Content | Date | Cost | Contractor Rank | Address | Contractor |
---|---|---|---|---|---|
SCORE 79 New 2 story 5 unit apartment building w/underground parking Applicant: Segoro & Associates | Permit status: Finaled | Completion date: August 15, 2003 | Permit id: 0011060027 | |||||
SCORE 86 Retaining wall for apt. Bldg. Long x 5 high and long x high fence wall Applicant: Ashoghian Markar | Permit status: Finaled | Completion date: August 15, 2003 | Permit id: 0106290024 | |||||
SCORE 72 Demo existing sfr & det. Garage. Applicant: Frame Jeff | Permit status: Finaled | Completion date: August 15, 2003 | Permit id: 0112070046 | |||||
SCORE 98 Install fire sprinklers for 5 unit apt. Bldg. Applicant: C V Fire Protection | Permit status: Finaled | Completion date: August 15, 2003 | Permit id: 0303200040 | |||||
SCORE 72 Temporary power pole Date: March 29, 2002 Contractor: J. Frame Properties Applicant: Frame Jeff | Permit status: Finaled | Completion date: August 15, 2003 | Permit id: 0203290003 | |||||
SCORE 86 Grading for 5 unit apartment building w/underground parking Date: July 30, 2001 Contractor: Marks Construction Co Applicant: Segoro & Associates | Permit status: Finaled | Completion date: August 15, 2003 | Permit id: 0012110001 | |||||
SCORE 84 Mechanical for 5 unit apartment building Date: March 26, 2003 Contractor: Terry L Huckaby Heating And Air Applicant: Terry L Huckaby Heating And A,C | Permit status: Finaled | Completion date: August 15, 2003 | Permit id: 0303260015 | |||||
SCORE 79 Plumbing for new 5-unit apartment building Date: July 19, 2002 Contractor: Frame Applicant: Segoro & Associates | Permit status: Finaled | Completion date: August 15, 2003 | Permit id: 0207190013 | |||||
SCORE 79 Connect new 5 unit apt. Building to public sewer Date: May 15, 2003 Contractor: Frame Applicant: Frame Jeff | Permit status: Finaled | Completion date: August 15, 2003 | Permit id: 0305150029 |