Mechanical Date: December 18, 2012 Client: Moushira El-Saify | Applicant: Robert John Soappman | Permit status: Permit issued | Permit id: M1300550 | |||||
The scope of work includes waterproofing repairs at the 3rd floor, exterior concourse of the condominum building and of the terraces. Date: September 12, 2014 Client: Warehouses At Union Row | Applicant: Traffic Engineering Services | Permit type: Alteration and repai | Permit status: Permit issued | Permit id: B1411268 | |||||
Plumbing and gas Date: October 16, 2014 Client: Scott Soan | Applicant: Richard L Nashwinter | Permit status: Completed | Permit id: P1500418 | |||||
Remove and replace tile and fixtures in 3 existing bathrooms Date: October 10, 2014 Client: Daniel C Hardy | Applicant: Todd Mizrahi | Permit type: Alteration and repai | Permit status: Completed | Permit id: B1500345 | |||||
Electrical Date: October 14, 2014 Client: Daniel C Hardy | Applicant: Clarence E. Williams | Permit status: Completed | Permit id: E1500324 | |||||
Remove drywall and tile from 2 bathrooms Date: October 1, 2014 Client: Daniel Hardy | Applicant: Todd Mizrahi | Permit type: Demolition | Permit status: Permit issued | Permit id: D1500003 | |||||
Expedited Date: December 31, 2014 Applicant: Na Na Na | Permit status: Permit issued | Permit id: Ehop1590202 | |||||
Expedited Date: March 2, 2014 Applicant: Na Na Na | Permit status: Permit issued | Permit id: Ehop1490346 | |||||
SCORE 93 Mechanical Date: December 18, 2012 Contractor: Robert John Soappman Client: Moushira El-Saify | Permit status: Permit issued | Permit id: M1300550 | |||||
SCORE 93 Mechanical Date: December 18, 2012 Contractor: Robert John Soappman Client: Moushira El-Saify | Permit status: Permit issued | Permit id: M1300550 | |||||
SCORE 93 Mechanical Date: December 18, 2012 Contractor: Robert John Soappman Client: Moushira El-Saify | Permit status: Permit issued | Permit id: M1300550 | |||||
SCORE 93 Plumbing and gas Date: October 16, 2014 Contractor: Richard L Nashwinter Client: Scott Soan | Permit status: Completed | Permit id: P1500418 | |||||
SCORE 93 Plumbing and gas Date: October 16, 2014 Contractor: Richard L Nashwinter Client: Scott Soan | Permit status: Completed | Permit id: P1500418 | |||||
SCORE 93 Plumbing and gas Date: October 16, 2014 Contractor: Richard L Nashwinter Client: Scott Soan | Permit status: Completed | Permit id: P1500418 | |||||
SCORE 93 Plumbing and gas Date: October 16, 2014 Contractor: Richard L Nashwinter Client: Scott Soan | Permit status: Completed | Permit id: P1500418 | |||||
SCORE 93 Plumbing and gas Date: January 19, 2016 Contractor: Richard L Nashwinter Client: Daniel C Hardy | Permit status: Completed | Permit id: P1602967 | |||||
SCORE 93 Plumbing and gas Date: January 19, 2016 Contractor: Richard L Nashwinter Client: Daniel C Hardy | Permit status: Completed | Permit id: P1602967 | |||||
SCORE 96 Electrical Date: October 14, 2014 Contractor: Clarence E. Williams Client: Daniel C Hardy | Permit status: Completed | Permit id: E1500324 | |||||
SCORE 89 Remove and replace tile and fixtures in 3 existing bathrooms Date: October 10, 2014 Contractor: Todd Mizrahi Client: Daniel C Hardy | Permit type: Alteration and repair | Permit status: Completed | Permit id: B1500345 | |||||
SCORE 89 Remove drywall and tile from 2 bathrooms Date: October 1, 2014 Contractor: Todd Mizrahi Client: Daniel Hardy | Permit type: Demolition | Permit status: Permit issued | Permit id: D1500003 | |||||
SCORE 96 Electrical Date: October 14, 2014 Contractor: Clarence E. Williams Client: Daniel C Hardy | Permit status: Completed | Permit id: E1500324 | |||||
SCORE 70 Remove tub, tile, walls, and floor and replace. Remove and replace light fixture. Install new fixtures. Date: January 11, 2016 Contractor: Mizrahi Client: Daniel Hardy | Permit type: Alteration and repair | Permit status: Completed | Permit id: B1603548 | |||||
SCORE 93 Plumbing and gas Date: January 19, 2016 Contractor: Richard L Nashwinter Client: Daniel C Hardy | Permit status: Completed | Permit id: P1602967 | |||||
SCORE 96 Plumbing and gas Date: May 20, 2016 Contractor: Thomas N Oconnor Client: Denise L Dias | Permit status: Completed | Permit id: P1606406 | |||||
SCORE 96 Plumbing and gas Date: September 7, 2016 Contractor: David L. Hahn Client: Denise L Dias | Permit status: Permit issued | Permit id: P1609254 | |||||
SCORE 96 Plumbing and gas Date: September 7, 2016 Contractor: David L. Hahn Client: Denise L Dias | Permit status: Permit issued | Permit id: P1609254 | |||||
SCORE 96 Plumbing and gas Date: May 20, 2016 Contractor: Thomas N Oconnor Client: Denise L Dias | Permit status: Completed | Permit id: P1606406 | |||||
SCORE 83 The scope of work includes waterproofing repairs at the 3rd floor, exterior concourse of the condominum building and of the terraces. Date: September 12, 2014 Contractor: Traffic Engineering Services Client: Warehouses At Union Row | Permit type: Alteration and repair | Permit status: Permit issued | Permit id: B1411268 | |||||
SCORE 96 Plumbing and gas Date: September 7, 2016 Contractor: David L. Hahn Client: Denise L Dias | Permit status: Permit issued | Permit id: P1609254 | |||||
SCORE 96 Plumbing and gas Date: May 20, 2016 Contractor: Thomas N Oconnor Client: Denise L Dias | Permit status: Completed | Permit id: P1606406 | |||||
SCORE 56 This supplemental permit was issued online. Use the online permit view application on dcra intranet to view the details and print a copy of the permit. Alternatively, you can copy and paste the following url into an internet browser. Https:/ospi. Dcra. Dc. Gov/ospi/printpermit. Aspx? Param=zi8iggjeilemw2ac0avlktblcx8qafee Date: May 18, 2016 Contractor: Howard Workeman; Daniel Hardy; Howard Workeman Client: Daniel Hardy | Permit type: Electrical | Permit status: Completed | Permit id: E20413636 | |||||
SCORE 96 Expedited Date: March 2, 2014 Contractor: Na Na Na Permit status: Permit issued | Permit id: Ehop1490346 | |||||
SCORE 96 Expedited Date: March 2, 2014 Contractor: Na Na Na Permit status: Permit issued | Permit id: Ehop1490346 | |||||
SCORE 96 Expedited Date: March 2, 2014 Contractor: Na Na Na Permit status: Permit issued | Permit id: Ehop1490346 | |||||
SCORE 96 Expedited Date: March 2, 2014 Contractor: Na Na Na Permit status: Permit issued | Permit id: Ehop1490346 | |||||
SCORE 96 Expedited Date: December 31, 2014 Contractor: Na Na Na Permit status: Permit issued | Permit id: Ehop1590202 | |||||
SCORE 96 Expedited Date: December 31, 2014 Contractor: Na Na Na Permit status: Permit issued | Permit id: Ehop1590202 | |||||
SCORE 96 Expedited Date: December 31, 2014 Contractor: Na Na Na Permit status: Permit issued | Permit id: Ehop1590202 | |||||
SCORE 96 Expedited Date: December 31, 2014 Contractor: Na Na Na Permit status: Permit issued | Permit id: Ehop1590202 | |||||
SCORE 96 Electrical Date: October 14, 2014 Contractor: Clarence E. Williams Client: Daniel C Hardy | Permit status: Completed | Permit id: E1500324 | |||||
SCORE 96 Electrical Date: October 14, 2014 Contractor: Clarence E. Williams Client: Daniel C Hardy | Permit status: Completed | Permit id: E1500324 | |||||
SCORE 96 Expedited Date: March 20, 2015 Contractor: Na Na Na Permit status: Permit issued | Permit id: Ehop1590435 | |||||
SCORE 96 Expedited Date: March 20, 2015 Contractor: Na Na Na Permit status: Permit issued | Permit id: Ehop1590435 | |||||
SCORE 96 Plumbing and gas Date: April 23, 2015 Contractor: Jess L Gordon Client: Ariel Fiszbein | Permit status: Permit canceled | Permit id: P1505285 | |||||
SCORE 96 Plumbing and gas Date: April 23, 2015 Contractor: Jess L Gordon Client: Ariel Fiszbein | Permit status: Permit canceled | Permit id: P1505285 | |||||
SCORE 96 Expedited Date: April 1, 2016 Contractor: Na Na Na Permit status: Permit issued | Permit id: Ehop1690544 | |||||
SCORE 96 Expedited Date: April 1, 2016 Contractor: Na Na Na Permit status: Permit issued | Permit id: Ehop1690544 | |||||
SCORE 96 Expedited Date: April 1, 2016 Contractor: Na Na Na Permit status: Permit issued | Permit id: Ehop1690544 | |||||
SCORE 96 Mechanical Date: July 20, 2016 Contractor: Louis Corrado Copeland Client: Simone C Petrella | Permit status: Completed | Permit id: M1602817 | |||||
SCORE 96 Mechanical Date: July 20, 2016 Contractor: Louis Corrado Copeland Client: Simone C Petrella | Permit status: Completed | Permit id: M1602817 | |||||