Electrical permit Date: March 28, 2016 Client: Fei Hong | Permit status: Expired | Permit id: 679181 | |||||
Alteration permit Date: February 18, 2016 Client: Fei Hong | Permit status: Completed | Permit id: 631124 | |||||
Zoning permit Date: January 13, 2016 Client: Fei Hong | Permit status: Completed | Permit id: 649548 | |||||
Mechanical permit Date: April 25, 2016 Client: Fei Hong | Permit status: Completed | Permit id: 686626 | |||||
Addition permit Date: March 24, 2016 Client: Fei Hong | Permit status: Active | Permit id: 667090 | |||||
Demolition permit Date: April 30, 2015 Client: Fei Hong | Permit status: Expired | Permit id: 606666 | |||||
Plumbing permit Date: March 29, 2016 Client: Fei Hong | Permit status: Completed | Permit id: 679830 | |||||
Addition permit Date: March 24, 2016 Client: Fei Hong | Permit status: Expired | Permit id: 667090 | |||||
Electrical permit Date: March 28, 2016 Client: Fei Hong | Permit status: Expired | Permit id: 679181 | |||||
Zoning permit Date: January 13, 2016 Client: Fei Hong | Permit status: Completed | Permit id: 649548 | |||||
Mechanical permit Date: April 25, 2016 Client: Fei Hong | Permit status: Completed | Permit id: 686626 | |||||
Plumbing permit Date: March 29, 2016 Client: Fei Hong | Permit status: Completed | Permit id: 679830 | |||||
Alteration permit Date: February 18, 2016 Client: Fei Hong | Permit status: Completed | Permit id: 631124 | |||||
Demolition permit Date: April 30, 2015 Client: Fei Hong | Permit status: Active | Permit id: 606666 | |||||
SCORE 89 Total rewiring and new 100amp service with all necessary bonding and ground per 2008 nec (sfd)south district Date: March 28, 2016 Contractor: D And R Company Electric Llc Client: Edwards Douglas V Feuer-Edwards Ashley L | Permit type: Electrical permit | Permit status: Completed | Completion date: April 10, 2017 | Permit id: 679181 | |||||
SCORE 100 Install water and drain lines for 2 wc, 2 lav, 1 tub, 1 ks, 1 dw, 1 wm. The installation will comply with the philadephia plubming code 2004 Date: March 29, 2016 Contractor: Shegda Construction Corp Client: Edwards Douglas V Feuer-Edwards Ashley L | Permit type: Plumbing permit | Permit status: Completed | Completion date: July 30, 2016 | Permit id: 679830 | |||||
SCORE 89 Install 1 hvac unit with ductwork (sfd) Date: April 25, 2016 Contractor: Lcd Heating And Air Conditioning Client: Edwards Douglas V Feuer-Edwards Ashley L | Permit type: Mechanical permit | Permit status: Completed | Completion date: July 13, 2016 | Permit id: 686626 | |||||
SCORE 82 Interior demo of non-load bearing walls only,no structural work on this permit Date: April 30, 2015 Contractor: Dante Reeves Client: Edwards Douglas V Feuer-Edwards Ashley L | Permit type: Demolition permit | Permit status: Expired | Completion date: January 23, 2017 | Permit id: 606666 | |||||
SCORE 99 Temporary shoring of interior load bearing floor joists per submitted plan. No other work permitted under this permit. Separate zoning and building permit required for reconstruction of rear wall and interior exterior alterations throughout. Date: February 18, 2016 Contractor: D R Builders 35 Llc Client: Edwards Douglas V Feuer-Edwards Ashley L | Permit type: Alteration permit | Permit status: Completed | Completion date: July 13, 2016 | Permit id: 631124 | |||||
SCORE 99 For the construction of a rear two story addition to an existing sfd as per plans. Separate permits require for all mechanical,electrical and plumbing work. Date: March 24, 2016 Contractor: D R Builders 35 Llc Client: Edwards Douglas V Feuer-Edwards Ashley L | Permit type: Addition permit | Permit status: Expired | Completion date: June 29, 2016 | Permit id: 667090 |