SCORE 100 Electrical Date: February 28, 2013 Contractor: Ricardo Ramos Permit status: Permit finaled | Current use: Commercial | Permit id: 13041-90000-052 | |||||
SCORE 59 Electrical Date: March 18, 2013 Contractor: Sean Canon Permit status: Permit finaled | Current use: Commercial | Permit id: 13041-90000-069 | |||||
SCORE 100 Electrical Date: March 20, 2013 Contractor: David Aguet Permit status: Permit finaled | Current use: Commercial | Permit id: 13041-90000-072 | |||||
SCORE 59 Electrical Date: March 21, 2013 Contractor: Daric Warneke Permit status: Permit finaled | Current use: Special equipment | Permit id: 13041-90000-073 | |||||
SCORE 59 Electrical Date: April 4, 2013 Contractor: Juanita Burgos Permit status: Issued | Current use: Commercial | Permit id: 13041-90000-086 | |||||
SCORE 93 Electrical Date: May 16, 2013 Contractor: Lauren Ebalo Permit status: Permit expired | Current use: Commercial | Permit id: 13041-90000-128 | |||||
SCORE 96 Electrical Date: August 15, 2013 Contractor: Glenn Lawrence Permit status: Permit expired | Current use: Commercial | Permit id: 13041-90000-220 | |||||
SCORE 98 Electrical Date: September 16, 2013 Contractor: Javier Torres Permit status: Permit expired | Current use: Commercial | Permit id: 13041-90000-254 | |||||
SCORE 100 Electrical Date: January 7, 2014 Contractor: Arica Simpson Permit status: Permit finaled | Current use: Commercial | Permit id: 14041-90000-003 | |||||
SCORE 100 Electrical Date: April 21, 2014 Contractor: Ricardo Ramos Permit status: Issued | Current use: Commercial | Permit id: 14041-90000-103 | |||||
SCORE 71 Electrical Date: January 14, 2015 Contractor: Nathan Kahawai Permit status: Issued | Current use: Commercial | Permit id: 15041-90000-011 | |||||
SCORE 100 Electrical Date: January 16, 2015 Contractor: Arica Simpson Permit status: Permit finaled | Current use: Commercial | Permit id: 15041-90000-014 | |||||
SCORE 100 Electrical Date: June 21, 2015 Contractor: David Aguet Permit status: Permit finaled | Current use: Commercial | Permit id: 15041-90000-193 | |||||
SCORE 100 Electrical Date: July 1, 2015 Contractor: Ricardo Ramos Permit status: Permit finaled | Current use: Commercial | Permit id: 15041-90000-207 | |||||
SCORE 93 Electrical Date: July 7, 2015 Contractor: Lauren Ebalo Permit status: Issued | Current use: Commercial | Permit id: 15041-90000-214 | |||||
Electrical Date: May 27, 2011 Permit status: Permit finaled | Current use: Special equipment | Permit id: 11041-10000-109 | |||||
SCORE 100 Fire sprinkler Date: May 24, 2010 Contractor: Jeff Pettitt Permit status: Refund completed | Current use: Commercial | Permit id: 10043-90000-010 | |||||
SCORE 61 Elevator Date: December 17, 2010 Contractor: Jvaughn Permit status: Permit finaled | Current use: Commercial | Permit id: 10046-10000-013 | |||||
SCORE 56 Electrical Date: April 19, 2010 Contractor: Parke Jones Permit status: Permit finaled | Current use: Commercial | Permit id: 10041-90000-070 | |||||
SCORE 100 Fire sprinkler Date: September 30, 2011 Contractor: Jeff Pettitt Permit status: Permit finaled | Current use: Commercial | Permit id: 11043-90000-025 | |||||
SCORE 100 Electrical Date: August 24, 2010 Contractor: Ricardo Ramos Permit status: Permit finaled | Current use: Commercial | Permit id: 10041-10000-164 | |||||
SCORE 100 Ti for office on 11th floor; non bearing partitions, millwork and susp Permit type: Bldg-alter/repair | Permit status: Permit finaled | Current use: Commercial | Permit id: 10016-10000-128 | |||||
Elevator Date: May 15, 2012 Permit status: Permit finaled | Current use: Commercial | Permit id: 12046-90000-005 | |||||
SCORE 56 Replace generator paralleling switchgear. Epc is for power. Date: May 16, 2012 Contractor: Patrick Carolan Permit type: Electrical | Permit status: Permit finaled | Current use: Commercial | Permit id: 12041-10000-041 | |||||
SCORE 100 Electrical Date: June 29, 2011 Contractor: Arica Simpson Permit status: Issued | Current use: Commercial | Permit id: 11041-90000-135 | |||||
Fire sprinkler Date: August 6, 2010 Permit status: Permit finaled | Current use: Commercial | Permit id: 10043-10000-016 | |||||
SCORE 100 Electrical Date: April 27, 2011 Contractor: Ricardo Ramos Permit status: Permit finaled | Current use: Commercial | Permit id: 11041-90000-084 | |||||
SCORE 96 Hvac Date: January 13, 2012 Contractor: Aviva Murprhy Permit status: Permit finaled | Current use: Commercial | Permit id: 12044-90000-003 | |||||
SCORE 96 Electrical Date: April 11, 2011 Contractor: Glenn Lawrence Permit status: Permit finaled | Current use: Commercial | Permit id: 11041-90000-071 | |||||
Add plumbing fixtures on 40, 41, and 42 floors. Date: December 27, 2012 Permit type: Plumbing | Permit status: Issued | Current use: Commercial | Permit id: 12042-10000-192 | |||||
SCORE 96 Hvac Date: November 18, 2010 Contractor: Aviva Murprhy Permit status: Permit finaled | Current use: Commercial | Permit id: 10044-90000-114 | |||||
SCORE 56 Ti for office on 19th floor. Non-bearing partitions, millwork and rewo Permit type: Bldg-alter/repair | Permit status: Permit finaled | Current use: Commercial | Permit id: 11016-10000-102 | |||||
SCORE 100 Plumbing Date: March 22, 2010 Contractor: Sherri Taylor Permit status: Permit finaled | Current use: Commercial | Permit id: 10042-90000-045 | |||||
Interior minor tenant improvement non-bearing partitions; reconfigurin Date: April 12, 2011 Value: $15,000 Permit type: Bldg-alter/repair | Permit status: Permit finaled | Current use: Commercial | Permit id: 11016-10000-059 | |||||
SCORE 100 Plumbing Date: February 3, 2012 Contractor: Sherri Taylor Permit status: Permit finaled | Current use: Commercial | Permit id: 12042-90000-021 | |||||
T. I within 22nd floor. Extended coverage sprinklers within offices. Date: March 24, 2010 Permit type: Fire sprinkler | Permit status: Permit finaled | Current use: Commercial | Permit id: 10043-10000-006 | |||||
SCORE 100 Electrical Date: July 3, 2012 Contractor: Ricardo Ramos Permit status: Permit finaled | Current use: Commercial | Permit id: 12041-20000-154 | |||||
SCORE 74 Electrical Date: April 3, 2012 Contractor: William Snyder Permit status: Permit finaled | Current use: Commercial | Permit id: 12041-90000-075 | |||||
T. I within suite 1940. Extended coverage sprinklers within offices. Date: March 24, 2010 Permit type: Fire sprinkler | Permit status: Permit finaled | Current use: Commercial | Permit id: 10043-10000-006 | |||||
SCORE 99 Electrical Date: December 6, 2010 Contractor: Mark Levin Permit status: Permit finaled | Current use: Commercial | Permit id: 10041-90000-242 | |||||
SCORE 100 Ti for office on 25th floor; non bearing partitions, millwork and Permit type: Bldg-alter/repair | Permit status: Permit finaled | Current use: Commercial | Permit id: 11016-10000-043 | |||||
SCORE 89 Electrical Date: January 18, 2012 Contractor: Sugheim Gonzalez Permit status: Permit expired | Current use: Commercial | Permit id: 12041-90000-011 | |||||
SCORE 86 Electrical Date: December 6, 2010 Contractor: Curtis Chipley Permit status: Permit expired | Current use: Commercial | Permit id: 10041-90000-242 | |||||
SCORE 100 Plumbing Date: March 16, 2010 Contractor: Kevin Michel Permit status: Permit finaled | Current use: Commercial | Permit id: 10042-90000-042 | |||||
SCORE 82 Ti on 27th floor. (n) partitions, doors, ceiling to re-work private o Permit type: Bldg-alter/repair | Permit status: Permit finaled | Current use: Commercial | Permit id: 11016-10000-028 | |||||
SCORE 100 Tenant improvement on second floor. Permit type: Bldg-alter/repair | Permit status: Permit expired | Current use: Commercial | Permit id: 12016-20000-077 | |||||
SCORE 100 Fire sprinkler Date: March 2, 2012 Contractor: Jeff Pettitt Permit status: Permit expired | Current use: Commercial | Permit id: 12043-10000-006 | |||||
SCORE 56 Electrical Date: March 1, 2011 Contractor: C Sarmiento Permit status: Permit finaled | Current use: Commercial | Permit id: 11041-10000-038 | |||||
SCORE 100 Electrical Date: April 14, 2010 Contractor: Arica Simpson Permit status: Permit finaled | Current use: Commercial | Permit id: 10041-90000-067 | |||||
SCORE 96 Hvac Date: May 18, 2011 Contractor: Aviva Murprhy Permit status: Permit finaled | Current use: Commercial | Permit id: 11044-90000-054 | |||||
SCORE 97 Tenant improvement for (e) office suite # 19 (b occupancy, 46 sq Permit type: Bldg-alter/repair | Permit status: Permit finaled | Current use: Commercial | Permit id: 10016-10000-017 | |||||
SCORE 67 Create new openings for interior stairs connecting floors 40, 41 and 4 Permit type: Bldg-alter/repair | Permit status: Permit finaled | Current use: Commercial | Permit id: 12016-10000-159 | |||||
SCORE 97 Interior tenant improvement for existing office suite on ground floor: Permit type: Bldg-alter/repair | Permit status: Permit finaled | Current use: Commercial | Permit id: 10016-30000-155 | |||||
SCORE 82 Demo of interior partitions ceiling and finishes at the 42 Permit type: Bldg-alter/repair | Permit status: Permit finaled | Current use: Commercial | Permit id: 11016-10000-249 | |||||
SCORE 67 Office space build out for floors 40th ,41st & 42nd. Structural openin Permit type: Bldg-alter/repair | Permit status: Issued | Current use: Commercial | Permit id: 12016-10000-177 | |||||
SCORE 74 Remove and replace water damaged drywall and ceiling tiles on the 5th Permit type: Bldg-alter/repair | Permit status: Issued | Current use: Commercial | Permit id: 11016-20000-068 | |||||
SCORE 100 Electrical Date: January 18, 2012 Contractor: Bernadette Agcaoili Permit status: Permit finaled | Current use: Commercial | Permit id: 12041-10000-010 | |||||
SCORE 99 Electrical Date: April 13, 2011 Contractor: Igal Yungman Permit status: Permit finaled | Current use: Commercial | Permit id: 11041-90000-073 | |||||
SCORE 97 T. I. For office on 30th floor; add demising wall to divide one tenant Permit type: Bldg-alter/repair | Permit status: Permit finaled | Current use: Commercial | Permit id: 10016-10000-221 | |||||
SCORE 99 Fire sprinkler Date: September 13, 2010 Contractor: Jeff Pettit Permit status: Permit finaled | Current use: Commercial | Permit id: 10043-10000-020 | |||||
T/i work in ste# 2500. Extended coverage with proof calculations Date: April 29, 2011 Permit type: Fire sprinkler | Permit status: Permit finaled | Current use: Commercial | Permit id: 11043-10000-010 | |||||
SCORE 86 Hvac Date: March 29, 2010 Contractor: Gerardus Opzeeland Permit status: Permit finaled | Current use: Commercial | Permit id: 10044-90000-028 | |||||
SCORE 97 Electrical Date: February 15, 2012 Contractor: Ricardo Permit status: Issued | Current use: Commercial | Permit id: 12041-10000-035 | |||||
SCORE 100 Add demising walls on 38th floor to create (2) office tenant spaces. Permit type: Bldg-alter/repair | Permit status: Permit finaled | Current use: Commercial | Permit id: 11016-10000-003 | |||||
SCORE 82 Office t. I . On 3rd floor: combine suite 3 and 3 into a single tena Permit type: Bldg-alter/repair | Permit status: Permit finaled | Current use: Commercial | Permit id: 11016-10000-235 | |||||
SCORE 82 T. I. To (e) office space, approx 1306 sqft (install nonbearing partiti Permit type: Bldg-alter/repair | Permit status: Permit finaled | Current use: Commercial | Permit id: 11016-20000-238 | |||||
SCORE 100 Hvac Date: March 10, 2010 Contractor: Michael Mamroth Permit status: Permit finaled | Current use: Commercial | Permit id: 10044-90000-022 | |||||
Early start demolition of interior nonbearing walls and finishes Date: January 29, 2010 Value: $50,000 Permit type: Bldg-alter/repair | Permit status: Permit finaled | Current use: Commercial | Permit id: 10016-20000-016 | |||||
SCORE 100 Ti on 36th floor; unit #3630. (n) partitions, millwork & finishes Permit type: Bldg-alter/repair | Permit status: Permit finaled | Current use: Commercial | Permit id: 12016-10000-128 | |||||
SCORE 82 Interior non structural tenant improvement (install non bearing partio Permit type: Bldg-alter/repair | Permit status: Permit finaled | Current use: Commercial | Permit id: 12016-20000-057 | |||||
SCORE 82 Ti on 24th floor; (n) door & finishes at existing tenant suite; ~2,100 Permit type: Bldg-alter/repair | Permit status: Permit finaled | Current use: Commercial | Permit id: 12016-10000-034 | |||||
SCORE 100 Electrical Date: February 24, 2010 Contractor: Monica Withers Permit status: Permit finaled | Current use: Commercial | Permit id: 10041-90000-032 | |||||
SCORE 56 Electrical Date: August 22, 2011 Contractor: Keith Glasman Permit status: Issued | Current use: Commercial | Permit id: 11041-10000-178 | |||||
SCORE 87 Electrical Date: March 29, 2010 Contractor: Shelby Toal Permit status: Permit finaled | Current use: Commercial | Permit id: 10041-90000-056 | |||||
SCORE 89 Fire sprinkler tenant improvement on 2nd floor. Add (2) and relocate Date: July 22, 2011 Contractor: Ed Navarro Permit type: Fire sprinkler | Permit status: Permit finaled | Current use: Commercial | Permit id: 11043-10000-018 | |||||
T. I within 18th floor, added and relocated sprinklers. Date: April 21, 2011 Permit type: Fire sprinkler | Permit status: Issued | Current use: Commercial | Permit id: 11043-10000-009 | |||||
SCORE 100 Electrical Date: February 2, 2012 Contractor: Arica Simpson Permit status: Permit finaled | Current use: Commercial | Permit id: 12041-90000-025 | |||||
SCORE 86 Interior tenant improvement for existing office suite on 22nd floor (p Permit type: Bldg-alter/repair | Permit status: Permit finaled | Current use: Commercial | Permit id: 10016-10000-037 | |||||
SCORE 100 Early start demo < 24,527 sf of entire 40th floor; 17,067 sf on 42 Permit type: Bldg-alter/repair | Permit status: Permit finaled | Current use: Commercial | Permit id: 12016-10000-079 | |||||
SCORE 100 Demo only, early start 21,5 sf <4th floor> Permit type: Bldg-alter/repair | Permit status: Permit expired | Current use: Commercial | Permit id: 12016-10000-011 | |||||
SCORE 100 Plumbing Date: April 29, 2011 Contractor: Sherri Taylor Permit status: Permit finaled | Current use: Commercial | Permit id: 11042-90000-073 | |||||
SCORE 100 Install gyp. Board ceiling in elevator lobby on 25th floor. Permit type: Bldg-alter/repair | Permit status: Permit finaled | Current use: Commercial | Permit id: 10016-10000-151 | |||||
SCORE 79 Elevator Date: February 28, 2012 Contractor: Suzin Lufrano Permit status: Permit finaled | Current use: Commercial | Permit id: 12046-90000-002 | |||||
Early start permit: demolition of non-bearing walls, millwork, finish Date: January 28, 2010 Value: $25,000 Permit type: Bldg-alter/repair | Permit status: Permit finaled | Current use: Commercial | Permit id: 10016-10000-009 | |||||
SCORE 100 Electrical Date: July 22, 2012 Contractor: David Aguet Permit status: Permit finaled | Current use: Commercial | Permit id: 12041-90000-170 | |||||
SCORE 97 Fire sprinkler Date: March 30, 2011 Contractor: Jeff Permit status: Permit finaled | Current use: Commercial | Permit id: 11043-10000-007 | |||||
SCORE 95 Tenant improvements to existing starbucks coffee at the basement lev Permit type: Bldg-alter/repair | Permit status: Issued | Current use: Commercial | Permit id: 11016-10000-052 | |||||
SCORE 100 Ti- remove (e) demising wall and construct new demising wall to exten Permit type: Bldg-alter/repair | Permit status: Permit finaled | Current use: Commercial | Permit id: 11016-10000-245 | |||||
SCORE 100 Supplemental permit to 10016-10000-12883 to add additional office spac Permit type: Bldg-alter/repair | Permit status: Permit finaled | Current use: Commercial | Permit id: 10016-10001-128 | |||||
Full floor early start interior non-structural demolition of non-beari Date: September 19, 2011 Value: $122,300 Permit type: Bldg-alter/repair | Permit status: Permit finaled | Current use: Commercial | Permit id: 11016-10000-181 | |||||
SCORE 69 Supplemental permit to 09016-10000-17795, tenant improvement. New int Permit type: Bldg-alter/repair | Permit status: Permit finaled | Current use: Commercial | Permit id: 09016-10001-177 | |||||
T. I. On 11th floor. (n) non-bearing partitions, partial ceiling, fini Date: April 11, 2011 Value: $40,000 Permit type: Bldg-alter/repair | Permit status: Permit finaled | Current use: Commercial | Permit id: 11016-10000-061 | |||||
SCORE 100 Re-roof with class a or b material weighing less than 6 lbs. Per sq. F Permit type: Bldg-alter/repair | Permit status: Issued | Current use: Commercial | Permit id: 12016-20000-211 | |||||
T. I installation of new sprinklers due to new ceiling. Date: October 7, 2010 Permit type: Fire sprinkler | Permit status: Permit finaled | Current use: Commercial | Permit id: 10043-10000-021 | |||||
SCORE 76 Fire sprinkler Date: January 13, 2010 Contractor: John Knespler Permit status: Permit finaled | Current use: Commercial | Permit id: 10043-10001-000 | |||||
SCORE 66 Ti on 4th floor, (n) partitions, finishes. 2,6 s. F. Permit type: Bldg-alter/repair | Permit status: Permit finaled | Current use: Commercial | Permit id: 12016-10000-016 | |||||
SCORE 100 Electrical Date: March 10, 2010 Contractor: David Aguet Permit status: Permit finaled | Current use: Commercial | Permit id: 10041-90000-043 | |||||
SCORE 93 Minor ti work to include new partition, new ceiling; enclosed (e) door Permit type: Bldg-alter/repair | Permit status: Permit finaled | Current use: Commercial | Permit id: 11016-10000-048 | |||||
SCORE 100 Elevator Date: August 22, 2011 Contractor: Sharon Green Permit status: Permit finaled | Current use: Commercial | Permit id: 11046-10000-010 | |||||
SCORE 97 T. I. On 23rd floor: install interior non-bearing partitions, millwork Permit type: Bldg-alter/repair | Permit status: Permit finaled | Current use: Commercial | Permit id: 10016-10000-186 | |||||
SCORE 72 Fire sprinkler Date: March 3, 2011 Contractor: Paul Marrujo Permit status: Permit finaled | Current use: Commercial | Permit id: 11043-10000-005 | |||||
SCORE 56 Interior improvement; minor demolition of (e) glass partition, new non Permit type: Bldg-alter/repair | Permit status: Permit finaled | Current use: Commercial | Permit id: 10016-10000-015 | |||||
SCORE 89 Fire sprinkler Date: February 6, 2012 Contractor: Frank J. Mone Permit status: Permit finaled | Current use: Commercial | Permit id: 12043-90000-003 | |||||
SCORE 100 Add (2) and relocate (32) fire sprinklers in suite 400. Date: February 3, 2012 Contractor: Jimmy Pulido Permit type: Fire sprinkler | Permit status: Permit finaled | Current use: Commercial | Permit id: 12043-10000-003 | |||||
SCORE 92 Elevator Date: July 20, 2012 Contractor: Lidia Gonzalez Permit status: Permit finaled | Current use: Commercial | Permit id: 12046-90000-008 | |||||
SCORE 98 Electrical Date: October 4, 2010 Contractor: Raymond Permit status: Permit finaled | Current use: Commercial | Permit id: 10041-10000-185 | |||||
SCORE 100 Electrical Date: November 28, 2011 Contractor: Jj Ross Permit status: Permit finaled | Current use: Commercial | Permit id: 11041-90000-252 | |||||
SCORE 56 Ti for office on 2nd floor; non bearing partitions, millwork and susp Permit type: Bldg-alter/repair | Permit status: Permit finaled | Current use: Commercial | Permit id: 11016-10000-108 | |||||
SCORE 95 Electrical Date: July 12, 2011 Contractor: Jason De La Garza Permit status: Permit expired | Current use: Commercial | Permit id: 11041-90000-144 | |||||
SCORE 92 Electrical Date: September 9, 2010 Contractor: Gordon Maccani Permit status: Permit finaled | Current use: Commercial | Permit id: 10041-90000-178 | |||||
SCORE 82 Electrical Date: March 9, 2010 Contractor: Donna Woodford Permit status: Permit finaled | Current use: Commercial | Permit id: 10041-90000-042 | |||||
Plumbing Date: March 31, 2016 Permit status: Issued | Current use: Commercial | Permit id: 16042-30000-063 | |||||
SCORE 93 Early start demo Permit type: Bldg-alter/repair | Permit status: Permit finaled | Current use: Commercial | Permit id: 15016-10000-212 | |||||
Hvac Date: March 12, 2015 Permit status: Permit finaled | Current use: Commercial | Permit id: 15044-20000-022 | |||||
SCORE 100 Electrical Date: April 11, 2016 Contractor: Arica Simpson Permit status: Issued | Current use: Commercial | Permit id: 16041-90000-125 | |||||
SCORE 76 Change of use 8 sq ft portion from office to barber shop in suite # Permit type: Bldg-alter/repair | Permit status: Permit finaled | Current use: Commercial | Permit id: 15016-30000-177 | |||||
SCORE 96 Hvac Date: August 2, 2013 Contractor: Clay Dunn Permit status: Permit finaled | Current use: Commercial | Permit id: 13044-90000-080 | |||||
SCORE 96 Hvac Date: April 30, 2015 Contractor: Clay Dunn Permit status: Issued | Current use: Commercial | Permit id: 15044-90000-040 | |||||
SCORE 98 Electrical Date: January 16, 2013 Contractor: Frank Permit status: Permit finaled | Current use: Commercial | Permit id: 13041-10000-012 | |||||
SCORE 100 Fire sprinkler Date: August 20, 2015 Contractor: Anna Alpizar Permit status: Permit finaled | Current use: Commercial | Permit id: 15043-90000-037 | |||||
SCORE 100 Electrical Date: October 20, 2015 Contractor: Ali Sherafat Permit status: Permit finaled | Current use: Commercial | Permit id: 15041-10000-340 | |||||
Electrical Date: May 21, 2014 Permit status: Permit finaled | Current use: Commercial | Permit id: 14041-10000-135 | |||||
SCORE 96 Hvac Date: January 9, 2013 Contractor: Aviva Murprhy Permit status: Permit finaled | Current use: Commercial | Permit id: 13044-90000-002 | |||||
SCORE 61 Electrical Date: May 12, 2014 Contractor: Mohammad Irani Permit status: Permit finaled | Current use: Commercial | Permit id: 14041-10000-125 | |||||
SCORE 100 Non-structural interior office ti. No change of use. New demising wall Permit type: Bldg-alter/repair | Permit status: Permit finaled | Current use: Commercial | Permit id: 14016-10000-125 | |||||
SCORE 93 Interior renovation of an exising office space including new non-beari Permit type: Bldg-alter/repair | Permit status: Permit finaled | Current use: Commercial | Permit id: 13016-10000-176 | |||||
SCORE 82 Early start interior non-structural demolition on 9th floor. Permit type: Bldg-alter/repair | Permit status: Permit finaled | Current use: Commercial | Permit id: 13016-10000-205 | |||||
SCORE 100 Supplemental to permit number 15016-10000-28193 to revise floor plan. Permit type: Bldg-alter/repair | Permit status: Issued | Current use: Commercial | Permit id: 15016-10001-281 | |||||
SCORE 100 Fire sprinkler Date: September 24, 2015 Contractor: Jeff Pettitt Permit status: Permit finaled | Current use: Commercial | Permit id: 15043-90000-042 | |||||
SCORE 59 New glass guardrail system for (e) stairs @ 10th floor. Permit type: Bldg-alter/repair | Permit status: Permit finaled | Current use: Commercial | Permit id: 14016-10000-022 | |||||
SCORE 84 Plumbing Date: April 24, 2015 Contractor: Ethan Permit status: Permit finaled | Current use: Commercial | Permit id: 15042-10000-082 | |||||
Add 19 fan coil units and modify existing hvac system on 40, 41, and Date: January 8, 2013 Permit type: Hvac | Permit status: Permit finaled | Current use: Commercial | Permit id: 12044-10000-113 | |||||
Electrical Date: April 8, 2013 Permit status: Permit finaled | Current use: Commercial | Permit id: 13041-10000-088 | |||||
SCORE 100 Hvac Date: February 3, 2016 Contractor: Michael Mamroth Permit status: Permit finaled | Current use: Commercial | Permit id: 16044-20000-012 | |||||
SCORE 100 Tenant improvement for office on partial of suite 1200. Interior parti Permit type: Bldg-alter/repair | Permit status: Issued | Current use: Commercial | Permit id: 16016-10000-029 | |||||
SCORE 100 Fire sprinkler Permit status: Permit finaled | Current use: Commercial | Permit id: 13043-10000-003 | |||||
SCORE 100 Plumbing Date: March 4, 2013 Contractor: Sherri Taylor Permit status: Permit finaled | Current use: Commercial | Permit id: 13042-90000-043 | |||||
SCORE 96 Hvac Date: June 18, 2015 Contractor: Aviva Murprhy Permit status: Permit finaled | Current use: Commercial | Permit id: 15044-90000-059 | |||||
SCORE 98 Tenant improvement involving renovations for three office rooms on 40 Permit type: Bldg-alter/repair | Permit status: Permit finaled | Current use: Commercial | Permit id: 15016-30000-069 | |||||
SCORE 100 Partial floor office tenant improvement including: demolition, new pa Permit type: Bldg-alter/repair | Permit status: Permit finaled | Current use: Commercial | Permit id: 15016-10000-145 | |||||
SCORE 99 Added interconnecting stair between 28th and 29th floors and modern fo Permit type: Bldg-alter/repair | Permit status: Permit finaled | Current use: Commercial | Permit id: 15016-10000-091 | |||||
SCORE 100 Fire sprinkler Date: June 4, 2013 Contractor: Jeff Pettitt Permit status: Permit finaled | Current use: Commercial | Permit id: 13043-10000-017 | |||||
SCORE 100 T. I. - new fire sprinklers on 21st, 22nd, and 23rd floor office spaces Date: March 15, 2016 Contractor: Jeff Pettitt Permit type: Fire sprinkler | Permit status: Issued | Current use: Commercial | Permit id: 16043-10000-011 | |||||
SCORE 100 Electrical Date: April 7, 2015 Contractor: Ali Sherafat Permit status: Permit finaled | Current use: Commercial | Permit id: 14041-10000-175 | |||||
SCORE 68 Electrical Date: December 2, 2014 Contractor: Frank Kim Permit status: Permit finaled | Current use: Commercial | Permit id: 14041-10000-333 | |||||
SCORE 96 Hvac Date: January 7, 2014 Contractor: Clay Dunn Permit status: Permit finaled | Current use: Commercial | Permit id: 14044-90000-001 | |||||
SCORE 62 Office ti of existing tenant space; no change in use; existing b ocu Permit type: Bldg-alter/repair | Permit status: Permit finaled | Current use: Commercial | Permit id: 13016-10000-086 | |||||
SCORE 93 Interior t. I. Including non-bearing partitions, new demising wall, cei Permit type: Bldg-alter/repair | Permit status: Issued | Current use: Commercial | Permit id: 15016-10000-101 | |||||
SCORE 92 10th floor ti on non bearing walls; new interior remodeling 127 sq Permit type: Bldg-alter/repair | Permit status: Permit finaled | Current use: Commercial | Permit id: 13016-10000-241 | |||||
SCORE 100 Fire sprinkler Date: October 27, 2014 Contractor: Jeff Pettitt Permit status: Permit finaled | Current use: Commercial | Permit id: 14043-90000-044 | |||||
SCORE 100 Electrical Date: January 7, 2013 Contractor: Ali Sherafat Permit status: Permit finaled | Current use: Commercial | Permit id: 12041-20000-311 | |||||
SCORE 88 Tenant improvement to (e) office; new non bearing partitions, millwork Permit type: Bldg-alter/repair | Permit status: Permit finaled | Current use: Commercial | Permit id: 14016-10000-227 | |||||
SCORE 99 Interior tenant improvement: demo non-bearing walls and constructino Permit type: Bldg-alter/repair | Permit status: Permit finaled | Current use: Commercial | Permit id: 14016-10000-251 | |||||
SCORE 61 Electrical Date: May 6, 2015 Contractor: Wmgroup Permit status: Permit finaled | Current use: Commercial | Permit id: 15041-10000-136 | |||||
SCORE 59 Add 309 and relocate 64 fire sprinklerr heads, 28th an 29th floors. Date: April 30, 2015 Contractor: Jett Pettitt Permit type: Fire sprinkler | Permit status: Permit finaled | Current use: Commercial | Permit id: 15043-10000-017 | |||||
SCORE 100 Tenant improvement to (e) office. Construct nonbearing partitions, ce Permit type: Bldg-alter/repair | Permit status: Permit finaled | Current use: Commercial | Permit id: 15016-10000-283 | |||||
SCORE 93 Electrical Date: April 27, 2016 Contractor: Sue Permit status: Issued | Current use: Commercial | Permit id: 16041-20000-147 | |||||
SCORE 100 Ti for office on 3rd floor non bearing partitions, millwork, suspended Permit type: Bldg-alter/repair | Permit status: Permit finaled | Current use: Commercial | Permit id: 15016-10000-279 | |||||
SCORE 59 Supplemental permit to change address from: 2049 s century park east t Date: October 1, 2014 Contractor: Christine Ozols Permit type: Bldg-alter/repair | Permit status: Permit finaled | Current use: Commercial | Permit id: 14016-20001-180 | |||||
SCORE 93 Early start interior demolition for (e) office bldg on levels 21-23 pe Permit type: Bldg-alter/repair | Permit status: Issued | Current use: Commercial | Permit id: 16016-10000-041 | |||||
SCORE 100 Interior ti to an existing lunch room of an existing office ti space; Permit type: Bldg-alter/repair | Permit status: Permit finaled | Current use: Commercial | Permit id: 13016-10000-248 | |||||
SCORE 59 Suplemental to #15016-10000-07718 change the address, add 28th flo Date: April 27, 2015 Contractor: Tabia Kallies Permit type: Bldg-alter/repair | Permit status: Permit finaled | Current use: Commercial | Permit id: 15016-10001-077 | |||||
SCORE 59 Supplemental to permit #13016-10000-08696 to modify demising wall & co Permit type: Bldg-alter/repair | Permit status: Permit finaled | Current use: Commercial | Permit id: 13016-10001-086 | |||||
SCORE 59 Provide supplemental to permit# 14016-10000-12109 revise floor plan. ( Permit type: Bldg-alter/repair | Permit status: Permit finaled | Current use: Commercial | Permit id: 14016-10001-121 | |||||
SCORE 100 Electrical Date: January 19, 2016 Contractor: Ali Sherafat Permit status: Permit finaled | Current use: Commercial | Permit id: 16041-10000-016 | |||||
SCORE 100 Electrical Date: February 19, 2016 Contractor: Ali Sherafat Permit status: Issued | Current use: Commercial | Permit id: 16041-10000-053 | |||||
SCORE 100 Fire sprinkler Date: September 16, 2013 Contractor: Frank Mone Permit status: Permit finaled | Current use: Commercial | Permit id: 13043-90000-030 | |||||
SCORE 96 Hvac Date: November 7, 2014 Contractor: Aviva Murprhy Permit status: Permit finaled | Current use: Commercial | Permit id: 14044-90000-112 | |||||
SCORE 100 Electrical Date: April 19, 2016 Contractor: Ricardo Ramos Permit status: Issued | Current use: Commercial | Permit id: 16041-90000-135 | |||||
SCORE 59 Supplemental permit to change address from: 2049 s century park east t Date: June 3, 2015 Contractor: Kim Waldrup Permit type: Bldg-alter/repair | Permit status: Permit finaled | Current use: Commercial | Permit id: 15016-20001-101 | |||||
SCORE 86 Tenant improvement - new interior partitions, wall covering, floor cov Permit type: Bldg-alter/repair | Permit status: Permit finaled | Current use: Commercial | Permit id: 13016-10000-233 | |||||
SCORE 100 Fire sprinkler Date: July 15, 2015 Contractor: Frank Mone Permit status: Permit finaled | Current use: Commercial | Permit id: 15043-90000-030 | |||||
SCORE 86 Hvac Date: October 1, 2015 Contractor: Aviva Murphy Permit status: Permit finaled | Current use: Commercial | Permit id: 15044-90000-102 | |||||
SCORE 98 Electrical Date: July 9, 2013 Contractor: James Permit status: Permit expired | Current use: Commercial | Permit id: 13041-40000-180 | |||||
SCORE 100 Add 4 and relocate 12 fire sprinkler heads, 2nd floor. Date: October 8, 2015 Contractor: Jeff Pettitt Permit type: Fire sprinkler | Permit status: Permit finaled | Current use: Commercial | Permit id: 15043-10000-046 | |||||
SCORE 93 T. I. To remove (e) interior stair from 8th to 9th floors, infill floor Permit type: Bldg-alter/repair | Permit status: Permit finaled | Current use: Commercial | Permit id: 13016-10000-107 | |||||
SCORE 100 Add 3 and relocate 22 fire sprinkler heads, suite # 32 3206, 32nd Date: November 5, 2013 Contractor: Jeff Pettitt Permit type: Fire sprinkler | Permit status: Permit finaled | Current use: Commercial | Permit id: 13043-10000-037 | |||||
SCORE 100 Add 4 and relocate 22 fire sprinkler heads, suite #2410s. Date: June 16, 2015 Contractor: Jeff Pettitt Permit type: Fire sprinkler | Permit status: Permit finaled | Current use: Commercial | Permit id: 15043-10000-025 | |||||
SCORE 100 Electrical Date: May 21, 2014 Contractor: Ali Sherafat Permit status: Issued | Current use: Commercial | Permit id: 14041-10001-134 | |||||
SCORE 99 Relocate 7 and add 2 sprinklers to an existing office building on the Date: January 13, 2015 Contractor: Jeff Pettit Permit type: Fire sprinkler | Permit status: Permit finaled | Current use: Commercial | Permit id: 15043-10000-001 | |||||
SCORE 100 Tenant improvement on 3rd floor to add (7) and relocate (18) heads. Date: November 13, 2014 Contractor: Jeff Pettitt Permit type: Fire sprinkler | Permit status: Permit finaled | Current use: Commercial | Permit id: 14043-10000-046 | |||||
SCORE 99 Tenant improvement on 8th floor of existing commercial building. Relo Date: April 5, 2016 Contractor: Jeff Pettit Permit type: Fire sprinkler | Permit status: Issued | Current use: Commercial | Permit id: 16043-10000-015 | |||||
SCORE 67 Supplemental permit for structural support for new stairs connecting f Permit type: Bldg-alter/repair | Permit status: Permit expired | Current use: Commercial | Permit id: 12016-10001-177 | |||||
SCORE 98 Electrical Date: June 3, 2014 Contractor: Thomas Permit status: Permit finaled | Current use: Commercial | Permit id: 14041-10000-146 | |||||
SCORE 100 T. I. For office on 43rd floor (suite 4320); minor demo. & (n) low wal Permit type: Bldg-alter/repair | Permit status: Permit finaled | Current use: Commercial | Permit id: 12016-10000-255 | |||||
SCORE 100 Plumbing Date: May 14, 2014 Contractor: Sherri Taylor Permit status: Permit finaled | Current use: Commercial | Permit id: 14042-90000-091 | |||||
SCORE 86 Hvac Date: February 19, 2016 Contractor: Aviva Murphy Permit status: Issued | Current use: Commercial | Permit id: 16044-90000-018 | |||||
SCORE 86 Electrical Date: June 18, 2015 Contractor: Ali Sharafat Permit status: Permit finaled | Current use: Commercial | Permit id: 15041-10000-184 | |||||
SCORE 61 Electrical Date: January 12, 2016 Contractor: P.E.M Permit status: Permit finaled | Current use: Commercial | Permit id: 15041-20000-261 | |||||
SCORE 86 Interior demolition to tenant space only, no structural, bathroom or Permit type: Bldg-alter/repair | Permit status: Permit finaled | Current use: Commercial | Permit id: 15016-10000-241 | |||||
SCORE 99 Electrical Date: July 24, 2015 Contractor: Ron Permit status: Issued | Current use: Commercial | Permit id: 15041-10000-236 | |||||
SCORE 76 Office renovation of approx 60 sf includes demo and new non bearing Permit type: Bldg-alter/repair | Permit status: Permit finaled | Current use: Commercial | Permit id: 13016-10000-122 | |||||
SCORE 61 Electrical Date: September 18, 2015 Contractor: Chris Sarmiento Permit status: Permit finaled | Current use: Commercial | Permit id: 15041-10000-269 | |||||
SCORE 59 Tenant improvement on 10th floor (11,885 sq. Ft.), limited to west por Permit type: Bldg-alter/repair | Permit status: Issued | Current use: Commercial | Permit id: 14016-10000-121 | |||||
SCORE 59 Supplemental-to 13016-10000-260 for minor revisions reductions in sc Permit type: Bldg-alter/repair | Permit status: Issued | Current use: Commercial | Permit id: 13016-10001-260 | |||||
SCORE 92 Supplemental to correct the address on 13016-10000-24168 with work des Date: December 17, 2013 Contractor: Nikki Permit type: Bldg-alter/repair | Permit status: Permit finaled | Current use: Commercial | Permit id: 13016-10001-241 | |||||
SCORE 100 T. I. For office on 36th floor; non-bearing partitions, millwork, susp Permit type: Bldg-alter/repair | Permit status: Permit finaled | Current use: Commercial | Permit id: 13016-10000-029 | |||||
SCORE 61 Electrical Date: September 19, 2013 Contractor: Christopher Bertell Permit status: Permit expired | Current use: Commercial | Permit id: 13041-10000-258 | |||||
SCORE 93 Electrical Date: April 13, 2016 Contractor: Brad Gulsrud Permit status: Issued | Current use: Commercial | Permit id: 16041-90000-129 | |||||
SCORE 97 Ti to the 27th floor to relocate 11 sprinkler heads and add 1. All hea Date: January 29, 2015 Contractor: Jeff Permit type: Fire sprinkler | Permit status: Refund completed | Current use: Commercial | Permit id: 15043-10000-004 | |||||
SCORE 99 Electrical Date: October 7, 2015 Contractor: Jason Permit status: Issued | Current use: Commercial | Permit id: 15041-20000-332 | |||||
SCORE 59 Tenant improvement to existing office (suite #2700) 1,4 sq ft: remov Permit type: Bldg-alter/repair | Permit status: Permit finaled | Current use: Commercial | Permit id: 13016-10000-201 | |||||
SCORE 100 Supplemental permit to 12016-10000-25842 to reinforce composite floor. Permit type: Bldg-alter/repair | Permit status: Permit expired | Current use: Commercial | Permit id: 12016-30001-258 | |||||
SCORE 100 Fire sprinkler Date: February 11, 2016 Contractor: Jeff Pettitt Permit status: Permit finaled | Current use: Commercial | Permit id: 16043-10000-006 | |||||
SCORE 93 Supplemental permit to 13016-10000-26065 to revise the scope of work t Date: March 26, 2015 Contractor: Grisselda Hernandez Permit type: Bldg-alter/repair | Permit status: Permit finaled | Current use: Commercial | Permit id: 13016-30001-260 | |||||
SCORE 77 Tenant improvement to (e) office - remove and construct new nonbearing Permit type: Bldg-alter/repair | Permit status: Permit finaled | Current use: Commercial | Permit id: 13016-10000-200 | |||||
SCORE 100 Early start demo permit to remove non-bearing partition walls, millwor Permit type: Bldg-alter/repair | Permit status: Permit finaled | Current use: Commercial | Permit id: 13016-10000-154 | |||||
Interior nonstructural t. I. (4348 sf) to install new non bearing parti Date: February 21, 2013 Value: $195,660 Permit type: Bldg-alter/repair | Permit status: Permit finaled | Current use: Commercial | Permit id: 13016-10000-031 | |||||
SCORE 93 For suite 3180, interior non structural t. I. For an existing office; Permit type: Bldg-alter/repair | Permit status: Permit finaled | Current use: Commercial | Permit id: 13016-10000-154 | |||||
SCORE 100 Electrical Date: February 5, 2016 Contractor: Jason Williams Permit status: Issued | Current use: Commercial | Permit id: 16041-10000-042 | |||||
SCORE 98 Tenant improvement at 42nd floor to create three new offices and alter Permit type: Bldg-alter/repair | Permit status: Permit finaled | Current use: Commercial | Permit id: 15016-30000-071 | |||||
Supplemental permit for deferred submittal of glass hand and guard rai Date: April 12, 2013 Value: $301 Permit type: Bldg-alter/repair | Permit status: Permit expired | Current use: Commercial | Permit id: 12016-10002-177 | |||||
SCORE 98 Electrical Date: May 17, 2013 Contractor: Frank Permit status: Issued | Current use: Commercial | Permit id: 13041-40000-129 | |||||
SCORE 82 Structural strengthening in the core area of building. Permit type: Bldg-alter/repair | Permit status: Permit expired | Current use: Commercial | Permit id: 13016-10000-037 | |||||
SCORE 100 Add 2 and relocate 4 fire sprinkler heads, 2nd floor. Date: August 20, 2015 Contractor: Jeff Pettitt Permit type: Fire sprinkler | Permit status: Permit finaled | Current use: Commercial | Permit id: 15043-10000-037 | |||||
SCORE 100 Tenant improvement to (e) office on 23rd floor, work includes new int Permit type: Bldg-alter/repair | Permit status: Permit finaled | Current use: Commercial | Permit id: 12016-10000-258 | |||||
SCORE 100 Tenant improvement to add (73) standard and extended coverage and rel Date: May 20, 2014 Contractor: Jeff Pettitt Permit type: Fire sprinkler | Permit status: Permit finaled | Current use: Commercial | Permit id: 14043-10000-018 | |||||
SCORE 93 Electrical Date: November 2, 2015 Contractor: Gabriel Juarez Permit status: Issued | Current use: Commercial | Permit id: 15041-10000-368 | |||||
SCORE 92 Electrical Date: August 14, 2015 Contractor: Jessie Permit status: Permit finaled | Current use: Commercial | Permit id: 15041-10000-265 | |||||
SCORE 70 Ti on the 40, 41, and 42 floors of a highrise office bldg. New panels, Date: January 11, 2013 Contractor: Michael Adebanjo Permit type: Electrical | Permit status: Permit finaled | Current use: Commercial | Permit id: 12041-10000-254 | |||||
Addition of one non-bearing partition on the 18th floor to enclose (e) Date: September 25, 2013 Value: $3,000 Permit type: Bldg-alter/repair | Permit status: Permit finaled | Current use: Commercial | Permit id: 13016-10000-195 | |||||
SCORE 91 Electrical Date: January 15, 2015 Contractor: Kelly Evans Permit status: Permit finaled | Current use: Commercial | Permit id: 14041-10000-337 | |||||
SCORE 93 Supplemental to 16016-10000-04136 to revise the address range from flr Date: February 29, 2016 Contractor: Sarah Catalan Permit type: Bldg-alter/repair | Permit status: Issued | Current use: Commercial | Permit id: 16016-10001-041 | |||||
SCORE 93 Minor tenant improvement of executive suite and meeting space for floo Permit type: Bldg-alter/repair | Permit status: Permit finaled | Current use: Commercial | Permit id: 13016-10000-260 | |||||
SCORE 96 Structural demolition of existing convenience stair bewteen 28 & 29 fl Permit type: Bldg-alter/repair | Permit status: Permit finaled | Current use: Commercial | Permit id: 15014-10000-017 | |||||
SCORE 99 Proposed non-structural interior alterations. Permit type: Bldg-alter/repair | Permit status: Issued | Current use: Commercial | Permit id: 15016-10000-077 | |||||
SCORE 93 Interior renovation including new partitions, ceilng, and finishes. Re Permit type: Bldg-alter/repair | Permit status: Permit finaled | Current use: Commercial | Permit id: 13016-10000-216 | |||||
SCORE 100 Tenant improvement for office space, including interior partition, doo Permit type: Bldg-alter/repair | Permit status: Permit finaled | Current use: Commercial | Permit id: 15016-10000-212 | |||||
SCORE 79 Elevator Date: June 2, 2014 Contractor: Sharon Greey Permit status: Permit finaled | Current use: Commercial | Permit id: 14046-10000-008 | |||||
SCORE 78 Early start interior demolition only; non structural demo of 56,514sf Permit type: Bldg-alter/repair | Permit status: Issued | Current use: Commercial | Permit id: 15016-10000-044 | |||||
SCORE 100 Tenant improvemnet for office space, including partition, door, electr Permit type: Bldg-alter/repair | Permit status: Permit finaled | Current use: Commercial | Permit id: 15016-10000-242 | |||||
SCORE 100 Supplemental to 13016-10000-260 b& 13016-10001-260 for revision on Permit type: Bldg-alter/repair | Permit status: Permit finaled | Current use: Commercial | Permit id: 13016-10002-260 | |||||
SCORE 98 Electrical Date: September 11, 2013 Contractor: David Morales Permit status: Issued | Current use: Commercial | Permit id: 13041-10000-250 | |||||
SCORE 61 Electrical Date: February 12, 2013 Contractor: Corey Mattaliano Permit status: Permit finaled | Current use: Commercial | Permit id: 13041-30000-036 | |||||
SCORE 99 T. I. Interior early start demo only non-bearing walls. Permit type: Bldg-alter/repair | Permit status: Permit expired | Current use: Commercial | Permit id: 13016-10000-024 | |||||
SCORE 93 Interior tenant improvment to (e) office space, including non-bearing Permit type: Bldg-alter/repair | Permit status: Permit finaled | Current use: Commercial | Permit id: 14016-20000-249 | |||||
SCORE 98 Office t. I. On the 41st floor(1,2 sq ft).(see comments). Permit type: Bldg-alter/repair | Permit status: Permit finaled | Current use: Commercial | Permit id: 15016-30000-070 | |||||
SCORE 70 Electrical Date: April 19, 2016 Contractor: Dan Winovitch Permit status: Issued | Current use: Commercial | Permit id: 16041-90000-136 | |||||
SCORE 100 Change of address from 2049 s century park east to 2049 s century park Date: November 5, 2015 Contractor: Kim Permit type: Bldg-alter/repair | Permit status: Issued | Current use: Commercial | Permit id: 15016-20001-237 | |||||
SCORE 100 Fire sprinkler Date: February 5, 2014 Contractor: Frank Mone Permit status: Permit finaled | Current use: Commercial | Permit id: 14043-90000-003 | |||||
SCORE 61 Electrical Date: January 12, 2015 Contractor: Wm Group Permit status: Permit finaled | Current use: Commercial | Permit id: 15041-10000-004 | |||||
SCORE 100 Add and relocate 5 heads, "westmount assety management", suite #250 Date: April 2, 2015 Contractor: Jeff Pettitt Permit type: Fire sprinkler | Permit status: Issued | Current use: Commercial | Permit id: 15043-10000-013 | |||||
SCORE 67 Electrical Date: August 1, 2013 Contractor: Frank Zainabad Permit status: Permit finaled | Current use: Commercial | Permit id: 13041-10000-205 | |||||
SCORE 100 Tenant improvement to add (14) extended coverage and relocate (4) hea Date: December 18, 2014 Contractor: Jeff Pettitt Permit type: Fire sprinkler | Permit status: Permit finaled | Current use: Commercial | Permit id: 14043-10000-051 | |||||
SCORE 59 Pc for power . Medium voltage. Commercial building. Addition of 4 vfd Date: April 1, 2016 Contractor: Devine Stevens Permit type: Electrical | Permit status: Issued | Current use: Commercial | Permit id: 16041-10000-051 | |||||
SCORE 100 Supplemental application for permit 15016-10000-16320: to indice 2nd Date: September 22, 2015 Contractor: Frank Limahelu Permit type: Bldg-alter/repair | Permit status: Permit finaled | Current use: Commercial | Permit id: 15016-10001-163 | |||||
SCORE 93 Ti: interior office tenant improvement on partial 21st, 22nd, and 23rd Permit type: Bldg-alter/repair | Permit status: Issued | Current use: Commercial | Permit id: 16016-10000-031 | |||||
SCORE 100 Ti for the 40th floor of a high rise building to relocate and add 245 Date: January 11, 2013 Contractor: Frank Mone Permit type: Fire sprinkler | Permit status: Permit finaled | Current use: Commercial | Permit id: 13043-10000-000 | |||||
SCORE 59 Tenant improvement of office space. New non-bearing partitions, no str Permit type: Bldg-alter/repair | Permit status: Issued | Current use: Commercial | Permit id: 15016-10000-237 | |||||
SCORE 100 Office space t. I. Addition of (83) heads and relocate (59) heads. Al Date: December 26, 2013 Contractor: Jeff Pettitt Permit type: Fire sprinkler | Permit status: Permit finaled | Current use: Commercial | Permit id: 13043-10000-043 | |||||
SCORE 96 Hvac Date: February 24, 2016 Contractor: Clay Dunn Permit status: Permit finaled | Current use: Commercial | Permit id: 16044-90000-020 | |||||
SCORE 61 Electrical Date: August 18, 2015 Contractor: One Hundred Tow Permit status: Permit finaled | Current use: Commercial | Permit id: 15041-20000-269 | |||||
SCORE 100 Elevator Date: September 2, 2014 Contractor: Sharon Permit status: Permit finaled | Current use: Commercial | Permit id: 14046-10000-012 | |||||
SCORE 91 Interior ti on the 6th floor of an existing office building to include Permit type: Bldg-alter/repair | Permit status: Issued | Current use: Commercial | Permit id: 16016-10000-104 | |||||
SCORE 100 Tenant improvement to add and relocate sprinkler heads. Includes exte Date: June 23, 2016 Contractor: Jeff Pettitt Permit type: Fire sprinkler | Permit status: Issued | Current use: Commercial | Permit id: 16043-10000-028 | |||||
SCORE 100 Tenant improvement - non bearing partitions and renovation to public Permit type: Bldg-alter/repair | Permit status: Issued | Current use: Commercial | Permit id: 16016-10000-133 | |||||
SCORE 100 Ti on the 14th, 15th, and 30th floors to upgrade mens bathroom to be Permit type: Bldg-alter/repair | Permit status: Issued | Current use: Commercial | Permit id: 16016-10000-132 | |||||
SCORE 93 Supplemental permit to 16016-10000-035 to add 3 handrails to stairca Permit type: Bldg-alter/repair | Permit status: Issued | Current use: Commercial | Permit id: 16016-10001-035 | |||||
SCORE 99 Interior office ti for existing tenant space on the 27th floor. Work a Permit type: Bldg-alter/repair | Permit status: Issued | Current use: Commercial | Permit id: 16016-10000-152 | |||||
SCORE 93 Hvac Date: July 11, 2016 Contractor: Joseph Aisenson Permit status: Issued | Current use: Commercial | Permit id: 16044-90000-075 | |||||
SCORE 68 Ti: replace interior 2 offices door to office located on 41st floor s Permit type: Bldg-alter/repair | Permit status: Issued | Current use: Commercial | Permit id: 16016-30000-057 | |||||
SCORE 93 Construct new interconnecting stairs between 21st, 22nd and 23rd floor Permit type: Bldg-alter/repair | Permit status: Issued | Current use: Commercial | Permit id: 16016-10000-035 | |||||
SCORE 100 Hvac Date: May 10, 2016 Contractor: Russell Wright Permit status: Issued | Current use: Commercial | Permit id: 16044-10001-039 | |||||
SCORE 93 Electrical Date: July 25, 2016 Contractor: Charles Kirtland Permit status: Issued | Current use: Commercial | Permit id: 16041-90000-261 | |||||
SCORE 100 Electrical Date: August 11, 2016 Contractor: Ali Permit status: Issued | Current use: Commercial | Permit id: 16041-30000-285 | |||||
SCORE 98 Electrical Date: October 23, 2013 Contractor: R And R Electric Permit status: Permit finaled | Current use: Commercial | Permit id: 13041-10001-292 | |||||
SCORE 98 Electrical Date: April 15, 2015 Contractor: R And R Electric Permit status: Permit finaled | Current use: Commercial | Permit id: 15041-10000-112 | |||||
SCORE 93 Plumbing Date: December 2, 2015 Contractor: Muirchase Plumbing Co Inc Permit status: Permit finaled | Current use: Commercial | Permit id: 15042-10000-238 | |||||
SCORE 98 Electrical Date: May 21, 2014 Contractor: R And R Electric Permit status: Permit finaled | Current use: Commercial | Permit id: 14041-10000-135 | |||||
SCORE 98 Electrical Date: June 1, 2016 Contractor: R And R Electric Permit status: Issued | Current use: Commercial | Permit id: 16041-30000-192 | |||||
SCORE 93 Plumbing Date: February 8, 2016 Contractor: Muirchase Plumbing Co Inc Permit status: Permit finaled | Current use: Commercial | Permit id: 16042-10000-025 | |||||
SCORE 82 Electrical Date: June 16, 2014 Contractor: D And M Communications Inc Permit status: Permit expired | Current use: Commercial | Permit id: 14041-10000-159 | |||||
SCORE 93 Plumbing Date: January 8, 2014 Contractor: Muirchase Plumbing Co Inc Permit status: Permit finaled | Current use: Commercial | Permit id: 14042-10000-003 | |||||
SCORE 93 Plumbing Date: May 9, 2013 Contractor: Muirchase Plumbing Co Inc Permit status: Permit finaled | Current use: Commercial | Permit id: 12042-10002-192 | |||||
SCORE 93 Hvac Date: March 12, 2015 Contractor: Valley Wide Air Corporation Permit status: Permit finaled | Current use: Commercial | Permit id: 15044-20000-022 | |||||
SCORE 99 Plumbing Date: February 8, 2016 Contractor: Xcel Mechanical Systems Inc Permit status: Permit finaled | Current use: Commercial | Permit id: 16042-30000-025 | |||||
SCORE 75 Electrical Date: April 7, 2015 Contractor: Dove Communications Inc Permit status: Permit finaled | Current use: Commercial | Permit id: 15041-30000-102 | |||||
SCORE 100 Electrical Date: April 8, 2013 Contractor: Bergelectric Corp Permit status: Permit finaled | Current use: Commercial | Permit id: 13041-10000-088 | |||||
SCORE 95 Elevator Date: December 23, 2014 Contractor: Otis Elevator Company Permit status: Permit finaled | Current use: Commercial | Permit id: 14046-10000-018 | |||||
SCORE 93 Fire sprinkler Date: August 30, 2013 Contractor: Campbell Scott E Co Permit status: Permit finaled | Current use: Commercial | Permit id: 13043-10000-028 | |||||
SCORE 95 Electrical Date: April 5, 2013 Contractor: Tekworks Inc Permit status: Permit finaled | Current use: Commercial | Permit id: 13041-30000-087 | |||||
SCORE 76 Electrical Date: July 26, 2016 Contractor: Sonitrol Gold Coast L P Permit status: Permit finaled | Current use: Commercial | Permit id: 16041-10000-263 | |||||
SCORE 82 Electrical Date: October 17, 2016 Contractor: Rosie Diaz Permit status: Issued | Current use: Commercial | Permit id: 16041-90000-366 | |||||
SCORE 84 Tenant improvement non bearing partitions renovation to an existing p Permit type: Bldg-alter/repair | Permit status: Issued | Current use: Commercial | Permit id: 16016-10000-204 | |||||
SCORE 64 Electrical Date: September 27, 2016 Contractor: Ali Sheafat Permit status: Issued | Current use: Commercial | Permit id: 16041-30000-337 | |||||
SCORE 93 Electrical Date: October 13, 2016 Contractor: Sarah Catalan Permit status: Issued | Current use: Commercial | Permit id: 16041-10000-361 | |||||
SCORE 93 Ti to an existing office building Permit type: Bldg-alter/repair | Permit status: Issued | Current use: Commercial | Permit id: 16016-10000-231 | |||||
SCORE 100 Electrical Date: October 13, 2016 Contractor: Damian Catalan Permit status: Issued | Current use: Commercial | Permit id: 16041-10000-361 | |||||
SCORE 93 Pc for an existing fire alarm system for an existing high rise commerc Date: September 6, 2016 Contractor: Gabriel Juarez Permit type: Electrical | Permit status: Issued | Current use: Commercial | Permit id: 16041-10000-314 | |||||
SCORE 95 Electrical Date: October 19, 2016 Contractor: Simplexgrinnell Lp Permit status: Issued | Current use: Commercial | Permit id: 16041-10000-371 | |||||
SCORE 99 Tenant improvement in stairwell for floors 21 and 22. Adding and relo Date: August 16, 2016 Contractor: Jeff Pettit Permit type: Fire sprinkler | Permit status: Permit finaled | Current use: Commercial | Permit id: 16043-10000-037 | |||||
SCORE 59 Equipment anchorage with (n) footings, platform at (e) mechanic room ( Permit type: Bldg-alter/repair | Permit status: Issued | Current use: Commercial | Permit id: 16016-30000-188 | |||||
SCORE 59 Electrical Date: October 13, 2016 Contractor: Ali Sheruput Permit status: Issued | Current use: Commercial | Permit id: 16041-10000-361 | |||||
SCORE 89 Electrical Date: August 17, 2016 Contractor: Frank Crane Permit status: Permit finaled | Current use: Commercial | Permit id: 16041-90000-292 | |||||
SCORE 100 Plumbing Date: October 7, 2016 Contractor: Sherri Taylor Permit status: Issued | Current use: Commercial | Permit id: 16042-90000-217 | |||||
SCORE 93 Tenant improvement on 30th floor of commercial building. Relocating s Date: November 1, 2016 Contractor: Jonathan Garcia Permit type: Fire sprinkler | Permit status: Issued | Current use: Commercial | Permit id: 16043-10000-050 | |||||
SCORE 67 T. I. To existing office space at 12th floor Permit type: Bldg-alter/repair | Permit status: Permit finaled | Current use: Commercial | Permit id: 16016-10000-233 | |||||
SCORE 92 T. I. Enclose pantry with new wall & door in office. Permit type: Bldg-alter/repair | Permit status: Permit finaled | Current use: Commercial | Permit id: 16016-30000-211 | |||||
SCORE 100 Install two new glass doors in existing office space to create separat Permit type: Bldg-alter/repair | Permit status: Issued | Current use: Commercial | Permit id: 16016-10000-274 | |||||
SCORE 100 Elevator Date: August 12, 2016 Contractor: Sharon Green Permit status: Permit finaled | Current use: Commercial | Permit id: 16046-10000-012 | |||||
SCORE 95 Elevator Date: December 5, 2016 Contractor: Otis Elevator Company Permit status: Issued | Current use: Commercial | Permit id: 16046-10000-019 | |||||
SCORE 82 Electrical Date: December 2, 2016 Contractor: Maia Tryggestad Permit status: Issued | Current use: Commercial | Permit id: 16041-10000-424 | |||||
SCORE 100 Tenant improvement to (e) tenant space on 25th floor; non bearing part Permit type: Bldg-alter/repair | Permit status: Permit finaled | Current use: Commercial | Permit id: 16016-10000-204 | |||||
SCORE 92 625 s. F. Office t. I. New partition walls in open office, rework drywal Permit type: Bldg-alter/repair | Permit status: Permit finaled | Current use: Commercial | Permit id: 16016-30000-267 | |||||
SCORE 93 Fire sprinkler Date: December 19, 2016 Contractor: Campbell Scott E Co Permit status: Issued | Current use: Commercial | Permit id: 16043-10000-059 | |||||
SCORE 100 (n) 105" x 80" non illuminated monument sign Permit type: Sign | Permit status: Issued | Current use: Onsite | Permit id: 16048-20000-025 | |||||
SCORE 95 Electrical Date: January 18, 2013 Contractor: Simplexgrinnell Lp Permit status: Permit finaled | Current use: Commercial | Permit id: 13041-10000-013 | |||||
SCORE 93 Fire sprinkler Date: November 24, 2015 Contractor: Campbell Scott E Co Permit status: Permit finaled | Current use: Commercial | Permit id: 15043-10000-053 | |||||
SCORE 100 Electrical Date: September 26, 2013 Contractor: Obryant Electric Inc Permit status: Issued | Current use: Commercial | Permit id: 13041-20000-267 | |||||
SCORE 93 Electrical Date: January 26, 2016 Contractor: Bee Communications Inc Permit status: Issued | Current use: Commercial | Permit id: 16041-20000-027 | |||||
SCORE 76 Hvac Date: January 22, 2016 Contractor: Global Mechanical Systems Inc Permit status: Issued | Current use: Commercial | Permit id: 16044-20000-008 | |||||
SCORE 76 Hvac Date: December 4, 2015 Contractor: Global Mechanical Systems Inc Permit status: Permit finaled | Current use: Commercial | Permit id: 15044-20000-128 | |||||
SCORE 95 Elevator Date: December 10, 2013 Contractor: Otis Elevator Company Permit status: Permit finaled | Current use: Commercial | Permit id: 13046-10000-016 | |||||
SCORE 93 Interior nonstructural t. I. (4348 sf) to install new non bearing parti Permit type: Bldg-alter/repair | Permit status: Permit finaled | Current use: Commercial | Permit id: 13016-10000-031 | |||||
SCORE 86 Addition of one non-bearing partition on the 18th floor to enclose (e) Permit type: Bldg-alter/repair | Permit status: Permit finaled | Current use: Commercial | Permit id: 13016-10000-195 | |||||
SCORE 95 Elevator Date: August 12, 2015 Contractor: Otis Elevator Company Permit status: Permit finaled | Current use: Commercial | Permit id: 15046-10000-012 | |||||
SCORE 95 Fire sprinkler Date: July 10, 2015 Contractor: Cosco Fire Protection Inc Permit status: Permit finaled | Current use: Commercial | Permit id: 15043-10000-030 | |||||
SCORE 95 Fire sprinkler Date: January 16, 2013 Contractor: Cosco Fire Protection Inc Permit status: Permit finaled | Current use: Commercial | Permit id: 13043-10000-001 | |||||
SCORE 94 Electrical Date: January 8, 2016 Contractor: Pinnacle Communication Services Permit status: Issued | Current use: Commercial | Permit id: 16041-10000-006 | |||||
SCORE 59 Electrical Date: May 18, 2015 Contractor: A Comm Permit status: Permit finaled | Current use: Commercial | Permit id: 15041-10000-151 | |||||
SCORE 92 Electrical Date: May 17, 2016 Contractor: Assi Security Permit status: Issued | Current use: Commercial | Permit id: 16041-10000-172 | |||||
SCORE 96 Electrical Date: May 26, 2016 Contractor: Audio Visual Innovations Inc Permit status: Permit finaled | Current use: 1 or 2 family dwelling | Permit id: 16041-40000-185 | |||||
SCORE 97 Add 19 fan coil units and modify existing hvac system on 40, 41, and Date: January 8, 2013 Contractor: Air Tec Permit type: Hvac | Permit status: Permit finaled | Current use: Commercial | Permit id: 12044-10000-113 | |||||
SCORE 82 T. I. W/demo of non-load-bearing walls, new wall layout for new open of Permit type: Bldg-alter/repair | Permit status: Issued | Current use: Commercial | Permit id: 14016-10000-076 | |||||
SCORE 100 T. I. To existing commercial building on 3rd floor. Relocate 16 heads, Date: January 12, 2016 Contractor: Jeff Pettitt Permit type: Fire sprinkler | Permit status: Permit finaled | Current use: Commercial | Permit id: 16043-10000-001 | |||||
SCORE 99 Plumbing Date: January 5, 2017 Contractor: Xcel Mechanical Systems Inc Permit status: Issued | Current use: Commercial | Permit id: 17042-30000-001 | |||||
SCORE 66 T. I. W/ new non-structural partitions, millwork, new ceiling @ 26th fl Permit type: Bldg-alter/repair | Permit status: Permit finaled | Current use: Commercial | Permit id: 13016-10000-260 | |||||
SCORE 100 Plumbing Date: January 5, 2017 Contractor: Frank Borbon Permit status: Issued | Current use: Commercial | Permit id: 17042-30000-001 | |||||
SCORE 99 Relocate 5 and add 2 sprinkler heads on 15th floor Date: October 31, 2016 Contractor: Jeff Pettit Permit type: Fire sprinkler | Permit status: Permit finaled | Current use: Commercial | Permit id: 16043-10000-051 | |||||
SCORE 100 Tenant improvement to (e) tenant space on 25th floor; non bearing part Permit type: Bldg-alter/repair | Permit status: Permit finaled | Current use: Commercial | Permit id: 16016-10000-204 | |||||
SCORE 97 Hvac Date: January 23, 2014 Contractor: Air Tec Permit status: Permit finaled | Current use: Commercial | Permit id: 14044-70000-006 | |||||
SCORE 100 Interior renovation of existing elevator lobby (group b occupancy). Pr Permit type: Bldg-alter/repair | Permit status: Issued | Current use: Commercial | Permit id: 16016-10001-212 | |||||
SCORE 100 Interior renovation of exsiting office building 6th floor to inlcude n Permit type: Bldg-alter/repair | Permit status: Issued | Current use: Commercial | Permit id: 16016-10000-212 | |||||
SCORE 84 Tenant improvement non bearing partitions renovation to an existing p Permit type: Bldg-alter/repair | Permit status: Issued | Current use: Commercial | Permit id: 16016-10000-204 | |||||
SCORE 93 Interior renovation to include demolition of non-bearing interior part Permit type: Bldg-alter/repair | Permit status: Permit finaled | Current use: Commercial | Permit id: 14016-10000-180 | |||||
SCORE 89 Supplemental permit for deferred submittal of glass hand and guard rai Permit type: Bldg-alter/repair | Permit status: Permit expired | Current use: Commercial | Permit id: 12016-10002-177 | |||||
SCORE 86 Interior renovation / retrofit to public restrooms on 8th floor no str Permit type: Bldg-alter/repair | Permit status: Permit finaled | Current use: Commercial | Permit id: 16016-10000-050 | |||||
SCORE 100 Ti non structural mtl stud partitions, suspended grid/tile ceiling, mi Permit type: Bldg-alter/repair | Permit status: Issued | Current use: Commercial | Permit id: 15016-10000-281 | |||||
SCORE 99 Tenant improvement in suite 2750. Adding and relocating sprinkler head Date: July 19, 2016 Contractor: Jeff Pettit Permit type: Fire sprinkler | Permit status: Permit finaled | Current use: Commercial | Permit id: 16043-10000-032 | |||||
SCORE 100 Ti on the 14th, 15th, and 30th floors to upgrade mens bathroom to be Permit type: Bldg-alter/repair | Permit status: Issued | Current use: Commercial | Permit id: 16016-10000-132 | |||||
SCORE 99 Interior tenant improvement for private offices/support spaces. Full Permit type: Bldg-alter/repair | Permit status: Permit finaled | Current use: Commercial | Permit id: 15016-10000-059 | |||||
SCORE 59 Minor non-structural demo to add/modify 7-new offices; modify grid cei Permit type: Bldg-alter/repair | Permit status: Permit finaled | Current use: Commercial | Permit id: 15016-10000-163 | |||||
SCORE 100 Tenant improvement - non bearing partitions and renovation to public Permit type: Bldg-alter/repair | Permit status: Issued | Current use: Commercial | Permit id: 16016-10000-133 | |||||
SCORE 100 Replace and relocate 62 standard heads to extended coverage heads and Date: December 7, 2015 Contractor: Jeff Pettitt Permit type: Fire sprinkler | Permit status: Permit finaled | Current use: Commercial | Permit id: 15043-10000-055 | |||||
SCORE 100 T. I - installation of (19) new and (11) relocated fire sprinkler heads Date: February 22, 2016 Contractor: Jeff Pettitt Permit type: Fire sprinkler | Permit status: Permit finaled | Current use: Commercial | Permit id: 16043-10000-007 | |||||
SCORE 97 Hvac Date: December 4, 2015 Contractor: Air Tec Permit status: Permit finaled | Current use: Commercial | Permit id: 15044-10000-128 | |||||
SCORE 86 Electrical Date: September 27, 2016 Contractor: Anderson Audio Visual Irvine Lp Permit status: Permit finaled | Current use: Commercial | Permit id: 16041-40000-342 |