Content | Date | Cost | Contractor Rank | Address | Contractor |
---|---|---|---|---|---|
Plumbing permit Date: August 24, 2007 Client: Bunster Ignacio F Palms Sylvia T | Permit status: Completed | Permit id: 98342 | |||||
Electrical permit Date: September 7, 2007 Client: Bunster Ignacio F Palms Sylvia T | Permit status: Completed | Permit id: 100782 | |||||
Alteration permit Date: August 1, 2007 Client: Bunster Ignacio F Palms Sylvia T | Permit status: Completed | Permit id: 93372 | |||||
Plumbing permit Date: August 24, 2007 Client: Bunster Ignacio F Palms Sylvia T | Permit status: Completed | Permit id: 98342 | |||||
Alteration permit Date: August 1, 2007 Client: Bunster Ignacio F Palms Sylvia T | Permit status: Completed | Permit id: 93372 | |||||
Electrical permit Date: September 7, 2007 Client: Bunster Ignacio F Palms Sylvia T | Permit status: Completed | Permit id: 100782 | |||||
SCORE 100 Install 7 fixtures, 15 switches, 9 receptacles, 3 gfci, and 1 phone jack Date: September 7, 2007 Contractor: A T B Electric Inc Client: Bunster Ignacio F Palms Sylvia T | Permit type: Electrical permit | Permit status: Completed | Completion date: September 17, 2008 | Permit id: 100782 | |||||
SCORE 100 Replace 3 piece bath & 4 piece bath Date: August 24, 2007 Contractor: William Gruber Jr Client: Bunster Ignacio F Palms Sylvia T | Permit type: Plumbing permit | Permit status: Completed | Completion date: March 19, 2008 | Permit id: 98342 | |||||
Rehab (2) bathrooms: new pocket door, remove openable window on third floor reframe and install frosted glass, minor interior demolition,minor framing, new flooring, tile,etc. Date: August 1, 2007 Client: Bunster Ignacio F Palms Sylvia T | Permit type: Alteration permit | Permit status: Completed | Completion date: March 25, 2008 | Permit id: 93372 |