New construction, foundation to grade Date: September 16, 2014 Client: The Kop Llc The Kop Llc | Applicant: The Kop Llc The Kop Llc | Permit type: Foundation only | Permit status: Permit issued | Permit id: Fd1400102 | |||||
3 spt borings drilled using the hollow stem auger method one at feet , the other two at feet each, totaling 1 feet drilled for geotechnical information for a residential 4 story building. Maximum diameter of the boreholes will be 8 inches. The boreholes will be grouted in accordance with ddoe standards upon completion. Date: April 22, 2014 Client: The Kop, Llc | Applicant: Mehari Sequar | Permit type: Miscellaneous | Permit status: Permit issued | Permit id: Sb1400257 | |||||
One sewer or water line cut. Date: July 22, 2014 Applicant: Ralph Beall | Permit type: Plumbing | Permit status: Permit issued | Permit id: Pc86542833 | |||||
Plumbing and gas Date: November 19, 2014 Client: Sajjan Agribiz Corp Usa Inc | Applicant: Franklin T Gaines | Permit status: Completed | Permit id: P1501367 | |||||
Too raze single story commercial Date: August 6, 2014 Client: Sajjan Agribiz Corp Usa Inc | Applicant: Mehari Sequar | Permit type: Raze | Permit status: Permit issued | Permit id: R1400080 | |||||
New construction, foundation to grade Date: September 16, 2014 Client: The Kop Llc The Kop Llc | Permit type: Foundation only | Permit status: Permit issued | Permit id: Fd1400102 | |||||
SCORE 93 One sewer or water line cut. Date: July 22, 2014 Contractor: Ralph Beall Permit type: Plumbing | Permit status: Permit issued | Permit id: Pc14125264 | |||||
SCORE 96 Plumbing and gas Date: November 19, 2014 Contractor: Franklin T Gaines Client: Sajjan Agribiz Corp Usa Inc | Permit status: Completed | Permit id: P1501367 | |||||
Amendment to new building permit b14107 to include elevator. Elevator was in the original plans, but not reviewed. Date: April 17, 2015 Client: The Kop Llc The Kop Llc | Permit type: Alteration and repair | Permit status: Completed | Permit id: B1506506 | |||||
Amendment to garage entrance on foundation to grade permit fd1400102. Garage entrance moved to adams street from 4th street. Date: February 6, 2015 Client: The Kop Llc The Kop Llc | Permit type: Foundation only | Permit status: Permit issued | Permit id: Fd1500044 | |||||
New construction - 4 story + cellar apartment building with 17 units (two iz units required - units b01 and 102) and cellar level parking garage providing nine parking spaces. Foundation to grade permit fd1400102. Date: February 12, 2015 Client: The Kop Llc The Kop Llc | Permit type: New building | Permit status: Completed | Permit id: B1410700 | |||||
SCORE 96 Electrical Date: March 20, 2015 Contractor: Gregory E Ligon Client: The Kop Llc | Permit status: Completed | Permit id: E1504261 | |||||
SCORE 96 Electrical Date: May 13, 2015 Contractor: John A Traylor Client: The Kop Llc | Permit status: Completed | Permit id: E1505788 | |||||
SCORE 96 Plumbing and gas Date: March 23, 2015 Contractor: Franklin T Gaines Client: The Kop Llc | Permit status: Completed | Permit id: P1504431 | |||||
SCORE 82 Plumbing and gas Date: March 31, 2015 Contractor: Vernon W. Williams Jr Client: The Kop Llc | Permit status: Completed | Permit id: P1504634 | |||||
SCORE 96 Plumbing and gas Date: November 19, 2014 Contractor: Franklin T Gaines Client: Sajjan Agribiz Corp Usa Inc | Permit status: Completed | Permit id: P1501367 | |||||
New construction, foundation to grade Date: September 16, 2014 Client: The Kop Llc The Kop Llc | Permit type: Foundation only | Permit status: Permit issued | Permit id: Fd1400102 | |||||
SCORE 96 Plumbing and gas Date: November 19, 2014 Contractor: Franklin T Gaines Client: Sajjan Agribiz Corp Usa Inc | Permit status: Completed | Permit id: P1501367 | |||||
SCORE 82 Plumbing and gas Date: March 31, 2015 Contractor: Vernon W. Williams, Jr Client: The Kop Llc | Permit status: Completed | Permit id: P1504634 | |||||
SCORE 100 3 spt borings drilled using the hollow stem auger method one at feet , the other two at feet each, totaling 1 feet drilled for geotechnical information for a residential 4 story building. Maximum diameter of the boreholes will be 8 inches. The boreholes will be grouted in accordance with ddoe standards upon completion. Date: April 22, 2014 Contractor: Mehari Sequar Client: The Kop, Llc | Permit type: Miscellaneous | Permit status: Permit issued | Permit id: Sb1400257 | |||||
SCORE 93 One sewer or water line cut. Date: July 22, 2014 Contractor: Ralph Beall Permit type: Plumbing | Permit status: Permit issued | Permit id: Pc86542833 | |||||
SCORE 82 New construction, foundation to grade Date: September 16, 2014 Contractor: The Kop Llc The Kop Llc Client: The Kop Llc The Kop Llc | Permit type: Foundation only | Permit status: Permit issued | Permit id: Fd1400102 | |||||
SCORE 96 Plumbing and gas Date: November 19, 2014 Contractor: Franklin T Gaines Client: Sajjan Agribiz Corp Usa Inc | Permit status: Completed | Permit id: P1501367 | |||||
SCORE 82 New construction - 4 story + cellar apartment building with 17 units (two iz units required - units b01 and 102) and cellar level parking garage providing nine parking spaces. Foundation to grade permit fd1400102. Date: February 12, 2015 Contractor: The Kop Llc The Kop Llc Client: The Kop Llc The Kop Llc | Permit type: New building | Permit status: Completed | Permit id: B1410700 | |||||
SCORE 82 Amendment to garage entrance on foundation to grade permit fd1400102. Garage entrance moved to adams street from 4th street. Date: February 6, 2015 Contractor: The Kop Llc The Kop Llc Client: The Kop Llc The Kop Llc | Permit type: Foundation only | Permit status: Permit issued | Permit id: Fd1500044 | |||||
SCORE 82 Amendment to new building permit b14107 to include elevator. Elevator was in the original plans, but not reviewed. Date: April 17, 2015 Contractor: The Kop Llc The Kop Llc Client: The Kop Llc The Kop Llc | Permit type: Alteration and repair | Permit status: Completed | Permit id: B1506506 | |||||
SCORE 96 Electrical Date: May 13, 2015 Contractor: John A Traylor Client: The Kop Llc | Permit status: Completed | Permit id: E1505788 | |||||
SCORE 96 Electrical Date: March 20, 2015 Contractor: Gregory E Ligon Client: The Kop Llc | Permit status: Completed | Permit id: E1504261 | |||||
SCORE 96 Plumbing and gas Date: March 23, 2015 Contractor: Franklin T Gaines Client: The Kop Llc | Permit status: Completed | Permit id: P1504431 | |||||
SCORE 82 Plumbing and gas Date: March 31, 2015 Contractor: Vernon W. Williams, Jr Client: The Kop Llc | Permit status: Completed | Permit id: P1504634 | |||||
SCORE 95 Type of elevator :one (1) electrical /steel/center/ passenger Date: May 1, 2015 Contractor: Kone Inc Client: Ontario Residential Llc | Permit type: Elevator - new | Permit status: Permit issued | Permit id: En1501910 | |||||
SCORE 56 This supplemental permit was issued online. Use the online permit view application on dcra intranet to view the details and print a copy of the permit. Alternatively, you can copy and paste the following url into an internet browser. Https:/ospi. Dcra. Dc. Gov/ospi/printpermit. Aspx? Param=zi8iggjeilehqeiy2lrtf%2bfmayfam2hp Date: November 13, 2015 Contractor: Rashad Watt; The Kop; Jerry Bethea Client: The Kop | Permit type: Mechanical | Permit status: Completed | Permit id: Ar72274061 |