Content | Date | Cost | Contractor Rank | Address | Contractor |
---|---|---|---|---|---|
SCORE 100 In will call contractors signature and fees paid glass replacement on exterior Date: September 1, 2015 Contractor: Bigd Construction Corp Permit type: Permit | Permit status: Accepted - standard | Completion date: September 1, 2015 | Current use: Commercial | Permit id: Bld2015-07062 | |||||
SCORE 100 Interior remodel plus cut out and install 8 windows on exterior of building, patch exterior. Electrical permit required. Date: August 10, 2015 Contractor: Bigd Construction Corp Permit type: Permit | Permit status: Completed | Completion date: August 12, 2015 | Current use: Commercial | Permit id: Bld2015-06325 | |||||
SCORE 70 Replacement of existing building envelope, landscaping and extended existing entrance lobby 725 sq ft Date: June 29, 2015 Contractor: Ffkr Architects Permit type: Permit | Permit status: Corrections required | Completion date: August 19, 2015 | Current use: Commercial | Permit id: Bld2015-04779 | |||||
SCORE 70 Install 2 incinerators. Plans submitted for review. Plans on don davies desk for review and routing. Date: June 26, 2015 Contractor: Ffkr Architects Permit type: Mechanical | Permit status: Reviews not require | Completion date: June 26, 2015 | Current use: Commercial | Permit id: Bld2015-04701 | |||||
SCORE 95 Flat sign Date: June 22, 2015 Contractor: Yesco Llc Permit type: Sign | Permit status: Accepted - standard | Completion date: June 22, 2015 | Current use: Na | Permit id: Bld2015-04489 | |||||
SCORE 99 Sprinklers Date: January 23, 2015 Contractor: Chaparral Fire Protection Inc Permit type: Fire | Permit status: Pass | Completion date: April 23, 2015 | Current use: Commercial | Permit id: Bld2015-00492 | |||||
SCORE 56 Fire alarm installation Date: January 19, 2015 Contractor: O.C. Tanner Sw Addition Wp 2 Permit type: Low voltage | Permit status: Corrections required | Completion date: January 27, 2015 | Current use: Commercial | Permit id: Bld2015-00352 | |||||
SCORE 100 Fire sprinklers Date: November 5, 2014 Contractor: Fire Engineering Company Inc Permit type: Fire | Permit status: Completed | Completion date: November 7, 2014 | Current use: Commercial | Permit id: Bld2014-08124 | |||||
SCORE 99 Electrical remodel & site Date: October 27, 2014 Contractor: Taylor Electric Permit type: Electrical | Permit status: Reviews not require | Completion date: October 27, 2014 | Current use: Commercial | Permit id: Bld2014-07800 | |||||
SCORE 100 Install (40) fixtures, (1) water heater, (1) distribution piping, (1) gas piping for remodel Date: September 26, 2014 Contractor: Alternative Mechanical Contractors Inc Permit type: Plumbing | Permit status: On-line ready | Completion date: September 26, 2014 | Current use: Commercial | Permit id: Bld2014-07032 | |||||
SCORE 99 Temp service Date: August 14, 2014 Contractor: Taylor Electric Permit type: Electrical | Permit status: Completed | Completion date: August 14, 2014 | Current use: Commercial | Permit id: Bld2014-05900 | |||||
SCORE 100 Refinery loading dock addition Date: May 7, 2014 Contractor: Bigd Construction Corp Permit type: Permit | Permit status: Pass | Completion date: September 4, 2014 | Current use: Commercial | Permit id: Bld2014-03113 | |||||
SCORE 100 Fire sprinklers Date: April 15, 2014 Contractor: Fire Engineering Company Inc Permit type: Fire | Permit status: Completed | Completion date: May 15, 2014 | Current use: Commercial | Permit id: Bld2014-02450 | |||||
SCORE 100 17,0 square feet single story plus mezzanine remodel. Date: April 11, 2014 Contractor: Bigd Construction Corp Permit type: Permit | Permit status: Pass | Completion date: September 4, 2014 | Current use: Commercial | Permit id: Bld2014-02412 | |||||
SCORE 100 Addition of sump to existing sewer system. Date: January 16, 2014 Contractor: Bigd Construction Corp Permit type: Permit | Permit status: Completed | Completion date: March 18, 2014 | Current use: Commercial | Permit id: Bld2014-00312 | |||||
SCORE 100 Southwest entry remodel & west loading dock remodel. Work package #1 of 2 Date: January 15, 2014 Contractor: Bigd Construction Corp Permit type: Permit | Permit status: Pass | Completion date: September 4, 2014 | Current use: Commercial | Permit id: Bld2014-00260 | |||||
Glass replacement on exterior Date: September 1, 2015 Permit type: Permit | Permit status: Completed | Completion date: September 8, 2015 | Current use: Commercial | Permit id: Bld2015-07062 | |||||
Interior remodel plus cut out and install 8 windows on exterior of building, patch exterior. Electrical permit required. Date: August 10, 2015 Permit type: Permit | Permit status: Completed | Completion date: August 12, 2015 | Current use: Commercial | Permit id: Bld2015-06325 | |||||
Replacement of existing building envelope, landscaping and extended existing entrance lobby 725 sq ft Date: June 29, 2015 Permit type: Permit | Permit status: Completed | Completion date: October 5, 2015 | Current use: Commercial | Permit id: Bld2015-04779 | |||||
SCORE 64 Install 2 incinerators. Plans submitted for review. Plans on don davies desk for review and routing. Date: June 26, 2015 Contractor: Ffkr Architectsoc Tanner Dock Permit type: Mechanical | Permit status: On-line ready | Completion date: June 26, 2015 | Current use: Commercial | Permit id: Bld2015-04701 | |||||
Sprinklers Date: January 23, 2015 Permit type: Fire | Permit status: Completed | Completion date: April 23, 2015 | Current use: Commercial | Permit id: Bld2015-00492 | |||||
Fire alarm installation Date: January 19, 2015 Permit type: Low voltage | Permit status: Corrections required | Completion date: January 27, 2015 | Current use: Commercial | Permit id: Bld2015-00352 | |||||
SCORE 64 Addition of conv outlets and light fixtures for the loading dock Date: January 16, 2015 Contractor: Hunt Electricoc Tanner Loading Dock Permit type: Electrical | Permit status: Closed | Completion date: February 25, 2015 | Current use: Commercial | Permit id: Bld2015-00322 | |||||
SCORE 64 Fire sprinklers Date: November 5, 2014 Permit type: Fire | Permit status: Inspections | Completion date: November 7, 2014 | Current use: Commercial | Permit id: Bld2014-08124 | |||||
SCORE 59 Electrical remodel & site Date: October 27, 2014 Contractor: Taylor Electricoc Tanner Wp 2 Permit type: Electrical | Permit status: Accepted | Completion date: October 27, 2014 | Current use: Commercial | Permit id: Bld2014-07800 | |||||
SCORE 74 Install (40) fixtures, (1) water heater, (1) distribution piping, (1) gas piping for remodel Date: September 26, 2014 Permit type: Plumbing | Permit status: Closed | Completion date: December 4, 2015 | Current use: Commercial | Permit id: Bld2014-07032 | |||||
SCORE 75 Temp service Date: August 14, 2014 Contractor: Taylor Electricoc Tanner Permit type: Electrical | Permit status: Inspections | Completion date: August 14, 2014 | Current use: Commercial | Permit id: Bld2014-05900 | |||||
SCORE 74 Plumbing permit Date: May 12, 2014 Permit type: Plumbing | Permit status: Closed | Completion date: September 26, 2014 | Current use: Commercial | Permit id: Bld2014-03217 | |||||
Refinery loading dock addition Date: May 7, 2014 Permit type: Permit | Permit status: Pass | Completion date: September 4, 2014 | Current use: Commercial | Permit id: Bld2014-03113 | |||||
SCORE 59 Electrical work for south west remodel Date: April 24, 2014 Contractor: Hunt Electricoc Tanner Wp 1 Permit type: Electrical | Permit status: Pass | Completion date: November 13, 2014 | Current use: Commercial | Permit id: Bld2014-02715 | |||||
SCORE 64 Fire sprinklers Date: April 15, 2014 Permit type: Fire | Permit status: Inspections | Completion date: May 15, 2014 | Current use: Commercial | Permit id: Bld2014-02450 | |||||
17,0 square feet single story plus mezzanine remodel. Date: April 11, 2014 Permit type: Permit | Permit status: Pass | Completion date: September 4, 2014 | Current use: Commercial | Permit id: Bld2014-02412 | |||||
Addition of sump to existing sewer system. Date: January 16, 2014 Permit type: Permit | Permit status: Completed | Completion date: March 18, 2014 | Current use: Commercial | Permit id: Bld2014-00312 | |||||
Southwest entry remodel & west loading dock remodel. Work package #1 of 2 Date: January 15, 2014 Permit type: Permit | Permit status: Pass | Completion date: September 4, 2014 | Current use: Commercial | Permit id: Bld2014-00260 | |||||
SCORE 64 Fire sprinklers for locker room remodel Date: November 29, 2012 Contractor: Quality Fire Protection Incoc Tanner Permit type: Fire | Permit status: No certificate req | Completion date: February 13, 2013 | Current use: Commercial | Permit id: Bld2012-08746 | |||||
SCORE 64 Hvac Date: November 27, 2012 Permit type: Mechanical | Permit status: Closed | Completion date: February 13, 2013 | Current use: Commercial | Permit id: Bld2012-08670 | |||||
SCORE 64 Electrical work, job bid: 8,000. 00 Date: November 27, 2012 Contractor: Red Peak Electric Incoc Tanner Permit type: Electrical | Permit status: Closed | Completion date: February 13, 2013 | Current use: Commercial | Permit id: Bld2012-08652 | |||||
SCORE 64 Locker room remodel d. D. Bp zone, locker room remodel, accessory use to principal office use a. S. Date: November 9, 2012 Contractor: Big Tree Construction Llcoc Tanner Permit type: Permit | Permit status: Completed | Completion date: February 13, 2013 | Current use: Commercial | Permit id: Bld2012-08346 | |||||
SCORE 64 Installation of grease interceptor on south end of the building. Date: October 12, 2012 Contractor: V.O.Brothers Mechanicalloc Tanner Permit type: Plumbing | Permit status: Closed | Completion date: October 15, 2012 | Current use: Commercial | Permit id: Bld2012-07567 | |||||
SCORE 64 Fire sprinklers for laquer finishing room. Date: August 31, 2012 Permit type: Fire | Permit status: Completed | Completion date: October 8, 2012 | Current use: Commercial | Permit id: Bld2012-06493 | |||||
Relocating laquer finishing room. Date: August 6, 2012 Permit type: Permit | Permit status: Certificate of completion | Completion date: October 8, 2012 | Current use: Commercial | Permit id: Bld2012-05752 | |||||
SCORE 75 Temporary use for a company event with a tent; approved by alan h Date: September 8, 2011 Contractor: Diamond Rentalsoc Tanner Permit type: Temporary use | Permit status: Completed | Completion date: September 9, 2011 | Permit id: Bld2011-05734 | |||||
SCORE 64 Temp use employee function (stage cover). Fire dept approval reqd Date: May 27, 2011 Contractor: Diamond Rentalo. C. Tanner Jewelry Co Permit type: Temporary use | Permit status: Closed | Completion date: May 27, 2011 | Permit id: Bld2011-03069 | |||||
SCORE 75 Temporary use for a company event with a tent; approved by alan h Date: September 21, 2009 Contractor: Diamond Rentalsoc Tanner Permit type: Temporary use | Permit status: No certificate req | Completion date: July 14, 2010 | Permit id: Bld2009-05692 | |||||
SCORE 82 Temp use, tent/canopy for employee function Date: May 26, 2009 Contractor: Diamond Rentaldiamond Rental Permit type: Temporary use | Permit status: No certificate req | Completion date: July 14, 2010 | Permit id: Bld2009-03067 | |||||
Interior remodel plus cut out and install 8 windows on exterior of building, patch exterior. Electrical permit required. Date: August 12, 2015 Permit status: Inspections | Current use: Commercial | Permit id: Bld2015-06325 | |||||
Refinery loading dock addition Date: July 7, 2014 Permit status: Inspections | Current use: Commercial | Permit id: Bld2014-03113 | |||||
Replacement of existing building envelope, landscaping and extended existing entrance lobby 725 sq ft Date: October 5, 2015 Permit status: Inspections | Current use: Commercial | Permit id: Bld2015-04779 | |||||
SCORE 61 17,0 square feet single story plus mezzanine remodel. Date: July 25, 2014 Contractor: Oc Tanner Southwest Remodelian Swinton Permit status: Inspections | Current use: Commercial | Permit id: Bld2014-02412 | |||||
SCORE 61 Glass replacement on exterior Date: September 8, 2015 Contractor: Officececila Uriburn Permit status: Inspections | Current use: Commercial | Permit id: Bld2015-07062 | |||||
SCORE 61 Southwest entry remodel & west loading dock remodel. Work package #1 of 2 Date: April 16, 2014 Contractor: Oc Tanner Southwest Remodelandrew Soderquist Permit status: Inspections | Current use: Commercial | Permit id: Bld2014-00260 | |||||
SCORE 61 Addition of sump to existing sewer system. Date: March 18, 2014 Contractor: O.C. Tanner Sewer Sump Additionandrew Soderquist Permit status: Inspections | Current use: Commercial | Permit id: Bld2014-00312 | |||||
Relocating laquer finishing room. Date: August 6, 2012 Permit status: Closed | Completion date: October 8, 2012 | Current use: Commercial | Permit id: Bld2012-05752 | |||||
SCORE 56 Basement employee restrooms / showers Date: November 9, 2012 Contractor: Ackerman Plumbing Inc.Oc Tanner Permit type: Plumbing | Permit status: Closed | Completion date: February 13, 2013 | Current use: Commercial | Permit id: Bld2012-08348 | |||||
Southwest entry remodel & west loading dock remodel. Work package #1 of 2 Date: January 15, 2014 Permit status: Inspections | Completion date: September 4, 2014 | Current use: Commercial | Permit id: Bld2014-00260 | |||||
Addition of sump to existing sewer system. Date: January 16, 2014 Permit status: Inspections | Completion date: March 18, 2014 | Current use: Commercial | Permit id: Bld2014-00312 | |||||
17,0 square feet single story plus mezzanine remodel. Date: April 11, 2014 Permit status: Inspections | Completion date: September 4, 2014 | Current use: Commercial | Permit id: Bld2014-02412 | |||||
SCORE 61 Electrical work for south west remodel Date: April 24, 2014 Contractor: Hunt Electricoc Tanner Wp #1 Permit type: Electrical | Permit status: Closed | Completion date: November 13, 2014 | Current use: Commercial | Permit id: Bld2014-02715 | |||||
SCORE 64 Electrical remodel & site Date: October 27, 2014 Contractor: Taylor Electricoc Tanner Wp#2 Permit type: Electrical | Permit status: Inspections | Completion date: October 27, 2014 | Current use: Commercial | Permit id: Bld2014-07800 | |||||
Fire alarm installation Date: January 19, 2015 Permit type: Low voltage | Permit status: In for review | Completion date: January 27, 2015 | Current use: Commercial | Permit id: Bld2015-00352 | |||||
Glass replacement on exterior Date: September 1, 2015 Permit status: Inspections | Completion date: September 8, 2015 | Current use: Commercial | Permit id: Bld2015-07062 | |||||
Basement employee restrooms / showers Date: November 9, 2012 Permit type: Plumbing | Permit status: No certificate req | Completion date: February 13, 2013 | Current use: Commercial | Permit id: Bld2012-08348 | |||||
SCORE 61 Date: September 8, 2015 Contractor: Officececila Uriburn Permit status: Inspections | Current use: Commercial | Permit id: Bld2015-07062 | |||||
SCORE 61 Date: March 18, 2014 Contractor: O.C. Tanner Sewer Sump Additionandrew Soderquist Permit status: Inspections | Current use: Commercial | Permit id: Bld2014-00312 | |||||
SCORE 64 Date: October 5, 2015 Contractor: Oc Tanner Reskinian Swinton Permit status: Inspections | Current use: Commercial | Permit id: Bld2015-04779 | |||||
SCORE 61 Oc tanner headquarters southwest remodel Date: July 25, 2014 Contractor: Oc Tanner Southwest Remodelian Swinton Permit status: Inspections | Current use: Commercial | Permit id: Bld2014-02412 | |||||
SCORE 64 Date: August 12, 2015 Contractor: Oc Tanner Reskinian Swinton Permit status: Inspections | Current use: Commercial | Permit id: Bld2015-06325 | |||||
SCORE 61 Date: April 16, 2014 Contractor: Oc Tanner Southwest Remodelandrew Soderquist Permit status: Inspections | Current use: Commercial | Permit id: Bld2014-00260 | |||||
SCORE 59 Refinery loading dock Date: July 7, 2014 Contractor: Oc Tanner Refinery Loading Dock Permit status: Inspections | Current use: Commercial | Permit id: Bld2014-03113 | |||||
SCORE 82 Temp use, tent canopy for employee function Date: May 26, 2009 Contractor: Diamond Rentaldiamond Rental Permit type: Temporary use | Permit status: Closed | Completion date: July 14, 2010 | Permit id: Bld2009-03067 | |||||
SCORE 75 Temporary use for a company event with a tent; approved by alan h Date: September 21, 2009 Contractor: Diamond Rentalsoc Tanner Permit type: Temporary use | Permit status: Closed | Completion date: July 14, 2010 | Permit id: Bld2009-05692 | |||||
SCORE 64 Temp use employee function (stage cover). Fire dept approval reqd Date: May 27, 2011 Contractor: Diamond Rentalo. C. Tanner Jewelry Co Permit type: Temporary use | Permit status: Closed | Completion date: May 27, 2011 | Permit id: Bld2011-03069 | |||||
SCORE 75 Temporary use for a company event with a tent; approved by alan h Date: September 8, 2011 Contractor: Diamond Rentalsoc Tanner Permit type: Temporary use | Permit status: Closed | Completion date: September 9, 2011 | Permit id: Bld2011-05734 | |||||
SCORE 59 Relocating laquer finishing room. Date: August 6, 2012 Permit status: Closed | Completion date: October 8, 2012 | Current use: Commercial | Permit id: Bld2012-05752 | |||||
SCORE 64 Fire sprinklers for laquer finishing room. Date: August 31, 2012 Permit type: Fire | Permit status: Closed | Completion date: October 8, 2012 | Current use: Commercial | Permit id: Bld2012-06493 | |||||
SCORE 64 Installation of grease interceptor on south end of the building. Date: October 12, 2012 Contractor: V.O.Brothers Mechanicalloc Tanner Permit type: Plumbing | Permit status: Closed | Completion date: October 15, 2012 | Current use: Commercial | Permit id: Bld2012-07567 | |||||
SCORE 64 Locker room remodel d. D. Bp zone, locker room remodel, accessory use to principal office use a. S. Date: November 9, 2012 Contractor: Big Tree Construction Llcoc Tanner Permit status: Closed | Completion date: February 13, 2013 | Current use: Commercial | Permit id: Bld2012-08346 | |||||
SCORE 59 Basement employee restrooms showers Date: November 9, 2012 Contractor: Ackerman Plumbing, Inc.Oc Tanner Permit type: Plumbing | Permit status: Closed | Completion date: February 13, 2013 | Current use: Commercial | Permit id: Bld2012-08348 | |||||
SCORE 64 Electrical work, job bid: 8,000. 00 Date: November 27, 2012 Contractor: Red Peak Electric Incoc Tanner Permit type: Electrical | Permit status: Closed | Completion date: February 13, 2013 | Current use: Commercial | Permit id: Bld2012-08652 | |||||
SCORE 64 Hvac Date: November 27, 2012 Permit type: Mechanical | Permit status: Closed | Completion date: February 13, 2013 | Current use: Commercial | Permit id: Bld2012-08670 | |||||
SCORE 64 Fire sprinklers for locker room remodel Date: November 29, 2012 Contractor: Quality Fire Protection Incoc Tanner Permit type: Fire | Permit status: Closed | Completion date: February 13, 2013 | Current use: Commercial | Permit id: Bld2012-08746 | |||||
SCORE 64 Southwest entry remodel & west loading dock remodel. Work package #1 of 2 Date: January 15, 2014 Permit status: Inspections | Completion date: September 4, 2014 | Current use: Commercial | Permit id: Bld2014-00260 | |||||
SCORE 59 Addition of sump to existing sewer system. Date: January 16, 2014 Permit status: Inspections | Completion date: March 18, 2014 | Current use: Commercial | Permit id: Bld2014-00312 | |||||
SCORE 64 17,0 square feet single story plus mezzanine remodel. Date: April 11, 2014 Permit status: Inspections | Completion date: September 4, 2014 | Current use: Commercial | Permit id: Bld2014-02412 | |||||
SCORE 64 Fire sprinklers Date: April 15, 2014 Permit type: Fire | Permit status: Inspections | Completion date: May 15, 2014 | Current use: Commercial | Permit id: Bld2014-02450 | |||||
SCORE 61 Electrical work for south west remodel Date: April 24, 2014 Contractor: Hunt Electricoc Tanner Wp #1 Permit type: Electrical | Permit status: Closed | Completion date: November 13, 2014 | Current use: Commercial | Permit id: Bld2014-02715 | |||||
SCORE 59 Refinery loading dock addition Date: May 7, 2014 Permit status: Inspections | Completion date: September 4, 2014 | Current use: Commercial | Permit id: Bld2014-03113 | |||||
SCORE 74 Plumbing permit Date: May 12, 2014 Permit type: Plumbing | Permit status: Closed | Completion date: September 26, 2014 | Current use: Commercial | Permit id: Bld2014-03217 | |||||
SCORE 75 Temp service Date: August 14, 2014 Contractor: Taylor Electricoc Tanner Permit type: Electrical | Permit status: Inspections | Completion date: August 14, 2014 | Current use: Commercial | Permit id: Bld2014-05900 | |||||
SCORE 74 Install (40) fixtures, (1) water heater, (1) distribution piping, (1) gas piping for remodel Date: September 26, 2014 Permit type: Plumbing | Permit status: Closed | Completion date: December 4, 2015 | Current use: Commercial | Permit id: Bld2014-07032 | |||||
SCORE 64 Electrical remodel & site Date: October 27, 2014 Contractor: Taylor Electricoc Tanner Wp#2 Permit type: Electrical | Permit status: Inspections | Completion date: October 27, 2014 | Current use: Commercial | Permit id: Bld2014-07800 | |||||
SCORE 64 Fire sprinklers Date: November 5, 2014 Permit type: Fire | Permit status: Inspections | Completion date: November 7, 2014 | Current use: Commercial | Permit id: Bld2014-08124 | |||||
SCORE 64 Addition of conv outlets and light fixtures for the loading dock Date: January 16, 2015 Contractor: Hunt Electricoc Tanner Loading Dock Permit type: Electrical | Permit status: Closed | Completion date: February 25, 2015 | Current use: Commercial | Permit id: Bld2015-00322 | |||||
SCORE 59 Fire alarm installation Date: January 19, 2015 Contractor: O.C. Tanner Sw Addition Wp#2 Permit type: Low voltage | Permit status: In for review | Completion date: January 27, 2015 | Current use: Commercial | Permit id: Bld2015-00352 | |||||
SCORE 100 Sprinklers Date: January 23, 2015 Contractor: Chaparral Fire Protection, Inc Permit type: Fire | Permit status: Inspections | Completion date: April 23, 2015 | Current use: Commercial | Permit id: Bld2015-00492 | |||||
SCORE 95 Flat sign Date: June 22, 2015 Contractor: Yesco Llc Permit type: Sign | Permit status: Inspections | Completion date: June 22, 2015 | Permit id: Bld2015-04489 | |||||
SCORE 64 Install 2 incinerators. Plans submitted for review. Plans on don davies desk for review and routing. Date: June 26, 2015 Contractor: Ffkr Architectsoc Tanner Dock Permit type: Mechanical | Permit status: In for review | Completion date: June 26, 2015 | Current use: Commercial | Permit id: Bld2015-04701 | |||||
SCORE 65 Replacement of existing building envelope, landscaping and extended existing entrance lobby 725 sq ft Date: June 29, 2015 Contractor: Bigd Construction Corp.Oc Tanner Reskin Permit status: Inspections | Completion date: October 5, 2015 | Current use: Commercial | Permit id: Bld2015-04779 | |||||
SCORE 65 Interior remodel plus cut out and install 8 windows on exterior of building, patch exterior. Electrical permit required. Date: August 10, 2015 Contractor: Bigd Construction Corp.Oc Tanner Reskin Permit status: Inspections | Completion date: August 12, 2015 | Current use: Commercial | Permit id: Bld2015-06325 | |||||
SCORE 62 Glass replacement on exterior Date: September 1, 2015 Contractor: Bigd Construction Corp.Office Permit status: Inspections | Completion date: September 8, 2015 | Current use: Commercial | Permit id: Bld2015-07062 |