existing garage space to game room. Applicant: Escobar Miguel | Permit status: Finaled | Completion date: February 24, 2014 | Permit id: 1307020038 | |||||
SCORE 67 New pool 11 s. F. And spa 48 s. F. Applicant: Bouganim Pamela | Permit status: Permisud | Permit id: 0504180008 | |||||
SCORE 80 Pool and spa std plan #26077 w/additional engineering Applicant: Sewell,Jr. Gary | Permit status: Finaled | Completion date: March 21, 2008 | Permit id: 0705110005 | |||||
SCORE 95 New pool and spa std plan 26077 Applicant: Nieto Sue | Permit status: Finaled | Completion date: October 31, 2014 | Permit id: 0712100002 | |||||
To final expired permit #cp0712100002,pool and spa standard plan 26077. Date: July 2, 2013 Value: $3,250 Applicant: Same As Owner | Permit status: Finaled | Completion date: October 31, 2014 | Permit id: 1307020001 | |||||
SCORE 98 Construct new 5756 sq ft sfr. 5 bedrooms,4. 5 bath,living room,familyroom,dining room,library,w/ att 6 sf garage. Date: October 20, 2000 Contractor: Mursol Construction Applicant: Sanyao International | Permit status: Finaled | Completion date: November 29, 2001 | Permit id: 0010200004 | |||||
SCORE 98 Temporary power pole Date: November 15, 2000 Contractor: Mursol Construction Applicant: Sanyao International | Permit status: Permisud | Permit id: 0011150023 | |||||
SCORE 93 Construct new 5756 sq ft sfr. 5 bedrooms,4. 5 bath,living room,familyroom,dining room,library,w/ att 6 sf garage. Date: April 30, 2001 Contractor: Terry Foley Electric Inc Applicant: Terry Foley Electric,Inc. | Permit status: Permisud | Permit id: 0104300006 | |||||
SCORE 59 Electrical for sump pump. Date: August 29, 2005 Contractor: Rezazadah Dibaei Applicant: Rezazadah Dibaei Ali | Permit status: Finaled | Completion date: December 13, 2013 | Permit id: 0508290050 | |||||
SCORE 94 Electrical for 8 pole mounted light fixtures for tennis court. Date: May 31, 2006 Contractor: Elite Builders And Remodeling Applicant: Dibaei Ali | Permit status: Finaled | Completion date: December 13, 2013 | Permit id: 0605310014 | |||||
To final expired electrical permits #el0605310014 for 8 pole mounted light,and el05082900 for sump pump. Date: July 2, 2013 Applicant: Same As Owner | Permit status: Finaled | Completion date: December 13, 2013 | Permit id: 1307020022 | |||||
SCORE 77 Electrical for game room. Date: September 24, 2013 Contractor: R J L Electrical Applicant: Lahr Robert | Permit status: Finaled | Completion date: February 24, 2014 | Permit id: 1309240050 | |||||
SCORE 80 Grading for new residence Date: January 11, 2002 Contractor: Mursol Construction Inc Applicant: Jong Honk | Permit status: Permisud | Permit id: 0002220002 | |||||
SCORE 59 Grading for future pool,tennis court and rec room Date: January 27, 2005 Contractor: Rezazadah Dibaei Applicant: Rezazadah Dibaei Ali | Permit status: Finaled | Completion date: September 2, 2005 | Permit id: 0403230003 | |||||
SCORE 98 Grading for new guest house. Date: August 31, 2011 Contractor: Triangle Services Applicant: Lang Daniel | Permit status: Finaled | Completion date: March 20, 2013 | Permit id: 1007150002 | |||||
SCORE 79 Hvac for new house Date: May 14, 2001 Contractor: Huntington A C Applicant: Huntington A/c | Permit status: Finaled | Completion date: January 4, 2002 | Permit id: 0105140002 | |||||
SCORE 71 Relocate 15 gal. Pretreatment septic tank and j15 treatment system. Date: October 8, 2013 Contractor: Advantage Septic Applicant: Dinwiddie Steve G | Permit status: Finaled | Completion date: December 13, 2013 | Permit id: 1310080006 |