Content | Date | Cost | Contractor Rank | Address | Contractor |
---|---|---|---|---|---|
Basement interior build out to add a receiving area, prep space, refrigerated storage, clean up, dry storage, and other office related support areas. This work includes all electrical, mechanical, and plumbing renovation with tie in of a fire life safety and sprinkler changes. The first floor work includes, but is not limited to the interior build-out of the merchantile space with an accessory assembly cafe, sales floor and restrooms. This work includes but is not limited to electrical, mechanical, and plumbing required for the space. The space will have refrigerated cases and coolers, and a kitchen area for food preparation, complete with overhead exhaust hood and fire protection. Date: December 14, 2012 Applicant: Danielle Vogel | Permit type: Alteration and repai | Permit status: Completed | Permit id: B1300373 | |||||
The scope of work for this portion of the project is to clear the space and make safe. The work will include removal of most existing finishes, existing hvac units, electrical wiring, and low voltage systems. The sprinkler heads, where they exist, will be turned up and temporary construction lighting will be installed. After demolition is complete, a building/construction permit will be applied for. Date: September 6, 2012 Client: Danielle Glens Garden Market | Applicant: Danielle Glens Garden Market; Bob Wallace Danten Permit Service | Permit type: Demolition | Permit status: Permit issued | Permit id: D1201068 | |||||
Elevator cab interior upgrade estimated cost of work: 27,358. 00 Date: January 23, 2012 Client: Sylvan C Herman, Trustee | Applicant: Elevator Modernization Co. Inc | Permit type: Elevator - repair | Permit status: Permit issued | Permit id: Er1200464 | |||||
Electrical Date: December 28, 2012 Applicant: George Hockaday-Bey | Permit status: Completed | Permit id: E1302035 | |||||
5 floor sinks 1 gas generator 1 kehle hub drains Date: December 20, 2012 Applicant: Dominic E Totaro | Permit type: Plumbing and gas | Permit status: Completed | Permit id: P1301788 | |||||
At? T proposes to install 12 panel antennas on penthouse wall as well as an equipment platform on rooftop for radio cabinets and natural gas powered emergency generator. Date: November 5, 2013 Client: At?t 20th And S Asociates Llc | Applicant: William Stone | Permit type: Miscellaneous | Permit status: Permit issued | Permit id: An1300218 | |||||
An after hours permit is respectfully requested from 4am saturday thru 9pm sunday Date: August 1, 2013 Client: Crane Service Co | Applicant: Christine Long | Permit type: Miscellaneous | Permit status: Permit issued | Permit id: Ah1300781 | |||||
Day temp sign installed by ladder in front of building Date: April 17, 2013 Client: Glens Garden Market | Applicant: None; Audrey Expedite It Permits | Permit type: Sign | Permit status: Permit issued | Permit id: Sg1300245 | |||||
Boiler Date: August 20, 2013 Applicant: Thomas E. Cuddeback | Permit status: Permit issued | Permit id: Fb1300095 | |||||
After hours permit for b1110768, january 28 - february 28, 2012 from 7:00pm to 7:00am. Date: January 27, 2012 Applicant: 20th ? S Associates, Llc; Tanya Hill | Permit type: Miscellaneous | Permit status: Permit issued | Permit id: Ah1200235 | |||||
Electrical Date: August 28, 2012 Client: Sylvan C Herman, Trustee | Applicant: Mitchell W Lock; Mitchell W Lock | Permit status: Completed | Permit id: E1209082 | |||||
SCORE 96 Electrical Date: December 28, 2012 Contractor: George Hockadaybey Permit status: Completed | Permit id: E1302035 | |||||
SCORE 96 Mechanical Date: December 20, 2012 Contractor: Dominic E Totaro Permit status: Completed | Permit id: M1300564 | |||||
SCORE 96 Mechanical Date: August 17, 2012 Contractor: Bryan E Austin Client: Sylvan C Herman, Trustee | Permit status: Completed | Permit id: M1202703 | |||||
Plumbing and gas Date: January 31, 2012 Client: Sylvan C Herman, Trustee | Permit status: Permit issued | Permit id: P1202750 | |||||
SCORE 96 Boiler Date: August 20, 2013 Contractor: Thomas E. Cuddeback Permit status: Permit issued | Permit id: Fb1300095 | |||||
SCORE 96 Electrical Date: February 22, 2013 Contractor: David P. Lanzi Permit status: Completed | Permit id: E1303315 | |||||
SCORE 89 Electrical Date: January 8, 2013 Contractor: Francis Gleeson Permit status: Permit issued | Permit id: E1302222 | |||||
Plumbing and gas Date: January 24, 2013 Permit status: Completed | Permit id: P1302380 | |||||
Plumbing and gas Date: January 24, 2013 Permit status: Completed | Permit id: P1302389 | |||||
SCORE 96 Mechanical Date: January 8, 2013 Contractor: Timothy L Pepper Permit status: Permit issued | Permit id: M1300654 | |||||
SCORE 56 Day temp sign installed by ladder in front of building Date: April 17, 2013 Contractor: None Audrey Expedite It Permits Client: Glens Garden Market | Permit type: Sign | Permit status: Permit issued | Permit id: Sg1300245 | |||||
SCORE 96 Mechanical Date: December 20, 2012 Contractor: Dominic E Totaro Permit status: Completed | Permit id: M1300564 | |||||
SCORE 96 Mechanical Date: August 17, 2012 Contractor: Bryan E Austin Client: Sylvan C Herman, Trustee | Permit status: Completed | Permit id: M1202703 | |||||
SCORE 96 Electrical Date: December 28, 2012 Contractor: George Hockadaybey Permit status: Completed | Permit id: E1302035 | |||||
SCORE 89 Electrical Date: January 8, 2013 Contractor: Francis Gleeson Permit status: Permit issued | Permit id: E1302222 | |||||
SCORE 96 Electrical Date: February 22, 2013 Contractor: David P. Lanzi Permit status: Completed | Permit id: E1303315 | |||||
SCORE 96 Mechanical Date: January 8, 2013 Contractor: Timothy L Pepper Permit status: Permit issued | Permit id: M1300654 | |||||
Plumbing and gas Date: January 24, 2013 Permit status: Completed | Permit id: P1302380 | |||||
SCORE 96 Boiler Date: August 20, 2013 Contractor: Thomas E. Cuddeback Permit status: Permit issued | Permit id: Fb1300095 | |||||
SCORE 56 The scope of work for this portion of the project is to clear the space and make safe. The work will include removal of most existing finishes, existing hvac units, electrical wiring, and low voltage systems. The sprinkler heads, where they exist, will be turned up and temporary construction lighting will be installed. After demolition is complete, a building/construction permit will be applied for. Date: September 6, 2012 Client: Danielle Glens Garden Market | Permit type: Demolition | Permit status: Permit issued | Permit id: D1201068 | |||||
Plumbing and gas Date: January 31, 2012 Client: Sylvan C Herman, Trustee | Permit status: Permit issued | Permit id: P1202750 | |||||
SCORE 99 An after hours permit is respectfully requested from 4am saturday thru 9pm sunday Date: August 1, 2013 Contractor: Christine Long Client: Crane Service Co | Permit type: Miscellaneous | Permit status: Permit issued | Permit id: Ah1300781 | |||||
SCORE 99 At? T proposes to install 12 panel antennas on penthouse wall as well as an equipment platform on rooftop for radio cabinets and natural gas powered emergency generator. Date: November 5, 2013 Contractor: William Stone Client: At?t 20th And S Asociates Llc | Permit type: Miscellaneous | Permit status: Permit issued | Permit id: An1300218 | |||||
SCORE 56 Day temp sign installed by ladder in front of building Date: April 17, 2013 Contractor: None; Audrey Expedite It Permits Client: Glens Garden Market | Permit type: Sign | Permit status: Permit issued | Permit id: Sg1300245 | |||||
SCORE 56 Basement interior build out to add a receiving area, prep space, refrigerated storage, clean up, dry storage, and other office related support areas. This work includes all electrical, mechanical, and plumbing renovation with tie in of a fire life safety and sprinkler changes. The first floor work includes, but is not limited to the interior build-out of the merchantile space with an accessory assembly cafe, sales floor and restrooms. This work includes but is not limited to electrical, mechanical, and plumbing required for the space. The space will have refrigerated cases and coolers, and a kitchen area for food preparation, complete with overhead exhaust hood and fire protection. Date: December 14, 2012 Contractor: Danielle Vogel Permit type: Alteration and repair | Permit status: Completed | Permit id: B1300373 | |||||
SCORE 69 Elevator cab interior upgrade estimated cost of work: 27,358. 00 Date: January 23, 2012 Contractor: Elevator Modernization Co. Inc Client: Sylvan C Herman, Trustee | Permit type: Elevator - repair | Permit status: Permit issued | Permit id: Er1200464 | |||||
SCORE 96 Electrical Date: December 28, 2012 Contractor: George Hockadaybey Permit status: Completed | Permit id: E1302035 | |||||
Plumbing and gas Date: January 31, 2012 Client: Sylvan C Herman, Trustee | Permit status: Permit issued | Permit id: P1202750 | |||||
SCORE 96 5 floor sinks 1 gas generator 1 kehle hub drains Date: December 20, 2012 Contractor: Dominic E Totaro Permit type: Plumbing and gas | Permit status: Completed | Permit id: P1301788 | |||||
SCORE 96 Mechanical Date: August 17, 2012 Contractor: Bryan E Austin Client: Sylvan C Herman, Trustee | Permit status: Completed | Permit id: M1202703 | |||||
SCORE 96 Mechanical Date: December 20, 2012 Contractor: Dominic E Totaro Permit status: Completed | Permit id: M1300564 | |||||
SCORE 96 Boiler Date: August 20, 2013 Contractor: Thomas E. Cuddeback Permit status: Permit issued | Permit id: Fb1300095 | |||||
SCORE 89 Electrical Date: January 8, 2013 Contractor: Francis Gleeson Permit status: Permit issued | Permit id: E1302222 | |||||
SCORE 96 Electrical Date: February 22, 2013 Contractor: David P. Lanzi Permit status: Completed | Permit id: E1303315 | |||||
Plumbing and gas Date: January 24, 2013 Permit status: Completed | Permit id: P1302380 | |||||
Plumbing and gas Date: January 24, 2013 Permit status: Completed | Permit id: P1302389 | |||||
SCORE 96 Mechanical Date: January 8, 2013 Contractor: Timothy L Pepper Permit status: Permit issued | Permit id: M1300654 | |||||
SCORE 95 Replace counterweight safeties, counterweight & frame, butlers giller weigts, roller guides and recable on elevator 1 & 2 (est. Cost of work) 149,381. 00 Date: March 24, 2016 Contractor: Kone Inc Client: S C Herman & Assoc | Permit type: Elevator - repair | Permit status: Permit issued | Permit id: Er1601477 | |||||
SCORE 82 Replace existing hydraulic power unit (tank) with new. Replace existing jack assembly with new. This is a single unit. Estimated cost of work : 34,000. 00 Date: April 19, 2016 Contractor: Robert C. Felter Permit type: Elevator - repair | Permit status: Permit issued | Permit id: Er1601187 | |||||
SCORE 56 The scope of work for this portion of the project is to clear the space and make safe. The work will include removal of most existing finishes, existing hvac units, electrical wiring, and low voltage systems. The sprinkler heads, where they exist, will be turned up and temporary construction lighting will be installed. After demolition is complete, a building/construction permit will be applied for. Date: September 6, 2012 Client: Danielle Glens Garden Market | Permit type: Demolition | Permit status: Permit issued | Permit id: D1201068 | |||||
SCORE 59 After hours permit for b1110768, january 28 - february 28, 2012 from 7:00pm to 7:00am. Date: January 27, 2012 Contractor: 20th S Associates Llc; Tanya Hill Permit type: Miscellaneous | Permit status: Permit issued | Permit id: Ah1200235 | |||||
SCORE 56 After hours permit for b1110768, january 28 - february 28, 2012 from 7:00pm to 7:00am. Date: January 27, 2012 Contractor: 20th S Associates Llc Tanya Hill Permit type: Miscellaneous | Permit status: Permit issued | Permit id: Ah1200235 | |||||
SCORE 59 After hours permit for b1110768, january 28 - february 28, 2012 from 7:00pm to 7:00am. Date: January 27, 2012 Contractor: 20th S Associates Llc; Tanya Hill Permit type: Miscellaneous | Permit status: Permit issued | Permit id: Ah1200235 | |||||
SCORE 56 After hours permit for b1110768, january 28 - february 28, 2012 from 7:00pm to 7:00am. Date: January 27, 2012 Contractor: 20th S Associates, Llc; Tanya Hill Permit type: Miscellaneous | Permit status: Permit issued | Permit id: Ah1200235 | |||||
SCORE 59 Electrical Date: August 28, 2012 Contractor: Mitchell W Lock; Mitchell W Lock Client: Sylvan C Herman, Trustee | Permit status: Completed | Permit id: E1209082 | |||||
SCORE 56 Electrical Date: August 28, 2012 Contractor: Mitchell W Lock Mitchell W Lock Client: Sylvan C Herman, Trustee | Permit status: Completed | Permit id: E1209082 | |||||
SCORE 59 Electrical Date: August 28, 2012 Contractor: Mitchell W Lock; Mitchell W Lock Client: Sylvan C Herman, Trustee | Permit status: Completed | Permit id: E1209082 |