Content | Date | Cost | Contractor Rank | Address | Contractor |
---|---|---|---|---|---|
Mechanical permit Date: June 29, 2009 Client: Cbm Homeownership Zone Phase Iii 2 | Permit status: Completed | Permit id: 222338 | |||||
Plumbing permit Date: November 12, 2008 Client: Cbm Homeownership Zone Phase Iii 2 | Permit status: Completed | Permit id: 185965 | |||||
New construction permit Date: August 12, 2008 Client: Cbm Homeownership Zone Phase Iii 2 | Permit status: Completed | Permit id: 162516 | |||||
Zoning/use permit Date: April 15, 2008 Client: Cbm Homeownership Zone Phase Iii 2 | Permit status: Completed | Permit id: 142810 | |||||
Zoning permit Date: April 15, 2008 Client: Cbm Homeownership Zone Phase Iii 2 | Permit status: Completed | Permit id: 139314 | |||||
Electrical permit Date: February 25, 2009 Client: Cbm Homeownership Zone Phase Iii 2 | Permit status: Completed | Permit id: 200519 | |||||
Zoning use permit Date: April 15, 2008 Client: Cbm Homeownership Zone Phase Iii 2 | Permit status: Completed | Permit id: 142810 | |||||
Mechanical permit Date: June 29, 2009 Client: Cbm Homeownership Zone Phase Iii 2 | Permit status: Completed | Permit id: 222338 | |||||
Plumbing permit Date: November 17, 2008 Client: Cbm Homeownership Zone Phase Iii 2 | Permit status: Completed | Permit id: 188488 | |||||
New construction permit Date: August 12, 2008 Client: Cbm Homeownership Zone Phase Iii 2 | Permit status: Completed | Permit id: 162516 | |||||
Electrical permit Date: February 25, 2009 Client: Cbm Homeownership Zone Phase Iii 2 | Permit status: Completed | Permit id: 200519 | |||||
Zoning permit Date: April 15, 2008 Client: Cbm Homeownership Zone Phase Iii 2 | Permit status: Completed | Permit id: 139314 | |||||
Install carrier 25hbr3 heat pump and carrier fa4c0 air handler Date: June 29, 2009 Client: Cbm Homeownership Zone Phase Iii 2 | Permit type: Mechanical permit | Permit status: Completed | Completion date: November 27, 2009 | Permit id: 222338 | |||||
SCORE 100 Installation of a 200amp service, 41 general recepts, light fixtures, 25 switches, 5 smoke detectors as per 2005 nec (north district) Date: February 25, 2009 Contractor: Apex Electrical Svcs Llc Client: Cbm Homeownership Zone Phase Iii 2 | Permit type: Electrical permit | Permit status: Completed | Completion date: December 7, 2009 | Permit id: 200519 | |||||
SCORE 100 Install house trap,lateral and stormwater management Date: November 17, 2008 Contractor: Meco Constructors Inc Client: Cbm Homeownership Zone Phase Iii 2 | Permit type: Plumbing permit | Permit status: Completed | Completion date: November 27, 2009 | Permit id: 188488 | |||||
SCORE 96 First floor: water closet, lavatory, kitchen sink. Second floor: water closet, lavatory, tub. Date: November 12, 2008 Contractor: J Rihl Inc Client: Cbm Homeownership Zone Phase Iii 2 | Permit type: Plumbing permit | Permit status: Completed | Completion date: November 27, 2009 | Permit id: 185965 | |||||
Erect 2 sty. Single family dwelling with interior parking as per plans. Separate permits required for mechanical, electrical and plumbing. See ap#158422 for plans. Date: August 12, 2008 Client: Cbm Homeownership Zone Phase Iii 2 | Permit type: New construction permit | Permit status: Completed | Completion date: November 27, 2009 | Permit id: 162516 | |||||
Erection of a new semi-detached two (2) story structure maximum height not to exceed 35 feeet for use as a single family dwelling. Date: April 15, 2008 Client: Cbm Homeownership Zone Phase Iii 2 | Permit type: Zoning/use permit | Permit status: Completed | Completion date: July 14, 2008 | Permit id: 142810 | |||||
18 into 1 and then subdivide into 8 lots, all s. F. D`s, no basement cellar,1 interior acc garage. Date: April 15, 2008 Client: Cbm Homeownership Zone Phase Iii 2 | Permit type: Zoning permit | Permit status: Completed | Completion date: April 15, 2008 | Permit id: 139314 |