Content | Date | Cost | Contractor Rank | Address | Contractor |
---|---|---|---|---|---|
Electrical permit Date: July 25, 2014 Client: Septa | Client Company: G Maier | Permit status: Expired | Permit id: 546406 | |||||
Zoning permit Date: August 5, 2014 Client: Septa | Client Company: G Maier | Permit status: Completed | Permit id: 547597 | |||||
Demolition permit Date: August 5, 2014 Client: Septa | Client Company: G Maier | Permit status: Completed | Permit id: 547602 | |||||
Suppression permit Date: August 22, 2011 Client: Septa | Client Company: G Maier | Permit status: Completed | Permit id: 339067 | |||||
Suppression permit Date: February 23, 2007 Client: Septa | Client Company: G Maier | Permit status: Completed | Permit id: 47739 | |||||
Demolition permit Date: August 5, 2014 Client: Septa | Client Company: G Maier | Permit status: Completed | Permit id: 547602 | |||||
Suppression permit Date: February 23, 2007 Client: Septa | Client Company: G Maier | Permit status: Completed | Permit id: 47739 | |||||
Zoning permit Date: August 5, 2014 Client: Septa | Client Company: G Maier | Permit status: Completed | Permit id: 547597 | |||||
Suppression permit Date: August 22, 2011 Client: Septa | Client Company: G Maier | Permit status: Completed | Permit id: 339067 | |||||
Electrical permit Date: July 25, 2014 Client: Septa | Client Company: G Maier | Permit status: Expired | Permit id: 546406 | |||||
SCORE 100 Add heads to provide coverage in loft area Date: August 22, 2011 Contractor: Precision Sprinkler Services Client: Septa | Client Company: G Maier | Permit type: Suppression permit | Permit status: Completed | Completion date: May 4, 2012 | Permit id: 339067 | |||||
SCORE 100 Install 2-new boilers, removal existing branch ckts, lights & disconnection of failed boilers, furnish new lighting, branch ckts out exist elec pnls as per nec 2008 (septa bus garage) south district Date: July 25, 2014 Contractor: Nucero Electrical Const Co Inc Client: Septa | Client Company: G Maier | Permit type: Electrical permit | Permit status: Expired | Completion date: July 25, 2014 | Permit id: 546406 | |||||
SCORE 100 For the complete demolition of an existing smoke stack. No change in height, area or use of any other existing structures on lot. Date: August 5, 2014 Contractor: Jpc Group Inc Client: Septa | Client Company: G Maier | Permit type: Zoning permit | Permit status: Completed | Completion date: August 5, 2014 | Permit id: 547597 | |||||
SCORE 100 Replacing extg. Damaged sprinkler heads and piping, as per plans. Date: February 23, 2007 Contractor: Fire Tech Automatic Client: Septa | Client Company: G Maier | Permit type: Suppression permit | Permit status: Completed | Completion date: August 21, 2007 | Permit id: 47739 | |||||
SCORE 100 For the complete demolition of masonry smoke stack. Demolition in accordance with department code bulletin b-1302. All work above 15 ft in height to be done by hand per submitted engineers report. Protection of pedestrians and adjacent structures to be maintained during all demolition activities. Date: August 5, 2014 Contractor: Jpc Group Inc Client: Septa | Client Company: G Maier | Permit type: Demolition permit | Permit status: Completed | Completion date: June 9, 2015 | Permit id: 547602 | |||||
SCORE 100 Alteration: site plumbing for a septa depot. The installation includes (2) 18" storm laterals, (10) catch basins, (2) trench drains and (1) rain leader. The installation shall comply with the philadelphia plumbing code, 2004. Date: June 2, 2017 Contractor: John J Bee,Inc Client: Septa | Client Company: G Maier | Permit type: Plumbing permit | Permit status: Active | Completion date: October 4, 2017 | Permit id: 779869 |