Content | Date | Cost | Contractor Rank | Address | Contractor |
---|---|---|---|---|---|
SCORE 100 Sewer connection for new sfd Date: January 21, 2014 Contractor: Wilcox And Wilcox U S A Corp Engineer: N, A | Applicant: Wilcox And Wilcox | Permit status: Finaled | Completion date: April 10, 2014 | Expiration date: January 21, 2015 | Permit id: 1401210025 | |||||
SCORE 99 Elect for roof-mounted pv sys 2. 3 kw, panels, 131. 31 sf Date: October 22, 2013 Contractor: Unpower Corporation Systems Engineer: William Thomas Kelley | Applicant: Sunpower Corp | Permit status: Finaled | Completion date: April 10, 2014 | Expiration date: October 22, 2014 | Permit id: 1310210054 | |||||
New sfd/gar/por/outdoor rm plan 4x cr 2,514/639/50/241 sf Date: September 19, 2013 Value: $495,000 Engineer: Woodley Architectural Group | Applicant: Same As Owner | Permit status: Finaled | Completion date: April 10, 2014 | Expiration date: September 19, 2014 | Permit id: 1308300005 | |||||
SCORE 99 New roof-mounted pv sys 2. 3 kw, panels, 131. 31 sq ft Engineer: William Thomas Kelley | Applicant: Sunpower Corp | Permit status: Finaled | Completion date: April 10, 2014 | Expiration date: October 22, 2014 | Permit id: 1310210104 | |||||
New sfd gar por outdoor rm plan 4x cr 2,514 639 50 241 sf Date: September 19, 2013 Value: $495,000 Engineer: Woodley Architectural Group | Applicant: Same As Owner | Permit status: Finaled | Completion date: April 10, 2014 | Expiration date: September 19, 2014 | Permit id: 1308300005 |