Content | Date | Cost | Contractor Rank | Address | Contractor |
---|---|---|---|---|---|
Mechanical permit Date: April 3, 2013 Client: Xu Xuandian | Permit status: Completed | Permit id: 462730 | |||||
Zoning/use permit Date: November 5, 2012 Client: Xu Xuandian | Permit status: Completed | Permit id: 433740 | |||||
New construction permit Date: January 15, 2013 Client: Xu Xuandian | Permit status: Completed | Permit id: 439789 | |||||
Electrical permit Date: May 3, 2013 Client: Xu Xuandian | Permit status: Completed | Permit id: 463429 | |||||
Plumbing permit Date: March 12, 2013 Client: Xu Xuandian | Permit status: Completed | Permit id: 458429 | |||||
Suppression permit Date: December 11, 2013 Client: Xu Xuandian | Permit status: Completed | Permit id: 465444 | |||||
Suppression permit Date: December 11, 2013 Client: Xu Xuandian | Permit status: Completed | Permit id: 465444 | |||||
Plumbing permit Date: March 28, 2013 Client: Xu Xuandian | Permit status: Completed | Permit id: 447704 | |||||
Mechanical permit Date: April 3, 2013 Client: Xu Xuandian | Permit status: Completed | Permit id: 462730 | |||||
Electrical permit Date: May 3, 2013 Client: Xu Xuandian | Permit status: Completed | Permit id: 463429 | |||||
New construction permit Date: January 15, 2013 Client: Xu Xuandian | Permit status: Completed | Permit id: 439789 | |||||
Zoning use permit Date: November 5, 2012 Client: Xu Xuandian | Permit status: Completed | Permit id: 433740 | |||||
For the erection of a new three (3) story structure with cellar. Separate sprinkler, plumbing, electrical, and mechanical permits required. Date: January 15, 2013 Client: Xuandian, Xu | Permit type: New construction permit | Permit status: Completed | Completion date: December 23, 2013 | Permit id: 439789 | |||||
SCORE 100 Install new fire suppression system and 2" service in accordance with nfpa 13 & 13r throughout the entire building. All work shall comply with the approved plans. All work shall be performed by a fire suppression contractor licensed by the city of philadelphia. Date: December 11, 2013 Contractor: B. M. Consulting Services Inc Client: Xuandian, Xu | Permit type: Suppression permit | Permit status: Completed | Completion date: January 27, 2014 | Permit id: 465444 | |||||
SCORE 98 600amp service wiring throughout and fire alarm per 2008 nec & nfpa 72 (mixed use) Date: August 8, 2013 Contractor: David Bell Client: Xuandian, Xu | Permit type: Electrical permit | Permit status: Completed | Completion date: December 10, 2013 | Permit id: 480538 | |||||
SCORE 100 Installing 2-3 4" water service and 5" sewer line and 4" fresh air inlet pa20130670989 (mixed use) Date: March 12, 2013 Contractor: Tommys Plumbing Client: Xuandian, Xu | Permit type: Plumbing permit | Permit status: Completed | Completion date: December 23, 2013 | Permit id: 458429 | |||||
SCORE 100 Install 3 heatpumps(mixed use) Date: April 3, 2013 Contractor: Talgar Inc Client: Xuandian, Xu | Permit type: Mechanical permit | Permit status: Completed | Completion date: December 23, 2013 | Permit id: 462730 | |||||
New construction of a (3) story building with cellar to use as household living for (4) dwelling units throughout 1st through 3rd floor levles and inhouse office on first floor at front. - given to jeanne klinger for audit will approve after confirmation Date: November 5, 2012 Client: Xuandian, Xu | Permit type: Zoning/use permit | Permit status: Completed | Completion date: July 19, 2013 | Permit id: 433740 | |||||
SCORE 97 25 fixtures, house drain, stack, and 6 hwh(mixed use) Date: March 28, 2013 Contractor: Richard Lawrence Client: Xuandian, Xu | Permit type: Plumbing permit | Permit status: Completed | Completion date: December 23, 2013 | Permit id: 447704 | |||||
SCORE 100 Fire panel, 11 horns, 2 horn strobes, tamper & flow, 1 smoke, 2 pull stations as per 2008 nec & nfpa 72 (multifamily) Date: May 3, 2013 Contractor: B H Holding Company Client: Xuandian, Xu | Permit type: Electrical permit | Permit status: Completed | Completion date: January 7, 2014 | Permit id: 463429 |