Mechanical permit Date: August 9, 2007 Client: Olive Aliza M Olive Joseph P | Permit status: Completed | Permit id: 95090 | |||||
Electrical permit Date: July 16, 2007 Client: Olive Aliza M Olive Joseph P | Permit status: Expired | Permit id: 89651 | |||||
Plumbing permit Date: August 2, 2007 Client: Olive Aliza M Olive Joseph P | Permit status: Completed | Permit id: 93710 | |||||
Zoning permit Date: March 19, 2007 Client: Olive Aliza M Olive Joseph P | Permit status: Completed | Permit id: 49194 | |||||
Addition permit Date: March 19, 2007 Client: Olive Aliza M Olive Joseph P | Permit status: Completed | Permit id: 49195 | |||||
Alteration permit Date: July 16, 2007 Client: Olive Aliza M Olive Joseph P | Permit status: Completed | Permit id: 87528 | |||||
SCORE 94 Demolition of the existing roof system. Erect a new roof system with a elevation termination 22-4"above grade. This elevation is two feet greater than the original. All work shall comply with the approved site plans. Date: March 19, 2007 Contractor: Mcdermott Construction Co Inc Client: Live Aliza M Olive Joseph P | Permit type: Zoning permit | Permit status: Completed | Completion date: March 19, 2007 | Permit id: 49194 | |||||
SCORE 94 Install _14__x__6_ deck in rear per ez permit standard for decks dated february 2007. Date: July 16, 2007 Contractor: Mcdermott Construction Co Inc Client: Live Aliza M Olive Joseph P | Permit type: Zoning permit | Permit status: Completed | Completion date: July 16, 2007 | Permit id: 87526 | |||||
SCORE 94 Install 14___x_6__deck in rear. Applicant agrees to limit construction to comply with ez permit standard for decks,dated february 2007. Deviation from the standard will result in revocation of this permit and imposition of further penalties. Date: July 16, 2007 Contractor: Mcdermott Construction Co Inc Client: Live Aliza M Olive Joseph P | Permit type: Alteration permit | Permit status: Completed | Completion date: March 11, 2008 | Permit id: 87528 | |||||
SCORE 100 Rough & finish. Wire rehab house to include 6 lts, recepts, 6 sws, 6 hw smokes. 200a svs in accord with 3005 nec. (south dist) Date: July 16, 2007 Contractor: Hawke Electrical Client: Live Aliza M Olive Joseph P | Permit type: Electrical permit | Permit status: Expired | Completion date: July 16, 2007 | Permit id: 89651 | |||||
SCORE 100 Throughtout, install plumbing for two 3 piece bathroom m plumbing for kitchen and laundry, (2 lav, 2 wc, 2 tubs, 1 sink, 1 laundry) Date: August 2, 2007 Contractor: Gerard Regan Client: Live Aliza M Olive Joseph P | Permit type: Plumbing permit | Permit status: Completed | Completion date: November 7, 2007 | Permit id: 93710 | |||||
SCORE 99 Install one ruud gas heating unit (sfd) Date: August 9, 2007 Contractor: David Mercado Client: Live Aliza M Olive Joseph P | Permit type: Mechanical permit | Permit status: Completed | Completion date: February 12, 2008 | Permit id: 95090 |