Content | Date | Cost | Contractor Rank | Address | Contractor |
---|---|---|---|---|---|
Office t. I. Mech/elec/plmbg permits reqd t. B. A. H. Date: August 27, 2014 Permit type: Permit | Permit status: Pass | Completion date: January 29, 2015 | Current use: Commercial | Permit id: Bld2014-06212 | |||||
Provide and install (46) vav boxes along with associated ducting and grilles. Date: September 16, 2014 Permit type: Mechanical | Permit status: Pass | Completion date: January 29, 2015 | Current use: Commercial | Permit id: Bld2014-06759 | |||||
Fire sprinkler ti 13th floor Date: October 10, 2014 Permit type: Fire | Permit status: Pass | Completion date: January 27, 2015 | Current use: Commercial | Permit id: Bld2014-07392 | |||||
Tenat finish in existing building Date: October 17, 2014 Permit type: Electrical | Permit status: Pass | Completion date: January 26, 2015 | Current use: Commercial | Permit id: Bld2014-07604 | |||||
SCORE 66 Fire alarm installation and labor Date: October 7, 2014 Contractor: 185 S State Building Permit type: Low voltage | Permit status: Pass | Completion date: January 28, 2015 | Current use: Commercial | Permit id: Bld2014-07287 | |||||
Reconfigure bathrooms Date: October 8, 2014 Permit type: Plumbing | Permit status: Pass | Completion date: January 29, 2015 | Current use: Commercial | Permit id: Bld2014-07312 | |||||
Replace boiler, circulation pumps and add dampers Date: November 21, 2014 Permit type: Electrical | Permit status: Pass | Completion date: December 22, 2014 | Current use: Commercial | Permit id: Bld2014-08622 | |||||
SCORE 69 Remove one boiler and replace with new boiler. Modify existing hws and hws pipes. Install new supply air and exhaust fan on roof. Shaft of mechanical equipment shall not be modified. Date: November 21, 2014 Contractor: Designtek Consulting Group Llc Permit type: Permit | Permit status: In progress | Completion date: November 21, 2014 | Current use: Commercial | Permit id: Bld2014-08623 | |||||
SCORE 100 1-boiler, 1-gas line. Exhaust fan to be authorized by separate permit. Date: November 21, 2014 Contractor: Alternative Mechanical Contractors Inc Permit type: Mechanical | Permit status: Accepted | Completion date: November 21, 2014 | Current use: Commercial | Permit id: Bld2014-08624 | |||||
Installation of customer provided return fan, supply air fan, and louvers. Removal of existing boiler. Date: November 21, 2014 Permit type: Mechanical | Permit status: Pass | Completion date: December 30, 2014 | Current use: Commercial | Permit id: Bld2014-08626 | |||||
SCORE 64 Channel letters on existing monument k. B. Date: February 23, 2012 Contractor: Ig Group Llcchase Bank Sign Permit type: Sign | Permit status: In progress | Completion date: February 21, 2012 | Permit id: Bld2012-01439 | |||||
SCORE 64 Remove existing roofing system, new class "a" single ply roofing system, gaf system r1306 assembly #15 l. L. A. H. Date: August 29, 2011 Permit type: Roofing | Permit status: Pass | Completion date: December 27, 2011 | Current use: Commercial | Permit id: Bld2011-05466 | |||||
Install monument sign (reface), 2 canopy signs, & directionals. Atm & drive up indicator signs except. Date: November 4, 2010 Permit type: Sign | Permit status: Pass | Completion date: February 1, 2011 | Permit id: Bld2010-07668 | |||||
SCORE 64 Elec work for maintenance change out of existing hvac eqpmnt. Electrical feeders to eqpmnt will be relocated. Date: April 2, 2010 Permit type: Electrical | Permit status: Pass | Completion date: September 21, 2010 | Current use: Commercial | Permit id: Bld2010-01868 | |||||
Office remodel on the 7th flr. Must satisfy all pu requirements prior to completion. Date: July 9, 2009 Permit type: Permit | Permit status: Pass | Completion date: February 11, 2010 | Current use: Commercial | Permit id: Bld2009-04019 | |||||
SCORE 59 2 building signs, 2 store front sign Date: January 19, 2016 Contractor: Yesco Llcfj Management Permit type: Sign | Permit status: Closed | Completion date: June 21, 2016 | Permit id: Bld2016-00399 | |||||
Sprinklers Date: October 6, 2015 Permit type: Fire | Permit status: Closed | Completion date: February 19, 2016 | Current use: Commercial | Permit id: Bld2015-08225 | |||||
SCORE 100 Fire sprinkler permit for tab bank ti Date: June 9, 2016 Contractor: Hennessy Construction Inc Permit status: Inspections | Completion date: June 9, 2016 | Current use: Commercial | Permit id: Bld2016-05509 | |||||
8th, 9th, & 11th floor tenant remodel Date: August 17, 2015 Permit status: Closed | Completion date: March 8, 2016 | Current use: Commercial | Permit id: Bld2015-06561 | |||||
SCORE 59 Fire sprinkler permit for tab bank ti / mailed out 7-29-16 Date: June 22, 2016 Contractor: Firetrol Protection Systemstab Bank Permit type: Fire | Permit status: Inspections | Completion date: July 29, 2016 | Current use: Commercial | Permit id: Bld2016-05961 | |||||
Fire sprinkler ti 12th floor Date: October 10, 2014 Permit type: Fire | Permit status: Pass | Completion date: January 27, 2015 | Current use: Commercial | Permit id: Bld2014-07394 | |||||
Fire sprinkler ti basement Date: October 10, 2014 Permit type: Fire | Permit status: Pass | Completion date: January 27, 2015 | Current use: Commercial | Permit id: Bld2014-07395 | |||||
Fm-2 fire extinguishing system for fj management server room. (detection portion - low voltage permit) Date: November 21, 2014 Permit type: Low voltage | Permit status: Pass | Completion date: March 11, 2015 | Current use: Commercial | Permit id: Bld2014-08628 | |||||
Interior t. I. Remodel, elec permit reqd r. M. D-1 zone int work to remodel office a. S. Date: August 1, 2013 Permit type: Permit | Permit status: Pass | Completion date: August 7, 2013 | Current use: Commercial | Permit id: Bld2013-05405 | |||||
SCORE 100 Low voltage fire alarm. Date: March 24, 2010 Contractor: Fire Protection Services Permit type: Low voltage | Permit status: Pass | Completion date: July 15, 2011 | Current use: Commercial | Permit id: Bld2010-01627 | |||||
SCORE 66 Low voltage fire alarm. Date: March 24, 2010 Contractor: Fire Protection Servicesus Attorneys Office Permit type: Low voltage | Permit status: Pass | Completion date: July 6, 2010 | Current use: Commercial | Permit id: Bld2010-01626 | |||||
SCORE 66 Replace 1,999,0 btu boiler & 2 chillers (154 tons total) Date: February 11, 2010 Contractor: Ralph Tye And Sons Incsun Capitol Advisers Permit type: Mechanical | Permit status: Pass | Completion date: October 5, 2010 | Current use: Commercial | Permit id: Bld2010-00719 | |||||
SCORE 66 Install plumbing fixtures & 2 floor drains for remodel of 2nd floor restrooms and lobby. Date: February 3, 2010 Contractor: Ralph Broderick Plumbing185 S. State Permit type: Plumbing | Permit status: Pass | Completion date: April 21, 2010 | Current use: Commercial | Permit id: Bld2010-00555 | |||||
SCORE 66 Electrical work for remodel of 2nd floor restrooms and lobby. Date: January 25, 2010 Contractor: P B Construction Inc185 S. State Permit type: Electrical | Permit status: Pass | Completion date: March 15, 2010 | Current use: Commercial | Permit id: Bld2010-00366 | |||||
Remodel of 2nd floor restrooms and lobby. 2nd level restroom remodel & demolish existing walls. D-1 zone interior zone. K. A. Zone: a. S. Date: January 15, 2010 Permit type: Permit | Permit status: Pass | Completion date: April 16, 2010 | Current use: Commercial | Permit id: Bld2010-00211 | |||||
Modifications to existing fire sprinkler system for remodel Date: July 31, 2009 Permit type: Fire | Permit status: Completed | Completion date: August 28, 2009 | Current use: Commercial | Permit id: Bld2009-04524 | |||||
SCORE 66 Install 2 sinks, 1 water closet, & 1 floor drain on 7th flr Date: July 28, 2009 Contractor: Ralph Broderick Plumbingus Attorney Permit type: Plumbing | Permit status: Pass | Completion date: April 13, 2012 | Current use: Commercial | Permit id: Bld2009-04415 | |||||
SCORE 66 Elec work for office remodel on the 7th flr. Date: July 13, 2009 Contractor: P B Construction Incus Attorney Permit type: Electrical | Permit status: Pass | Completion date: July 10, 2012 | Current use: Commercial | Permit id: Bld2009-04088 | |||||
SCORE 66 2 vav boxes for office remodel on the 7th flr Date: July 13, 2009 Contractor: Southern Heating Corporationus Attorney Permit type: Mechanical | Permit status: Pass | Completion date: February 11, 2010 | Current use: Commercial | Permit id: Bld2009-04073 |