Content | Date | Cost | Contractor Rank | Address | Contractor |
---|---|---|---|---|---|
SCORE 100 Construction of 238 unit apartment building (the residences at 29th street). To include below grade parking structure, and leasing office. Pool by seperate permit. (tco was issued for clubhouse) (phase 1-garage) tco-phase 2-building 1 1925 30th) (tco-phase 3-building 2 1955 30th)(phase 4-building 3 1975 30th) Client: Level 2nd | Applicant: Milender White Construction Company | Permit type: Building, electrical | Permit status: Co | Current use: Parking garage, | |||||
SCORE 100 Bore 334foot, trench & backfill 490foot & set 2 transformers Date: December 23, 2009 Contractor: Xcel Energy Client: Level 2nd | Applicant: Xcel Energy | Permit type: Right-of-way | Permit status: Iss | |||||
SCORE 100 Grading permit for the residences at 29th street. 55,0 cubic yards. See specifics in tec2009-00012 Date: January 14, 2010 Contractor: Milender White Construction Company Client: Level 2nd | Applicant: Milender White Construction Company | Permit type: Grading | Permit status: N&v | |||||
SCORE 89 Construction of relocated water, sanitary and storm sewer mains and a stormcepter. Installation of (2) new fire hydrants and 6inch fire service. New 4inch domestic service, 3 4inch irrigation and (2) 6inch sanitary services, {(1) is pool outfall only} initial phase utility work northwest end of prop. Only! Date: February 26, 2010 Contractor: R And D Pipeline Construction Inc Client: Level 2nd | Applicant: R & D Pipeline Construction, Inc | Permit type: Fire, water, wastewa | Permit status: Iss | |||||
SCORE 100 Reroute exixsting gas main for 29th st residence Date: March 9, 2010 Contractor: Xcel Energy Client: Level 2nd | Applicant: Xcel Energy | Permit type: Right-of-way | Permit status: Iss | |||||
SCORE 89 Night time road closure on 30th adjacent to the residences @ 29th street site. Closure to be limited to 9:00pm-6:30am - several occasions all closures must be coordinated with transportation projects and traffic operations Date: September 9, 2010 Contractor: R And D Pipeline Construction Inc Client: Level 2nd | Applicant: R & D Pipeline Construction, Inc | Permit type: Right-of-way | Permit status: Iss | |||||
SCORE 95 New sprinkler system for residences at 29th st Date: September 15, 2010 Contractor: Western States Fire Protection Client: Level 2nd | Applicant: Western States Fire Protection | Permit type: Fire | Permit status: Cmp | Completion date: November 30, 2011 | Current use: Multifamily dwe | |||||
SCORE 100 Installing gas service. Open trench 25foot Date: November 29, 2010 Contractor: Xcel Energy Client: Level 2nd | Applicant: Xcel Energy | Permit type: Right-of-way | Permit status: Iss | |||||
SCORE 100 Close walk along 30th for 3 months Date: February 10, 2011 Contractor: Milender White Construction Company Client: Level 2nd | Applicant: Milender White Construction Company | Permit type: Right-of-way | Permit status: Iss | |||||
SCORE 100 Crane set up in 30th & walnut to take down tower crane sat. 2-12 or sun. 2-13 Date: February 10, 2011 Contractor: Milender White Construction Company Client: Level 2nd | Applicant: Milender White Construction Company | Permit type: Right-of-way | Permit status: Iss | |||||
SCORE 100 Occupancy for crane disassembly and removal. Close and reroute multi-use path Date: April 20, 2011 Contractor: Milender White Construction Company Client: Level 2nd | Applicant: Milender White Construction Company | Permit type: Right-of-way | Permit status: Iss | |||||
SCORE 97 Sitework improvements as per approved tec-doc. To include c&g, sidewalk, drivepans, crosspan Date: April 18, 2011 Contractor: Thoutt Bros Concrete Contract Inc Client: Level 2nd | Applicant: Thoutt Bros Concrete Contract Inc | Permit type: Right-of-way | Permit status: Iss | |||||
SCORE 100 Install new pad and box in util easement for telecom svc to residences @ 29th. Trench from existing mh6113 in walnut (public access easement) to pad location Date: May 31, 2011 Contractor: Qwest Comm Centurylink Client: Level 2nd | Applicant: Qwest Comm/centurylink | Permit type: Right-of-way | Permit status: Iss | |||||
SCORE 72 Construction of 459 square foot covered outdoor kitchen for the residences at 29th street. See lur2008-00063 for site review approval. Client: Level 2nd | Applicant: Concrete Concepts Of The Rockies | Permit type: Building, electrical | Permit status: Cmp | Completion date: October 17, 2011 | Current use: Multifamily dwe | |||||
SCORE 100 Installation of a 91 kw solar array, with a 15 degree angle of tilt on roof of existing apartment building Date: September 6, 2011 Contractor: Douglass Colony Group Inc Client: Level 2nd | Applicant: Douglass Colony Group, Inc | Permit type: Photovoltaic | Permit status: Cmp | Completion date: February 1, 2012 | Current use: Multifamily dwe | |||||
SCORE 100 Install conductor through existing conduit from cabinet to transformer. All work and vehicles will be out of row. Date: September 29, 2011 Contractor: Xcel Energy Client: Level 2nd | Applicant: Xcel Energy | Permit type: Right-of-way | Permit status: Iss | Current use: Multifamily dwe | |||||
SCORE 100 Stock roof with pv materials with crane. (notice: walnut st w of 30th not city row. Must have macerich ok for any traffic impact.) Date: October 10, 2011 Contractor: Douglass Colony Group Inc Client: Level 2nd | Applicant: Douglass Colony Group Inc | Permit type: Right-of-way | Permit status: Iss | Current use: Multifamily dwe | |||||
SCORE 100 Construction of 238 unit apartment building (the residences at 29th street). To include below grade parking structure, and leasing office. Pool by seperate permit. (tco was issued for clubhouse) (phase 1-garage) tco-phase 2-building 1 1925 30th) (tco-phase 3-building 2 1955 30th)(phase 4-building 3 1975 30th) Client: Level | Permit type: Building, electrical, mechanical, plumbing, fire, water, wastewater, flood not required, sitework | Permit status: Co | Current use: Parking garage, new, multifamily dwellin | Permit id: Pmt2009-03940 | |||||
Bore 334foot, trench & backfill 490foot & set 2 transformers Date: December 23, 2009 Client: Level | Permit type: Right-of-way | Permit status: Iss | Permit id: Pmt2009-04800 | |||||
SCORE 99 Construction of relocated water, sanitary and storm sewer mains and a stormcepter. Installation of (2) new fire hydrants and 6inch fire service. New 4inch domestic service, 3 4inch irrigation and (2) 6inch sanitary services, {(1) is pool outfall only} initial phase utility work northwest end of prop. Only! Date: February 26, 2010 Contractor: R And D Pipeline Construction, Inc Client: Level | Permit type: Fire, water, wastewater, right-of-way | Permit status: Iss | Permit id: Pmt2010-00522 | |||||
Reroute exixsting gas main for 29th st residence Date: March 9, 2010 Client: Level | Permit type: Right-of-way | Permit status: Iss | Permit id: Pmt2010-00640 | |||||
SCORE 99 Night time road closure on 30th adjacent to the residences @ 29th street site. Closure to be limited to 9:00pm-6:30am - several occasions all closures must be coordinated with transportation projects and traffic operations Date: September 9, 2010 Contractor: R And D Pipeline Construction, Inc Client: Level | Permit type: Right-of-way | Permit status: Iss | Permit id: Pmt2010-03829 | |||||
SCORE 95 New sprinkler system for residences at 29th st Client: Level | Permit type: Fire | Permit status: Cmp | Completion date: November 30, 2011 | Current use: Multifamily dwellings, existing | Permit id: Pmt2010-03891 | |||||
Installing gas service. Open trench 25foot Date: November 29, 2010 Client: Level | Permit type: Right-of-way | Permit status: Iss | Permit id: Pmt2010-04707 | |||||
Install new pad and box in util easement for telecom svc to residences @ 29th. Trench from existing mh6113 in walnut (public access easement) to pad location Date: May 31, 2011 Client: Level | Permit type: Right-of-way | Permit status: Iss | Permit id: Pmt2011-02070 | |||||
SCORE 72 Construction of 459 square foot covered outdoor kitchen for the residences at 29th street. See lur2008-00063 for site review approval. Client: Level | Permit type: Building, electrical, mechanical, plumbing | Permit status: Cmp | Completion date: October 17, 2011 | Current use: Multifamily dwellings, existing, patio c | Permit id: Pmt2011-02293 | |||||
SCORE 88 Installation of a 91 kw solar array, with a 15 degree angle of tilt on roof of existing apartment building Client: Level | Permit type: Photovoltaic | Permit status: Cmp | Completion date: February 1, 2012 | Current use: Multifamily dwellings, existing | Permit id: Pmt2011-03551 | |||||
Install conductor through existing conduit from cabinet to transformer. All work and vehicles will be out of row. Date: September 29, 2011 Client: Level | Permit type: Right-of-way | Permit status: Iss | Current use: Multifamily dwellings, existing | Permit id: Pmt2011-04032 | |||||
SCORE 100 Stock roof with pv materials with crane. (notice: walnut st w of 30th not city row. Must have macerich ok for any traffic impact.) Date: October 10, 2011 Contractor: Douglass Colony Group Inc Client: Level | Permit type: Right-of-way | Permit status: Iss | Current use: Multifamily dwellings, existing | Permit id: Pmt2011-04320 | |||||
SCORE 70 Demolition permit to remove planters and non-structural brick walls per approved plan a1-3. Reference adr2016-00297. Date: April 12, 2017 Contractor: Harmon Renovations Client: Nine Two | Permit type: Demolition | Permit status: Iss | Current use: Multifamily dwellings, existing | Permit id: Pmt2017-01455 | |||||
SCORE 96 Close walk along 30th for 3 months Date: February 10, 2011 Contractor: Milender White Client: Level | Permit type: Right-of-way | Permit status: Iss | Permit id: Pmt2011-00533 | |||||
SCORE 96 Crane set up in 30th & walnut to take down tower crane sat. 2-12 or sun. 2-13 Date: February 10, 2011 Contractor: Milender White Client: Level | Permit type: Right-of-way | Permit status: Iss | Permit id: Pmt2011-00534 | |||||
SCORE 96 Occupancy for crane disassembly and removal. Close and reroute multi-use path Date: April 20, 2011 Contractor: Milender White Client: Level | Permit type: Right-of-way | Permit status: Iss | Permit id: Pmt2011-01457 |